Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T22CM05743
Permit Details
Apply Date:
07/28/2022
Applicant:
Jonathan Renfroe
Description:
Construction of New Tractor Supply Store
Permit Reviews
Permit Number - T22CM05743
Permit Status: Complete
Permit Description: Construction of New Tractor Supply Store
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
07/28/2022 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 08/31/2022 | COMPLETED |
10/18/2022 | RESUBMITTAL | 10/18/2022 | ACTIVE |
11/28/2023 | COMMERCIAL REVIEW - FULL v.3 | 12/21/2023 | REQUIRES RESUBMIT |
10/28/2022 | COMMERCIAL REVIEW - FULL v.1 | 11/10/2022 | REQUIRES RESUBMIT |
11/24/2023 | COMMERCIAL REVIEW - FULL v.2 | 11/24/2023 | REQUIRES RESUBMIT |
01/29/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 01/30/2024 | APPROVED |
11/23/2022 | COMMERCIAL REVIEW - FULL v.2 | 01/26/2023 | APPROVED |
01/12/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 01/12/2024 | APPROVED |
07/25/2023 | COMMERCIAL REVIEW - FULL v.1 | 07/28/2023 | APPROVED |
11/14/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 11/14/2023 | APPROVED |
11/22/2023 | COMMERCIAL REVIEW - FULL v.1 | 11/22/2023 | REQUIRES RESUBMIT |
08/24/2023 | COMMERCIAL REVIEW - FULL v.1 | 09/06/2023 | APPROVED |
03/23/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 03/29/2023 | REQUIRES RESUBMIT |
04/19/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 04/24/2023 | APPROVED |
Conditions
Permit Number - T22CM05743
Permit Status: Complete
Permit Description: Construction of New Tractor Supply Store
Date | Description | Comments |
---|---|---|
11/09/2022 | AIR BALANCING/COMMISSIONING REPORT IS REQUIRED. | |
11/09/2022 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
01/26/2023 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. | |
11/09/2022 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
11/09/2022 | SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED. | |
11/09/2022 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
11/09/2022 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. | |
11/09/2022 | SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED. | |
11/09/2022 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. | |
11/09/2022 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM05743
Permite Description: Construction of New Tractor Supply Store
Total Outstanding Inspections - 11
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/31/2023 | COT - HCPL - Plumbing Progress | N/A | Not Applicable | 5/31/23: James called to cancel sewer inspection, Pima County has jurisdiction. |
07/19/2023 | COT - HCEL - Electrical Underground | N/A | Re-inspection required | |
09/25/2023 | COT - HCEL - Electrical Progress | N/A | Not Applicable | 9/25/23: COT does not inspect the pad or foundations that will support transformers. |
09/18/2023 | COT - HCBU - Building Above Ceiling | N/A | Re-inspection required | 9/18/23: ceiling grid required to be installed for above ceiling inspection. The grid ceiling and ALL trades are inspected at one time. |
09/06/2023 | COT - HCBU - Building Progress | N/A | Partial Pass | 6-16-23: Pre-slab inside. 8/23/23: 145 L/F sidewalk on west side of building. Outdoor display area. 9/6/23: sidewalk at northwest area of building . |
10/03/2023 | COT - HCEL - Electrical Above Ceiling | N/A | Not Ready | |
07/06/2023 | COT - HCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | 7-6-23: FOD area. |
COT - FCON - Sprinkler - Final | N/A | Not Ready | ||
COT - FCON - Alarm - Final | N/A | Not Ready | ||
12/15/2023 | ENGR Engineering Final | N/A | Partial Pass | This site is approved for level 4 Occupancy for TCO at this time |
12/14/2023 | COT - FCON - Fire - Final | N/A | Partial Pass | Need operational permit for propane tank. |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM05743
Permit Description: Construction of New Tractor Supply Store
Total Completed Inspections - 33
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/08/2023 | COT - HCPL - Backwater Valve | Passed | 8/8/23: tested at 85 psi hydro | |
08/09/2023 | COT - HCEL - Electrical Intermediate | Passed | 8/9/23: all rooms. | |
08/09/2023 | COT - HCPL - Plumbing Intermediate | Passed | ||
09/13/2023 | COT - HCEL - Electrical Underground | Passed | ||
10/10/2023 | COT - HCBU - Building Above Ceiling | Passed | ||
10/12/2023 | COT - HCPL - Gas Final | Passed | ||
11/02/2023 | COT - HCME - Mechanical Progress | Passed | ||
11/15/2023 | COT - HCBU - Roof Nailing | Passed | ||
11/15/2023 | COT - HCBU - Framing | Passed | ||
11/15/2023 | COT - HCBU - Interior Shear Bracing | Passed | ||
11/15/2023 | COT - HCPL - Gas Pressure Test | Passed | ||
11/15/2023 | COT - HCPL - Plumbing Above Ceiling | Passed | ||
11/15/2023 | COT - HCPL - Sewer | Passed | ||
11/15/2023 | COT - HCME - Mechanical Intermediate | Passed | ||
11/15/2023 | COT - HCME - Mechanical Above Ceiling | Passed | ||
11/15/2023 | COT - HCBU - Stem Wall/Retaining Wall | Passed | ||
11/15/2023 | COT - HCBU - Masonry Pregrout | Passed | ||
11/15/2023 | COT - HCPL - Rough Soil | Passed | ||
11/15/2023 | COT - HCBU - Building Progress | Passed | ||
11/15/2023 | COT - HCEL - Electrical Above Ceiling | Passed | ||
12/13/2023 | COT - HCME - Mechanical Final | Passed | 12-13-23: Okay for a TCO Level 4. Project is complete, with mechanical, electrical, and plumbing fixtures installed and operational. | |
12/13/2023 | COT - HCBU - Building Final | Passed | 12-13-23: Okay for a TCO Level 4. Project is complete, with mechanical, electrical, and plumbing fixtures installed and operational. | |
12/13/2023 | COT - HCBU - Excavation/Rebar/Zoning | Passed | 12-13-23: All footing are completed. | |
12/13/2023 | COT - HCEL - Outdoor Lighting | Passed | Passed parking lot lights are installed and operational. Building lights are installed and operational. | |
12/13/2023 | COT - HCBU - Preslab | Passed | All concrete slabs have been approved and poured. | |
12/13/2023 | COT - HCPL - Plumbing Final | Passed | 12-13-23: Okay for a TCO Level 4. Project is complete, with mechanical, electrical, and plumbing fixtures installed and operational. | |
12/13/2023 | COT - HCEL - Electrical Final | Passed | 12-13-23: Okay for a TCO Level 4. Project is complete, with mechanical, electrical, and plumbing fixtures installed and operational. | |
12/13/2023 | COT - FCON - Sprinkler - Final | Passed | ||
12/14/2023 | COT - FCON - Alarm - Final | Passed | ||
12/13/2023 | COT - BULD - SWG Clearance | Passed | Passed on 11-8-23 by Thomas Lundberg. SWG has installed meter and turned gas on to building. | |
12/13/2023 | BULD - Electrical Clearance | Passed | Passed by Thomas Lundberg on 11-3-23. TEP has installed meters and powered up building. | |
01/11/2024 | ENGR Engineering Final | Passed | ||
01/30/2024 | COT - FCON - Fire - Final | Passed |