Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.

Permit Details

Status:
Complete
Type:
Commercial Building
Apply Date:
06/07/2022
Applicant:
Description:
Conversion of (1) existing R-2 occupancy type unit on the ground floor of a single story building in

Permit Reviews

Permit Number - T22CM04231
Permit Status: Complete
Permit Description: Conversion of (1) existing R-2 occupancy type unit on the ground floor of a single story building in
Start Date Submittal Complete Date Status  
06/07/2022 COMMERCIAL - TI 07/18/2022 COMPLETED Review Details
07/20/2022 RESUBMITTAL 09/14/2022 COMPLETED Review Details
05/11/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 05/11/2023 REQUIRES RESUBMIT Review Details
06/02/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.2 06/07/2023 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - T22CM04231
Permit Status: Complete
Permit Description: Conversion of (1) existing R-2 occupancy type unit on the ground floor of a single story building in
Total Outstanding Activity Conditions - 1
Date Name
06/20/2022 SPECIAL INSPECTION FORMS AND REPORTS REQUIRED PRIOR TO ISSUANCE OF A CERTIFICATE OF OCCUPANCY.

Conditions

Permit Number - T22CM04231
Permit Status: Complete
Permit Description: Conversion of (1) existing R-2 occupancy type unit on the ground floor of a single story building in
Date Description Comments
06/20/2022 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
06/20/2022 SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED.
08/04/2022 WATER DISINFECTION REPORT REQUIRED (SECTION 610.1, IPC 2018)
09/14/2022 Prior to permit issuance a General Contractor Letter (GCL) is required

Outstanding Inspections

Permit Status: Complete
Permit Number: T22CM04231
Permite Description: Conversion of (1) existing R-2 occupancy type unit on the ground floor of a single story building in
Total Outstanding Inspections - 7
Last Inspection Date Description Inspector Results Comments
10/26/2022 COT - LCEL - Electrical Intermediate N/A Not Ready
04/07/2023 COT - LCEL - Electrical Final N/A Re-inspection required 4-7-23: 1-Bathroom fixtures/accessible units are not per approved plans/Code. 2-Toilet seat is not open front. 3-Receptacles/ dedicated circuit missing for KitchenIsland.
04/04/2023 COT - FCON - Fire - Final N/A Partial Pass Smoke alarms need to be installed, Fire extinguisher needs to be hung, EM lights need to be fixed.
04/07/2023 COT - LCBU - Building Progress N/A Re-inspection required 4-7-23: 1-Bathroom fixtures/accessible units are not per approved plans/Code. 2-Toilet seat is not open front. 3-Receptacles/ dedicated circuit missing for KitchenIsland.
04/07/2023 COT - LCBU - CofO N/A Re-inspection required 4-7-23: 1-Bathroom fixtures/accessible units are not per approved plans/Code. 2-Toilet seat is not open front. 3-Receptacles/ dedicated circuit missing for KitchenIsland.
04/07/2023 COT - LCPL - Plumbing Final N/A Re-inspection required 4-7-23: 1-Bathroom fixtures/accessible units are not per approved plans/Code. 2-Toilet seat is not open front. 3-Receptacles/ dedicated circuit missing for KitchenIsland.
04/07/2023 COT - LCBU - Building Final N/A Re-inspection required 4-7-23: 1-Bathroom fixtures/accessible units are not per approved plans/Code. 2-Toilet seat is not open front. 3-Receptacles/ dedicated circuit missing for KitchenIsland.

Completed Inspections

Permit Status: Complete
Permit Number: T22CM04231
Permit Description: Conversion of (1) existing R-2 occupancy type unit on the ground floor of a single story building in
Total Completed Inspections - 10
Date Description Inspector Results Comments
02/24/2023 COT - LCEL - Electrical Intermediate Passed
04/04/2023 COT - LCBU - Building Above Ceiling Passed
04/04/2023 COT - LCBU - Framing Passed
04/04/2023 COT - LCPL - Plumbing Intermediate Passed
04/04/2023 COT - LCPL - Rough Soil Passed
04/04/2023 COT - LCEL - Electrical Above Ceiling Passed
04/04/2023 COT - LCME - Mechanical Intermediate Passed
04/07/2023 COT - LCME - Mechanical Final Passed
04/06/2023 COT - FCON - Fire - Final Passed
04/18/2023 COT - LCBU - Building Final Passed ok to issue C of O

Documents

File Name Document Type  
COFO_FINALCOFO_COMMERCIAL.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
LIGHTING COMCHECK.PDF DOCUMENTS VIEW
MECHANICAL COMCHECK.PDF DOCUMENTS VIEW
PLAN SET.PDF DOCUMENTS VIEW
STRUCTURAL CALCS.PDF DOCUMENTS VIEW