Permit: T22CM06464
Permit Details
Status:
Inspections
Type:
Residential Building - One or Two Family
Address:
8431 E SHILOH ST
Address NEW:
8431 E SHILOH ST
Apply Date:
08/22/2022
Applicant:
John Abbott
Description:
R-(T21DV07978) Fire Repair
Permit Reviews
Permit Number - T22CM06464
Permit Status: Inspections
Permit Description: R-(T21DV07978) Fire Repair
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/22/2022 | RESIDENTIAL - BLDG/WWM | 09/12/2022 | COMPLETED |
| 08/01/2023 | RESIDENTIAL NEW DWELLING v.2 | 08/01/2023 | REQUIRES RESUBMIT |
| 08/10/2023 | RESIDENTIAL NEW DWELLING v.3 | 08/14/2023 | APPROVED |
| 08/14/2023 | RESTAMP - RESIDENTIAL v.1 | 08/14/2023 | APPROVED |
| 12/20/2022 | RESIDENTIAL NEW DWELLING v.1 | 01/06/2023 | REQUIRES RESUBMIT |
Outstanding Inspections
Permit Status: Inspections
Permit Number: T22CM06464
Permite Description: R-(T21DV07978) Fire Repair
Total Outstanding Inspections - 5
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/14/2024 | COT - RSBU - Excavation/Rebar/Zoning | N/A | Not Applicable | |
| 10/14/2024 | COT - RSEL - Grounding/Bonding | N/A | Re-inspection required | 10/14/24: new panel needs to be grounded. |
| 10/14/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | N/A | Re-inspection required | 10/14/24: top plate penetrations need to be sealed. Registers have to be blocked on three sides. Pex needs to be under test. Fur out walls need to be fire blocked every ten feet. Electrical wiring in furout walls need to be protected with metal sheathing. Stopped inspection |
| 10/14/2024 | BULD - Electrical Clearance | N/A | Re-inspection required | 10/14/24: new panel needs to be grounded. |
| 10/15/2024 | COT - BULD - SWG Clearance | N/A | Not Ready |
Completed Inspections
Permit Status: Inspections
Permit Number: T22CM06464
Permit Description: R-(T21DV07978) Fire Repair
Total Completed Inspections - 8
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/15/2024 | COT - RSPL - Gas Pressure Test | Passed | ||
| 12/31/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 12/31/24 corrections have been made. | |
| 03/25/2025 | BULD - Electrical Clearance | Passed | ||
| 06/25/2025 | COT - BULD - SWG Clearance | Passed | 6/25/25 passed CLEARANCE SWG | |
| 07/11/2025 | COT - RSME - Mechanical Final | Passed | 7/11/25 corrections made | |
| 07/11/2025 | RSBU - Building Final | Passed | 7/11/25 corrections made | |
| 07/11/2025 | COT - RSPL - Plumbing Final | Passed | 7/11/25 corrections made | |
| 07/11/2025 | COT - RSEL - Electrical Final | Passed | 7/11/25 corrections made |