Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T22CM04808
Permit Details
Apply Date:
06/24/2022
Applicant:
Philip Carhuff
Description:
NEW GROUND UP 2,285 S.F. (+ 874 S.F. OF ROOF OVERHANG) DONUT SHOP W/ ASSOCIATED PARKING, DRIVE THRU
Permit Reviews
Permit Number - T22CM04808
Permit Status: Complete
Permit Description: NEW GROUND UP 2,285 S.F. (+ 874 S.F. OF ROOF OVERHANG) DONUT SHOP W/ ASSOCIATED PARKING, DRIVE THRU
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/24/2022 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 08/24/2022 | COMPLETED |
09/15/2022 | RESUBMITTAL | 10/11/2022 | COMPLETED |
11/22/2022 | COMMERCIAL REVIEW - FULL v.1 | 12/29/2022 | REQUIRES RESUBMIT |
11/07/2022 | COMMERCIAL REVIEW - FULL v.1 | 11/22/2022 | APPROVED |
01/09/2023 | COMMERCIAL REVIEW - FULL v.2 | 01/19/2023 | APPROVED |
Conditions
Permit Number - T22CM04808
Permit Status: Complete
Permit Description: NEW GROUND UP 2,285 S.F. (+ 874 S.F. OF ROOF OVERHANG) DONUT SHOP W/ ASSOCIATED PARKING, DRIVE THRU
Date | Description | Comments |
---|---|---|
09/26/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. | |
09/26/2022 | SPECIAL INSPECTION FOR CONCRETE IS REQUIRED.. | |
09/26/2022 | SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED. | |
09/26/2022 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. | |
09/26/2022 | SPECIAL INSPECTION IS REQUIRED - AIR BALANCE REPORT REQUIRED PRIOR TO FINAL INSPECTION. | |
11/13/2023 | COUNTY HEALTH INSPECTION IS REQUIRED - PLEASE PROVIDE DOCUMENTATION THAT THE INSPECTION HAS BEEN COMPLETED AND PASSED. | |
11/13/2023 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM04808
Permite Description: NEW GROUND UP 2,285 S.F. (+ 874 S.F. OF ROOF OVERHANG) DONUT SHOP W/ ASSOCIATED PARKING, DRIVE THRU
Total Outstanding Inspections - 9
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/21/2023 | COT - LCBU - Masonry Pregrout | N/A | Not Applicable | The contractor called this inspection in for the trash enclosure, which is incorrect. This inspection needs to be done on the development package and will be done accordingly for today. The structure footer and walls have been constructed at this time, but have not been inspected by engineering. This inspection will have to be performed by the engineer of record, and he will need to provide us with a certification, letter stamp, and sealed stating that the structure has been built according to the approved plans. Canyon has been advised to provide us with his documentation, and to let his special inspector witness the grouting of the walls. |
08/18/2023 | COT - HCBU - Interior Shear Bracing | N/A | Re-inspection required | 8/18/23: not ready for inspection. Maintain minimum 3/8" from edge of sheetrock with fasteners, do not tear the paper. |
09/29/2023 | COT - LCEL - Electrical Above Ceiling | N/A | Partial Pass | 9/28/2023 partial pending my cables need to be secured and off the grid. Also open j boxes need to be closed and labeled. |
08/21/2023 | COT - LCEL - Outdoor Lighting | N/A | Partial Pass | 8/21/23: 2 light pole bases at north side of site approved to pour concrete. Reinforcing and grounding per plan. |
10/10/2023 | COT - LCME - Mechanical Above Ceiling | N/A | Re-inspection required | |
10/10/2023 | COT - LCME - Kitchen Hood | N/A | Partial Pass | 10/10/23: vertical section of grease duct passed smoke test okay to wrap and install, lower horizontal section still needs inspection |
10/19/2023 | COT - LCPL - Plumbing Above Ceiling | N/A | Not Applicable | |
11/14/2023 | COT - FCON - Fire - Final | N/A | Partial Pass | Kitchen hood and fire alarm need to be tested. |
COT - FCON - Hood System - Final | N/A | Not Ready |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM04808
Permit Description: NEW GROUND UP 2,285 S.F. (+ 874 S.F. OF ROOF OVERHANG) DONUT SHOP W/ ASSOCIATED PARKING, DRIVE THRU
Total Completed Inspections - 25
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/28/2023 | COT - HCPL - Rough Soil | Passed | ||
05/30/2023 | COT - LCBU - Preslab | Passed | ||
06/20/2023 | COT - HCBU - Exterior Clips/Sheathing | Passed | ||
07/06/2023 | COT - LCPL - Gas Pressure Test | Passed | ||
08/09/2023 | COT - LCEL - Electrical Intermediate | Passed | ||
08/21/2023 | COT - HCBU - Interior Shear Bracing | Passed | 8/18/23: not ready for inspection. Maintain minimum 3/8" from edge of sheetrock with fasteners, do not tear the paper. 8/21/23: all wallboard approved to tape. |
|
09/06/2023 | COT - LCPL - Yard Water Line | Passed | Okay to backfill. Shading is required. 9/6/2023 | |
09/06/2023 | COT - LCPL - Plumbing Roof Drains | Passed | Duplicate inspection. 9/6/2023 | |
09/12/2023 | BULD - Electrical Clearance | Passed | Approved service panel, ECO Clearance to TEP is required new 3phase service | |
09/27/2023 | COT - LCPL - Sewer | Passed | ||
09/28/2023 | COT - HCEL - Electrical Underground | Passed | ||
09/28/2023 | COT - HCEL - Grounding/Bonding | Passed | ||
10/04/2023 | COT - LCEL - Outdoor Lighting | Passed | ||
10/18/2023 | COT - LCME - Mechanical Above Ceiling | Passed | ||
10/18/2023 | COT - LCME - Kitchen Hood | Passed | ||
10/18/2023 | COT - LCPL - Plumbing Intermediate | Passed | ||
10/18/2023 | COT - LCME - Mechanical Intermediate | Passed | ||
10/19/2023 | COT - HCBU - Excavation/Rebar/Zoning | Passed | 10/19/23: 3 footings for menu boards on east side of building approved. UG electric to the signs approved. | |
11/02/2023 | COT - LCEL - Electrical Final | Passed | ||
11/02/2023 | COT - LCPL - Plumbing Final | Passed | ||
11/09/2023 | COT - LCME - Mechanical Final | Passed | ||
11/09/2023 | COT - FCON - Sprinkler - Final | Passed | No sprinklers in this building | |
11/15/2023 | COT - FCON - Fire - Final | Passed | ||
11/15/2023 | COT - FCON - Hood System - Final | Passed | ||
11/15/2023 | COT - LCBU - Building Final | Passed | Canyon Builders is GC |