Permit: T22CM05391
Permit Details
Status:
Inspections
Type:
Residential Building - One or Two Family
Address:
9151 E MAGDALENA RD
Address NEW:
9151 E MAGDALENA RD
Apply Date:
07/15/2022
Applicant:
Description:
SFR within Engineered Building
Permit Reviews
Permit Number - T22CM05391
Permit Status: Inspections
Permit Description: SFR within Engineered Building
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/15/2022 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 08/15/2022 | COMPLETED |
| 12/13/2022 | RESIDENTIAL NEW DWELLING v.1 | 01/10/2023 | REQUIRES RESUBMIT |
| 02/16/2023 | RESIDENTIAL NEW DWELLING v.2 | 03/03/2023 | REQUIRES RESUBMIT |
| 05/01/2023 | RESTAMP - RESIDENTIAL v.1 | 05/02/2023 | APPROVED |
| 03/03/2023 | RESIDENTIAL NEW DWELLING v.3 | 03/22/2023 | REQUIRES RESUBMIT |
| 03/27/2023 | RESIDENTIAL NEW DWELLING v.4 | 04/18/2023 | APPROVED |
Conditions
Permit Number - T22CM05391
Permit Status: Inspections
Permit Description: SFR within Engineered Building
| Date | Description | Comments |
|---|---|---|
| 04/18/2023 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/integrated-planning/PDSD/PDSD_Owner_Builder_Affidavit.pdf, is required prior to issuance of permit. |
Outstanding Inspections
Permit Status: Inspections
Permit Number: T22CM05391
Permite Description: SFR within Engineered Building
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/14/2023 | COT - RSBU - Stem Wall/Retaining Wall | N/A | Partial Pass | Retaining wall all around building rebar per plan okay for grout 1st lift. 11/14/2023 |
| 01/02/2024 | COT - RSBU - Interior Shear Bracing | N/A | Partial Pass | 1/2/23: sheathing nailing per schedule at north and east exterior walls first floor. |
| COT - FCON - Sprinkler - Final | N/A | Not Ready | Sub contractor shall request inspection. |
Completed Inspections
Permit Status: Inspections
Permit Number: T22CM05391
Permit Description: SFR within Engineered Building
Total Completed Inspections - 21
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/31/2023 | COT - RSEL - Grounding/Bonding | Passed | ||
| 05/31/2023 | COT - RSPL - Rough Soil | Passed | ||
| 06/14/2023 | COT - RSPL - Sewer | Passed | ||
| 11/14/2023 | COT - RSBU - Preslab | Passed | 11/14/2023 remainder of 12' footing for retaining wall. West end of building, okay for concrete placement. | |
| 01/02/2024 | COT - RSBU - Stem Wall/Retaining Wall | Passed | Retaining wall all around building rebar per plan okay for grout 1st lift. 11/14/2023 1/2/23: Retaining wall all around building has reinforcement per plan ok to grout and cap. |
|
| 01/24/2024 | COT - RSBU - Interior Shear Bracing | Passed | ||
| 01/31/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
| 02/22/2024 | COT - RSBU - Roof Nailing | Passed | ||
| 02/22/2024 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | ||
| 04/02/2024 | COT - RSPL - Yard Water Line | Passed | ||
| 04/02/2024 | COT - RSEL - Electrical Underground | Passed | ||
| 04/17/2024 | BULD - Electrical Clearance | Passed | ||
| 07/09/2024 | RSBU - Building Progress | Passed | ||
| 07/16/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
| 09/10/2024 | COT - RSPL - Gas Pressure Test | Passed | ||
| 09/18/2024 | COT - BULD - SWG Clearance | Passed | ||
| 09/19/2024 | COT - RSEL - Outdoor Lighting | Passed | ||
| 10/18/2024 | COT - RSME - Mechanical Final | Passed | Construction is complete per plan. Okay to issue Certificate of Completion. | |
| 10/18/2024 | RSBU - Building Final | Passed | Construction is complete per plan. Okay to issue Certificate of Completion. | |
| 10/18/2024 | COT - RSPL - Plumbing Final | Passed | Construction is complete per plan. Okay to issue Certificate of Completion. | |
| 10/18/2024 | COT - RSEL - Electrical Final | Passed | Construction is complete per plan. Okay to issue Certificate of Completion. |