Permit Reviews
Permit Number - T22CM07565
Permit Status: Complete
Permit Description: TI: MEDICAL OFFICE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/03/2022 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 10/18/2022 | ACTIVE |
| 03/01/2023 | COMMERCIAL REVIEW - FULL v.3 | 03/16/2023 | APPROVED |
| 12/19/2022 | COMMERCIAL REVIEW - FULL v.2 | 02/17/2023 | REQUIRES RESUBMIT |
| 01/09/2024 | COMMERCIAL REVIEW - FULL v.1 | 01/26/2024 | REQUIRES RESUBMIT |
| 10/28/2022 | COMMERCIAL REVIEW - FULL v.1 | 11/28/2022 | REQUIRES RESUBMIT |
| 08/06/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 08/08/2024 | APPROVED |
| 06/13/2023 | COMMERCIAL REVIEW - FULL v.1 | 06/13/2023 | REQUIRES RESUBMIT |
| 08/01/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 08/05/2024 | APPROVED |
| 02/27/2024 | RESTAMP - COMMERCIAL v.1 | 03/04/2024 | APPROVED |
| 01/29/2024 | COMMERCIAL REVIEW - FULL v.2 | 02/27/2024 | APPROVED |
| 06/14/2023 | COMMERCIAL REVIEW - FULL v.2 | 06/15/2023 | APPROVED |
Conditions
Permit Number - T22CM07565
Permit Status: Complete
Permit Description: TI: MEDICAL OFFICE
| Date | Description | Comments |
|---|---|---|
| 06/18/2024 | AIR BALANCING REPORT IS REQUIRED. | |
| 10/03/2022 | GENERAL CONTRACTOR LETTER (GCL) REQUIRED PRIOR TO ISSUANCE | |
| 06/18/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
| 06/18/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 06/18/2024 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. | |
| 06/18/2024 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. | |
| 06/18/2024 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. | |
| 06/18/2024 | SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED. | |
| 06/18/2024 | WATER STERILIZATION REPORT IS REQUIRED. | |
| 06/18/2024 | SPECIAL INSPECTION FOR WELD REINF STEEL IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM07565
Permite Description: TI: MEDICAL OFFICE
Total Outstanding Inspections - 6
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/21/2023 | COT - HCBU - Preslab | N/A | Canceled | |
| 10/20/2023 | COT - HCME - Mechanical Intermediate | N/A | Not Applicable | |
| 11/20/2023 | COT - HCBU - Building Above Ceiling | N/A | Re-inspection required | 11/20/23: complete the grid in the lobby, open elect boxes, holes in duct & missing straps, install registers, support flex duct off grid, move grid wires away from Fire Damper doors. NOTE: the lobby ceiling is required to be finished per approved plans before a TCO is issued. |
| 06/21/2023 | COT - HCEL - Electrical Intermediate | N/A | Partial Pass | 6-21-23: Walls except electrical room. |
| 12/22/2023 | BULD - Electrical Clearance | N/A | Not Applicable | Existing electric meter on shell building. No electrical clearance required. |
| 08/13/2024 | COT - FCON - Fire - Final | N/A | Not Applicable |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM07565
Permit Description: TI: MEDICAL OFFICE
Total Completed Inspections - 22
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/15/2023 | COT - HCPL - Rough Soil | Passed | ||
| 06/23/2023 | COT - HCPL - Plumbing Intermediate | Passed | ||
| 11/20/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Passed | ||
| 11/30/2023 | COT - HCBU - Building Progress | Passed | Recommend Level Two TCO. | |
| 11/30/2023 | COT - HCEL - Electrical Above Ceiling | Passed | ||
| 11/30/2023 | COT - HCME - Mechanical Above Ceiling | Passed | ||
| 11/30/2023 | COT - HCPL - Plumbing Progress | Passed | ||
| 12/01/2023 | COT - BULD - SWG Clearance | Passed | ||
| 12/04/2023 | COT - HCPL - Gas Pressure Test | Passed | ||
| 12/13/2023 | COT - HCBU - Building Above Ceiling | Passed | ||
| 12/22/2023 | COT - HCPL - Plumbing Above Ceiling | Passed | ||
| 12/22/2023 | COT - HCME - Mechanical Final | Passed | Construction is complete. Mechanical, electrical, and plumbing fixtures are installed and operational. Okay to issue a Level 4 Certificate of Occupancy. | |
| 12/22/2023 | COT - HCEL - Electrical Intermediate | Passed | 12/22/23: Fire Department has approved finals. ADA requirements are completed in restroom. Outlet has been removed under mop sink. | |
| 12/22/2023 | COT - HCBU - Framing | Passed | 12/22/23: Fire Department has approved finals. ADA requirements are completed in restroom. Outlet has been removed under mop sink. | |
| 12/22/2023 | COT - HCPL - Plumbing Final | Passed | Construction is complete. Mechanical, electrical, and plumbing fixtures are installed and operational. Okay to issue a Level 4 Certificate of Occupancy. | |
| 12/22/2023 | COT - HCEL - Electrical Final | Passed | Construction is complete. Mechanical, electrical, and plumbing fixtures are installed and operational. Okay to issue a Level 4 Certificate of Occupancy. | |
| 12/22/2023 | COT - HCBU - Interior Shear Bracing | Passed | 12-22-23: Plans don't show interior shear walls. Not required for inspection. | |
| 12/22/2023 | COT - HCBU - Building Final | Passed | Construction is complete. Mechanical, electrical, and plumbing fixtures are installed and operational. Okay to issue a Level 4 Certificate of Occupancy. | |
| 12/22/2023 | COT - HCEL - Electrical Progress | Passed | ||
| 12/22/2023 | COT - HCPL - Gas Final | Passed | ||
| 06/14/2024 | ENGR Engineering Final | Passed | ||
| 06/14/2024 | COT - HCME - Mechanical Progress | Passed |