Permit Details

Status:
Complete
Type:
Commercial Building
Address:
5201 S 12TH AV
Address NEW:
5201 S 12TH AV
Apply Date:
10/12/2022
Applicant:
Description:
New Building

Permit Reviews

Permit Number - T22CM07804
Permit Status: Complete
Permit Description: New Building
Start Date Submittal Complete Date Status  
10/12/2022 COMMERCIAL - BLDG/FIRE/ZONING/ENG 10/12/2022 ACTIVE Review Details
07/18/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 07/18/2025 REQUIRES RESUBMIT Review Details
05/25/2023 COMMERCIAL REVIEW - FULL v.5 06/29/2023 REQUIRES RESUBMIT Review Details
07/22/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.2 07/24/2025 REQUIRES RESUBMIT Review Details
10/03/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 10/07/2025 APPROVED Review Details
12/22/2022 COMMERCIAL REVIEW - FULL v.2 01/17/2023 REQUIRES RESUBMIT Review Details
04/24/2023 COMMERCIAL REVIEW - FULL v.4 05/25/2023 REQUIRES RESUBMIT Review Details
07/25/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.3 07/25/2025 REQUIRES RESUBMIT Review Details
08/31/2023 COMMERCIAL REVIEW - FULL v.6 09/22/2023 REQUIRES RESUBMIT Review Details
10/08/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 10/13/2025 APPROVED Review Details
07/30/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.4 08/01/2025 APPROVED Review Details
02/16/2023 COMMERCIAL REVIEW - FULL v.3 03/15/2023 REQUIRES RESUBMIT Review Details
09/26/2023 COMMERCIAL REVIEW - FULL v.7 10/04/2023 APPROVED Review Details
10/28/2022 COMMERCIAL REVIEW - FULL v.1 11/25/2022 REQUIRES RESUBMIT Review Details
10/23/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 10/23/2024 APPROVED Review Details
10/04/2023 RESTAMP - COMMERCIAL v.1 10/17/2023 APPROVED Review Details

Conditions

Permit Number - T22CM07804
Permit Status: Complete
Permit Description: New Building
Date Description Comments
10/23/2024 AIR BALANCING REPORT IS REQUIRED.
10/12/2022 GENERAL CONTRACTOR LETTER (GCL) REQUIRD PRIOR TO ISSUANCE
10/23/2024 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
10/23/2024 COUNTY HEALTH INSPECTION IS REQUIRED - PLEASE PROVIDE DOCUMENTATION THAT THE INSPECTION HAS BEEN COMPLETED AND PASSED.
10/23/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
10/23/2024 SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED.
09/24/2024 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/
10/23/2024 SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED.
08/01/2025 SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED.
10/23/2024 WATER STERILIZATION REPORT IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: T22CM07804
Permite Description: New Building
Total Outstanding Inspections - 6
Last Inspection Date Description Inspector Results Comments
07/19/2024 COT - HCEL - Electrical Intermediate N/A Partial Pass 7/19/24: electrical in-wall at first floor per plan ok to proceed
05/20/2024 COT - HCBU - Masonry Pregrout N/A Partial Pass 2/14/24: reinforcement per plan first lift ok to grout @4ft
3/5/24 2nd lift ok for grout
3/21/24: 3rd lift ok for grout.
5/20/24: 4th lift ok to grout. Reinforcement at site wall per plans ok to proceed.
01/09/2024 COT - HCBU - Excavation/Rebar/Zoning N/A Partial Pass 1/9/24 partial for building exterior footers, interior to go
11/22/2024 COT - HCBU - Framing N/A Partial Pass 11/22/24: first floor framing passed.
12/17/2024 COT - HCBU - Building Progress N/A Partial Pass 12/17/24: drywall nailing passed ok to proceed.
11/04/2025 FCON – Fire – Intermediate N/A Not Applicable

Completed Inspections

Permit Status: Complete
Permit Number: T22CM07804
Permit Description: New Building
Total Completed Inspections - 36
Date Description Inspector Results Comments
02/02/2024 COT - HCPL - Rough Soil Passed 1/25/24: plumbing underground in building per plan ok to back fill. Shading required.
2/2/24: plumbing underground and sewer connection complete. Grease interceptor installed per plans and tested ok to proceed and backfill.
02/02/2024 COT - HCBU - Preslab Passed
08/02/2024 COT - HCPL - Gas Pressure Test Passed
11/26/2024 COT - HCPL - Plumbing Intermediate Passed OK to insulate and cover walls.
04/29/2025 BULD - Electrical Clearance Passed 4-29-25, panel is okay to be energized. ECO clearance sent to TEP.
07/11/2025 COT - HCBU - Building Above Ceiling Passed
07/11/2025 COT - HCPL - Plumbing Roof Drains Passed
07/11/2025 COT - LCME - Mechanical Above Ceiling Passed
07/11/2025 COT - HCEL - Electrical Above Ceiling Passed
07/11/2025 COT - HCBU - Exterior Clips/Sheathing Passed
07/22/2025 COT - BULD - SWG Clearance Passed 7/22/25: SWG CLEARANCE APPROVED
10/08/2025 COT - HCEL - Electrical Intermediate Passed
10/08/2025 COT - LCME - Mechanical Progress Passed
10/08/2025 COT - LCME - Kitchen Hood Passed
10/08/2025 COT - HCBU - Masonry Pregrout Passed
10/08/2025 COT - HCPL - Sewer Passed
10/08/2025 COT - HCBU - Excavation/Rebar/Zoning Passed
10/08/2025 COT - LCME - Mechanical Intermediate Passed
10/08/2025 COT - HCBU - Framing Passed
10/08/2025 COT - HCEL - Electrical Progress Passed
10/08/2025 COT - LCBU - Building Progress Passed
10/08/2025 COT - HCEL - Electrical Underground Passed
10/08/2025 COT - HCPL - Yard Water Line Passed
10/08/2025 COT - HCBU - Interior Shear Bracing Passed
10/08/2025 COT - HCBU - Building Progress Passed
10/22/2025 COT - HCPL - Gas Final Passed
10/31/2025 COT - LCBU - Building Final Passed
10/22/2025 COT - LCME - Mechanical Final Passed
10/31/2025 COT - HCBU - Building Final Passed
10/31/2025 COT - HCEL - Outdoor Lighting Passed
10/22/2025 COT - HCEL - Electrical Final Passed
10/28/2025 COT - FCON - Alarm - Final Passed
10/28/2025 COT - FCON - Fire - Final Passed
11/03/2025 ENGR Engineering Final Passed
11/04/2025 COT - FCON - Sprinkler - Final Passed
11/04/2025 COT - FCON - Hood System - Final Passed