Permit: T22CM03251
Permit Details
Apply Date:
04/29/2022
Applicant:
Description:
SFR 230.2690 T21-M0027
Outstanding Activity Conditions
Permit Number - T22CM03251
Permit Status: Issued
Permit Description: SFR 230.2690 T21-M0027
Total Outstanding Activity Conditions - 4
Date | Name |
---|---|
04/29/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
04/29/2022 | ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I) |
04/29/2022 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
04/29/2022 | NO FINAL UNTIL THE PUBLIC SEWER G-2020-100/P21WP00059, G-20-059/P20WP00060, G-20-089/P20WP00061 AND THE DOWNSTREAM OFFSITEPUBLIC SEWER FOR PARCEL 4 G-2020-087 IS ACCEPTED AND RELEASED BY PCRWRD |
Outstanding Inspections
Permit Status: Issued
Permit Number: T22CM03251
Permite Description: SFR 230.2690 T21-M0027
Total Outstanding Inspections - 3
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/03/2022 | COT - LCBU - Framing | N/A | Not Ready | replace shear wall that has been cut. double studs need to be continuous for double girders. add blocking to registers. add titan bolts center third of the bottom plates. secure bracing for trusses that have been loosened. add sister stud to the loose stud on second floor 1st bedroom. |
10/27/2022 | COT - RSPL - Plumbing Final | N/A | Not Ready | |
04/13/2023 | RSME - Mechanical Progress | N/A | Re-inspection required |
Completed Inspections
Permit Status: Issued
Permit Number: T22CM03251
Permit Description: SFR 230.2690 T21-M0027
Total Completed Inspections - 18
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/09/2022 | COT - RSPL - Yard Water Line | Passed | {Activity date: 06/09/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
06/09/2022 | COT - RSPL - Sewer | Passed | {Activity date: 06/09/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
06/09/2022 | COT - RSPL - Rough Soil | Passed | {Activity date: 06/09/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
06/20/2022 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 06/20/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
06/20/2022 | COT - RSBU - Preslab | Passed | {Activity date: 06/20/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
06/20/2022 | COT - RSEL - Electrical Underground | Passed | {Activity date: 06/20/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
06/20/2022 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 06/20/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
07/22/2022 | COT - RSBU - Roof Nailing | Passed | {Activity date: 07/22/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
08/02/2022 | COT - RSBU - Exterior Clips/Sheathing | Passed | {Activity date: 08/02/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 07/25/2022; Status: Not ready for Inspection; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - NR} ; {Activity date: 07/22/2022; Status: Denied; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - DE 1. Extend shear wall panels to the exterior face of wall per detail. 2. Missing double studs on first floor east wall that support girder trusses. 3. Remove all metal truss spacers that are hanging loose} | |
11/07/2022 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
11/07/2022 | COT - LCPL - Plumbing Intermediate | Passed | ||
12/02/2022 | COT - HCBU - Interior Shear Bracing | Passed | ||
02/08/2023 | COT - BULD - SWG Clearance | Passed | SWG for meter only | |
04/13/2023 | COT - RSPL - Plumbing Final | Passed | ||
04/13/2023 | COT - RSEL - Outdoor Lighting | Passed | ||
04/13/2023 | COT - RSME - Mechanical Final | Passed | ||
04/13/2023 | COT - RSEL - Electrical Final | Passed | ||
04/13/2023 | RSBU - Building Final | Passed |