Permit Number - T22CM06636
Permit Status: Issued
Permit Description: Accessory Dwelling Unit
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
08/26/2022 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 09/12/2022 | ACTIVE |
05/04/2023 | RESIDENTIAL NEW DWELLING v.3 | 06/07/2023 | APPROVED |
03/21/2023 | RESIDENTIAL NEW DWELLING v.2 | 04/28/2023 | REQUIRES RESUBMIT |
10/27/2022 | RESIDENTIAL NEW DWELLING v.1 | 12/08/2022 | REQUIRES RESUBMIT |
06/07/2023 | RESTAMP - RESIDENTIAL v.1 | 06/13/2023 | APPROVED |
Conditions
Permit Number - T22CM06636
Permit Status: Issued
Permit Description: Accessory Dwelling Unit
Date | Description | Comments |
---|---|---|
12/07/2022 | Unit number for proposed ADU is required. Email: Addressing@pima.govAddressing@pima.gov or 520-724-9512 | |
08/26/2022 | OWNER BUILDER AFFIDAVIT REQUIRED IF NOT RENTING GENERAL CONTRACTOR LETTER (GCL) NOT REQUIRED |
Outstanding Inspections
Permit Status: Issued
Permit Number: T22CM06636
Permite Description: Accessory Dwelling Unit
Total Outstanding Inspections - 2
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/06/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | N/A | Not Ready | |
11/06/2024 | RSBU - Building Final | N/A | Partial Pass | Need to install windows throughout. Ok to move in furniture and equipment. |
Completed Inspections
Permit Status: Issued
Permit Number: T22CM06636
Permit Description: Accessory Dwelling Unit
Total Completed Inspections - 18
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/30/2023 | COT - RSBU - Excavation/Rebar/Zoning | Passed | Footings for building and retaining walls. Ok to place concrete in progress areas. | |
12/06/2023 | COT - RSEL - Electrical Underground | Passed | ||
01/02/2024 | COT - RSPL - Rough Soil | Passed | Okay to back fill shading is required. 1/2/2024 | |
01/02/2024 | COT - RSPL - Sewer | Passed | Okay to back fill shading is required. 1/2/2024 | |
01/02/2024 | COT - RSPL - Yard Water Line | Passed | Okay to back fill shading is required. 1/2/2024 | |
05/21/2024 | COT - RSBU - Exterior Clips/Sheathing | Passed | Ok to finish coat (Elasto-metric coat) roof system | |
08/07/2024 | COT - RSBU - Roof Nailing | Passed | ||
08/23/2024 | COT - BULD - SWG Clearance | Passed | Clearance for Southwest Gas. 8/23/2024 | |
10/18/2024 | COT - RSPL - Plumbing Final | Passed | ||
10/22/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
10/22/2024 | COT - RSBU - Preslab | Passed | ||
10/22/2024 | COT - RSBU - Stem Wall/Retaining Wall | Passed | ||
10/22/2024 | COT - RSPL - Gas Pressure Test | Passed | ||
10/22/2024 | COT - RSEL - Grounding/Bonding | Passed | ||
10/22/2024 | COT - RSME - Mechanical Final | Passed | ||
11/06/2024 | BULD - Electrical Clearance | Passed | No electric clearance required. | |
11/06/2024 | COT - RSEL - Electrical Final | Passed | ||
11/06/2024 | COT - RSEL - Outdoor Lighting | Passed |