Permit: T22CM05355
Permit Details
Apply Date:
07/14/2022
Applicant:
Daria Hopkins
Description:
SFR 235.2960 T21-M0055
Permit Reviews
Permit Number - T22CM05355
Permit Status: Complete
Permit Description: SFR 235.2960 T21-M0055
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
07/14/2022 | OTHER | 08/08/2022 | COMPLETED |
03/05/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 03/15/2024 | APPROVED |
02/12/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 02/13/2024 | REQUIRES RESUBMIT |
Conditions
Permit Number - T22CM05355
Permit Status: Complete
Permit Description: SFR 235.2960 T21-M0055
Date | Description | Comments |
---|---|---|
07/14/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. | |
07/14/2022 | ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I) | |
07/14/2022 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
02/13/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
04/08/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
03/21/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. | |
03/07/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM05355
Permite Description: SFR 235.2960 T21-M0055
Total Outstanding Inspections - 7
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/11/2023 | COT - RSPL - Sewer | N/A | Not Ready | not ready |
04/12/2023 | COT - RSPL - Rough Soil | N/A | Not Ready | Not ready. Rocky soils remove all culichi. Stacks are to be filled to top. 4/12/2023 |
04/12/2023 | COT - RSPL - Yard Water Line | N/A | Not Ready | |
06/05/2023 | COT - LCPL - Plumbing Intermediate | N/A | Not Ready | 6-5-23: 1-Complete powder room electrical/ Mechanical/Plumbing. 2-Complete fire blocking at dead space upstairs. 3- Seal all fire locking. Inspection stopped; walk for check compliance/ completeness before rescheduling. |
06/05/2023 | COT - RSPL - Gas Pressure Test | N/A | Not Ready | 6-5-23: 1-Complete powder room electrical/ Mechanical/Plumbing. 2-Complete fire blocking at dead space upstairs. 3- Seal all fire locking. Inspection stopped; walk for check compliance/ completeness before rescheduling. |
06/05/2023 | COT - LCBU - Framing | N/A | Not Ready | 6-5-23: 1-Complete powder room electrical/ Mechanical/Plumbing. 2-Complete fire blocking at dead space upstairs. 3- Seal all fire locking. Inspection stopped; walk for check compliance/ completeness before rescheduling. |
06/05/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | N/A | Not Ready | 6-5-23: 1-Complete powder room electrical/ Mechanical/Plumbing. 2-Complete fire blocking at dead space upstairs. 3- Seal all fire locking. Inspection stopped; walk for check compliance/ completeness before rescheduling. |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM05355
Permit Description: SFR 235.2960 T21-M0055
Total Completed Inspections - 23
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/13/2023 | COT - RSPL - Rough Soil | Passed | ||
04/13/2023 | COT - RSPL - Yard Water Line | Passed | ||
04/26/2023 | COT - RSBU - Preslab | Passed | Post tension cables are in place with chairs holding them up above ground. Shear bracing is installed with rebar reinforcement. Ufer ground is in place. Okay to pour concrete. | |
04/26/2023 | COT - RSEL - Electrical Underground | Passed | Underground electrical for kitchen island installed. | |
04/26/2023 | COT - RSEL - Grounding/Bonding | Passed | Ufer ground in place. | |
04/26/2023 | COT - RSBU - Excavation/Rebar/Zoning | Passed | Post tension cables are in place with chairs holding them up above ground. Shear bracing is installed with rebar reinforcement. Ufer ground is in place. | |
05/05/2023 | COT - RSBU - Roof Nailing | Passed | ||
05/10/2023 | COT - RSBU - Exterior Clips/Sheathing | Passed | ||
06/05/2023 | COT - RSEL - Construction Power | Passed | ||
06/21/2023 | COT - LCPL - Plumbing Intermediate | Passed | ||
06/21/2023 | COT - RSPL - Gas Pressure Test | Passed | ||
06/21/2023 | COT - LCBU - Framing | Passed | ||
06/21/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
07/05/2023 | COT - HCBU - Interior Shear Bracing | Passed | ||
08/25/2023 | BULD - Electrical Clearance | Passed | resent clearance that was approved on 6/5/2023 | |
09/06/2023 | COT - BULD - SWG Clearance | Passed | ||
09/06/2023 | COT - RSPL - Plumbing Final | Passed | ||
09/12/2023 | COT - RSME - Mechanical Final | Passed | ||
09/12/2023 | ENGR Engineering Final | Passed | ||
09/12/2023 | RSBU - Building Final | Passed | ||
09/12/2023 | RSME - Mechanical Progress | Passed | ||
09/12/2023 | COT - RSEL - Outdoor Lighting | Passed | ||
09/12/2023 | COT - RSEL - Electrical Final | Passed |