Permit: T22CM03337
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
4882 E EASTLAND ST
Address NEW:
4882 E EASTLAND ST
Apply Date:
05/03/2022
Applicant:
Albert Calderon
Description:
Garage
Permit Reviews
Permit Number - T22CM03337
Permit Status: Complete
Permit Description: Garage
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/03/2022 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 05/17/2022 | COMPLETED |
| 03/16/2023 | RESIDENTIAL NEW DWELLING v.3 | 03/16/2023 | REQUIRES RESUBMIT |
| 03/27/2023 | RESIDENTIAL NEW DWELLING v.4 | 04/21/2023 | REQUIRES RESUBMIT |
| 04/26/2023 | RESIDENTIAL NEW DWELLING v.5 | 05/05/2023 | APPROVED |
| 01/19/2023 | RESIDENTIAL NEW DWELLING v.2 | 02/14/2023 | REQUIRES RESUBMIT |
| 12/02/2022 | RESIDENTIAL NEW DWELLING v.1 | 12/15/2022 | REQUIRES RESUBMIT |
Conditions
Permit Number - T22CM03337
Permit Status: Complete
Permit Description: Garage
| Date | Description | Comments |
|---|---|---|
| 05/05/2023 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/integrated-planning/PDSD/PDSD_Owner_Builder_Affidavit.pdf, is required prior to issuance of permit. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM03337
Permite Description: Garage
Total Outstanding Inspections - 15
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/30/2024 | RSBU - Building Final | N/A | Re-inspection required | No access for inspection. |
| 09/30/2024 | COT - RSPL - Plumbing Final | N/A | Partial Pass | No access for inspection. |
| 09/30/2024 | BULD - Electrical Clearance | N/A | Re-inspection required | No access for inspection. |
| 09/30/2024 | COT - BULD - SWG Clearance | N/A | Re-inspection required | No access for inspection. |
| 09/30/2024 | COT - RSBU - Interior Shear Bracing | N/A | Re-inspection required | No access for inspection. |
| 09/30/2024 | COT - RSPL - Gas Pressure Test | N/A | Re-inspection required | No access for inspection. |
| 09/30/2024 | COT - RSPL - Sewer | N/A | Re-inspection required | |
| 09/30/2024 | COT - RSPL - Yard Water Line | N/A | Re-inspection required | No access for inspection. |
| 09/30/2024 | RSEL - Electrical Progress | N/A | Not Applicable | |
| 09/30/2024 | RSME - Mechanical Progress | N/A | Not Applicable | |
| 09/30/2024 | RSPL - Plumbing Progress | N/A | Not Applicable | |
| 09/30/2024 | COT - RSEL - Grounding/Bonding | N/A | Re-inspection required | No access for inspection. |
| 09/30/2024 | COT - RSME - Mechanical Final | N/A | Re-inspection required | No access for inspection. |
| 09/30/2024 | COT - RSEL - Outdoor Lighting | N/A | Re-inspection required | No access for inspection. |
| 09/30/2024 | COT - RSEL - Electrical Underground | N/A | Re-inspection required | No access for inspection. |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM03337
Permit Description: Garage
Total Completed Inspections - 12
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/10/2023 | COT - RSBU - Preslab | Passed | ||
| 05/16/2023 | RSBU - Building Progress | Passed | ||
| 05/16/2023 | COT - RSBU - Roof Nailing | Passed | ||
| 07/17/2024 | COT - RSEL - Electrical Final | Passed | ||
| 09/30/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
| 09/30/2024 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | ||
| 09/30/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
| 09/30/2024 | COT - RSPL - Rough Soil | Passed | ||
| 10/01/2024 | COT - RSEL - Grounding/Bonding | Passed | ||
| 10/01/2024 | COT - RSME - Mechanical Final | Passed | ||
| 10/01/2024 | COT - RSEL - Outdoor Lighting | Passed | ||
| 10/01/2024 | COT - RSEL - Electrical Underground | Passed |