Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Partial Pass
Inspection History: COT - RSBU - Interior Shear Bracing
| Date |
Description |
Inspector |
Results |
Comments |
| 01/02/2024 |
COT - RSBU - Interior Shear Bracing |
|
Partial Pass |
1/2/23: sheathing nailing per schedule at north and east exterior walls first floor. |
| 01/02/2024 |
COT - RSBU - Interior Shear Bracing |
|
Partial Pass |
1/2/23: sheathing nailing per schedule at north and east exterior walls first floor. |
| 01/12/2024 |
COT - RSBU - Interior Shear Bracing |
|
Passed |
1/12/24: Sheathing nailing is per plan on the west side 2nd floor exterior wall. TJI floor joists are installed per plan, 3/4" T&G plywood is being installed for 2nd floor. |
| 01/24/2024 |
COT - RSBU - Interior Shear Bracing |
|
Passed |
|