Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - RSBU - Stem Wall/Retaining Wall
Permit Number - T22CM06636
Inspection Description - COT - RSBU - Stem Wall/Retaining Wall
Inspection Status - Partial Pass
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/10/2024 | COT - RSBU - Stem Wall/Retaining Wall | Partial Pass | Partial approval for approx 30' retailer-wall along south property line, east to west | |
02/13/2024 | COT - RSBU - Stem Wall/Retaining Wall | Partial Pass | ADU Avic block system at 0’ - 9’, OK to.grout,progress,areas. | |
03/07/2024 | COT - RSBU - Stem Wall/Retaining Wall | Partial Pass | All rebar reinforcement in place, walls topped out at 12’. Ok to grout progress areas. | |
08/02/2024 | COT - RSBU - Stem Wall/Retaining Wall | Passed | Footings for East side stem wall. Ok to place concrete in progress areas. | |
08/07/2024 | COT - RSBU - Stem Wall/Retaining Wall | Passed | Ok to place concrete in progress areas. | |
10/22/2024 | COT - RSBU - Stem Wall/Retaining Wall | Passed | ||
11/21/2023 | COT - RSBU - Stem Wall/Retaining Wall | Partial Pass | 11/21/23:reinforcement per plan ok to grout first lift at 32" at 900 SQ FT ADU. | |
12/13/2023 | COT - RSBU - Stem Wall/Retaining Wall | Partial Pass | Footing for bench and wall baring footer rebar per plans. okay for concrete placement in footing. 12/13/2023 |