Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T22CM05743

Parcel: 141185400


Addresses:

9848 E OLD VAIL RD


Inspection Status: Not Ready

Inspection History: COT - HCBU - Excavation/Rebar/Zoning 

Permit Number - T22CM05743

Inspection Description - COT - HCBU - Excavation/Rebar/Zoning 

Inspection Status - Not Ready

Date Description Inspector Results Comments
02/22/2023 COT - HCBU - Excavation/Rebar/Zoning  Not Ready This inspection was called without contractor verifying work was ready.
02/27/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 8 interior footings are approved to pour
03/01/2023 COT - HCBU - Excavation/Rebar/Zoning  Canceled Contractor texted to say cancel the inspection today, not ready
03/02/2023 COT - HCBU - Excavation/Rebar/Zoning  Canceled Contractor texted to say cancel the inspection today, not ready.
March 2nd: Joe called to cancel due to weather conditions.
03/06/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Contractor texted to say cancel the inspection today, not ready.
March 2nd: Joe called to cancel due to weather conditions.

March 6th: Partial for entire perimeter footing
05/09/2023 COT - HCBU - Excavation/Rebar/Zoning  Re-inspection required 5/9/23: storage shed footing reinforcing not per schedule.
05/17/2023 COT - HCBU - Excavation/Rebar/Zoning  Re-inspection required 5/9/23: storage shed footing reinforcing not per schedule.
5/17/23: reinforcing for 6 large footings at storage shed not in place. Approved plans not on site for round column footings at east side of main building
05/18/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 5/9/23: storage shed footing reinforcing not per schedule.
5/17/23: reinforcing for 6 large footings at storage shed not in place. Approved plans not on site for round column footings at east side of main building
5/18/23: 6 footings for Forage Shed approved to pour
05/24/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 5/9/23: storage shed footing reinforcing not per schedule.
5/17/23: reinforcing for 6 large footings at storage shed not in place. Approved plans not on site for round column footings at east side of main building
5/18/23: 6 footings for Forage Shed approved to pour
5/24/23: 20 pier footing for green house on east side of building approved to pour.
06/09/2023 COT - HCBU - Excavation/Rebar/Zoning  Re-inspection required 5/9/23: storage shed footing reinforcing not per schedule.
5/17/23: reinforcing for 6 large footings at storage shed not in place. Approved plans not on site for round column footings at east side of main building
5/18/23: 6 footings for Forage Shed approved to pour

5/24/23: 20 pier footing for green house on east side of building approved to pour.

6/9/23: 7 light pole bases not ready for inspection. Install 3 spacer wheels at mid-point of hole, maintain min 3" clearance of earth to reinforcing on all sides, install UFER ground.
06/13/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 5/9/23: storage shed footing reinforcing not per schedule.
5/17/23: reinforcing for 6 large footings at storage shed not in place. Approved plans not on site for round column footings at east side of main building
5/18/23: 6 footings for Forage Shed approved to pour

5/24/23: 20 pier footing for green house on east side of building approved to pour.

6/9/23: 7 light pole bases not ready for inspection. Install 3 spacer wheels at mid-point of hole, maintain min 3" clearance of earth to reinforcing on all sides, install UFER ground.

6/13/23: 7 light pole bases are approved to pour.
06/16/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 6-16-23: Pre-slab inside.
07/06/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 7-6-23: FOD area.
08/08/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 5/9/23: storage shed footing reinforcing not per schedule.
5/17/23: reinforcing for 6 large footings at storage shed not in place. Approved plans not on site for round column footings at east side of main building
5/18/23: 6 footings for Forage Shed approved to pour

5/24/23: 20 pier footing for green house on east side of building approved to pour.

6/9/23: 7 light pole bases not ready for inspection. Install 3 spacer wheels at mid-point of hole, maintain min 3" clearance of earth to reinforcing on all sides, install UFER ground.

6/13/23: 7 light pole bases are approved to pour.

6-16-23: Pre-slab inside.

7-6-23: FOD area.
8/8/23: pad on south side of building OK to pour.
11/15/2023 COT - HCBU - Excavation/Rebar/Zoning  Passed
12/13/2023 COT - HCBU - Excavation/Rebar/Zoning  Passed 12-13-23: All footing are completed.