Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T22CM02713
Permit Details
Apply Date:
04/13/2022
Applicant:
Description:
15,300sf, new retail building
Permit Reviews
Permit Number - T22CM02713
Permit Status: Complete
Permit Description: 15,300sf, new retail building
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/13/2022 | 3RD PARTY REVIEW - COMMERCIAL | 07/18/2022 | COMPLETED |
07/22/2022 | RESUBMITTAL | 07/29/2022 | COMPLETED |
08/19/2022 | REVISION - - 1ST | 10/04/2022 | COMPLETED |
05/10/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 05/11/2023 | REQUIRES RESUBMIT |
12/16/2022 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 01/27/2023 | APPROVED |
05/18/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 05/22/2023 | APPROVED |
05/25/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 06/05/2023 | APPROVED |
05/22/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 05/25/2023 | REQUIRES RESUBMIT |
03/24/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 03/30/2023 | APPROVED |
Conditions
Permit Number - T22CM02713
Permit Status: Complete
Permit Description: 15,300sf, new retail building
Date | Description | Comments |
---|---|---|
07/15/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. | |
07/15/2022 | SPECIAL INSPECTION FOR CONCRETE IS REQUIRED.. | |
07/15/2022 | SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED. | |
07/15/2022 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. | |
07/15/2022 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
07/15/2022 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
07/15/2022 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. | |
07/29/2022 | This building permit approval is without public sewer connection review or approval. It is strictly the responsibility of the owner and/or person doing the work to ensure that the appropriate review and approval to connect is obtained from Regional Wastewater Reclamation Department (RWRD) wastewater provider or Pima County DEQ approval of/and alternative disposal system. It is required that owner and/or person doing the work solicit all requisite approvals from the wastewater provider prior to obtaining this building construction permit. RWRD connection information is available at www.pima.gov/wwm/developer.htm | |
07/15/2022 | SPECIAL INSPECTION IS REQUIRED FOR EFIS. | |
07/15/2022 | SHOP DRAWINGS REQUIRED FOR PREFABRICATED WOOD TRUSSES. | |
07/15/2022 | SPECIAL INSPECTION IS REQUIRED FOR WATER CHLORINATION REPORT. | |
07/15/2022 | SPECIAL INSPECTION IS REQUIRED FOR AIR BALANCE REPORT. | |
07/29/2022 | PIMA COUNTY WASTEWATER SIGN OFF REQUIRED PRIOR TO ISSUANCE OF FINAL STATUS. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM02713
Permite Description: 15,300sf, new retail building
Total Outstanding Inspections - 13
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2022 | COT - LCBU - Preslab | N/A | Not Ready | |
10/26/2022 | COT - LCEL - Electrical Underground | N/A | Not Ready | |
01/04/2023 | COT - LCBU - Masonry Pregrout | N/A | Partial Pass | 5th lift entry columns at front entrance |
02/07/2023 | COT - LCBU - Exterior Clips/Sheathing | N/A | Not Applicable | |
03/27/2023 | COT - LCBU - Building Above Ceiling | N/A | Not Ready | |
03/27/2023 | COT - LCPL - Plumbing Above Ceiling | N/A | Partial Pass | partial approval for showroom only |
03/27/2023 | COT - LCEL - Electrical Above Ceiling | N/A | Partial Pass | partial approval for showroom area only |
10/26/2022 | COT - LCPL - Plumbing Final | N/A | Not Ready | |
05/10/2023 | COT - FCON - Sprinkler - Final | N/A | Partial Pass | Need to add a head under roll up door for coverage in stock room. |
05/11/2023 | COT - LCPL - Medical Gas Preconstruction Mtg | N/A | Not Applicable | |
03/27/2023 | COT - LCME - Mechanical Intermediate | N/A | Partial Pass | partial approval for ductwork in showroom area only |
05/10/2023 | COT - FCON - Fire - Final | N/A | Partial Pass | Sprinkler head needs to be added under roll up door for coverage in stock room, FCAP sign |
05/11/2023 | COT - LCBU - Building Final | N/A | Partial Pass | Need bacteria test and air balance reports to be submitted to Robert Sherry. Ok to move in operational equipment and train personnel. |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM02713
Permit Description: 15,300sf, new retail building
Total Completed Inspections - 34
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/20/2022 | COT - LCBU - Excavation/Rebar/Zoning | Passed | {Activity date: 09/20/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. Perimeter footings and interior column footings. Ok to place concrete in progress areas.} | |
09/20/2022 | COT - LCEL - Grounding/Bonding | Passed | {Activity date: 09/20/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. Electric ufer in place. Ok to cover.} | |
10/04/2022 | COT - LCBU - Stem Wall/Retaining Wall | Passed | {Activity date: 10/04/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved for perimeter walls, okay to grout} | |
10/11/2022 | COT - LCPL - Yard Water Line | Passed | {Activity date: 10/11/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved from meter to building, okay to backfill progress areas} | |
10/13/2022 | COT - LCPL - Rough Soil | Passed | {Activity date: 10/13/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - - Approved for sanitary lines within the building, okay to backfill progress areas } ; {Activity date: 10/11/2022; Status: Not ready for Inspection; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - NR} |
|
01/11/2023 | COT - LCBU - Masonry Pregrout | Passed | ||
02/07/2023 | COT - LCBU - Roof Nailing | Passed | ||
02/13/2023 | COT - LCPL - Backwater Valve | Passed | backflow preventer is installed and has been certified by R G & Sons. backwater valve is installed on domestic sewer line. |
|
02/13/2023 | COT - LCPL - Sewer | Passed | sewer lines are complete. | |
02/27/2023 | COT - LCBU - Framing | Passed | Wall framing is complete with fire blocking at 10' on all walls. | |
02/27/2023 | COT - LCBU - Firewall/Fire Barrier/Firestop | Passed | Wall framing is complete with fire blocking at 10' on all walls. | |
03/13/2023 | COT - LCEL - Electrical Intermediate | Passed | ||
03/27/2023 | COT - LCME - Mechanical Above Ceiling | Passed | ||
04/17/2023 | BULD - Electrical Clearance | Passed | Approved, ECO Clearance required to TEP for new 600A service | |
04/19/2023 | COT - BULD - SWG Clearance | Passed | ||
05/03/2023 | COT - LCBU - Building Above Ceiling | Passed | Electrical, mechanical, plumbing, & fire sprinkler system above ceilings in bathrooms, break room, hallway & office is complete. Okay to install ceiling tiles. | |
05/03/2023 | COT - LCPL - Plumbing Above Ceiling | Passed | Plumbing above ceiling of bathrooms, break room, hallway & office is complete. Okay to install ceiling tiles. | |
05/03/2023 | COT - LCEL - Electrical Above Ceiling | Passed | Electrical above ceiling of bathrooms, break room, hallway & office is complete. Okay to install ceiling tiles. | |
05/08/2023 | COT - LCPL - Plumbing Final | Passed | ||
05/08/2023 | COT - LCEL - Electrical Final | Passed | ||
05/10/2023 | COT - FCON - Alarm - Final | Passed | ||
05/10/2023 | COT - LCEL - Outdoor Lighting | Passed | Outdoor lighting is installed and operational. | |
05/11/2023 | COT - FCON - Sprinkler - Final | Passed | ||
05/11/2023 | COT - LCME - Mechanical Final | Passed | ||
05/11/2023 | COT - LCPL - Gas Pressure Test | Passed | ||
05/11/2023 | COT - LCBU - Sustainability | Passed | ||
05/11/2023 | COT - LCEL - Construction Power | Passed | ||
05/11/2023 | COT - LCME - Mechanical Intermediate | Passed | ||
05/11/2023 | COT - HCBU - Exterior Clips/Sheathing | Passed | ||
05/11/2023 | COT - HCBU - Interior Shear Bracing | Passed | ||
05/11/2023 | COT - LCPL - Plumbing Intermediate | Passed | ||
05/16/2023 | ENGR Engineering Final | Passed | ||
05/18/2023 | COT - FCON - Fire - Final | Passed | ||
05/19/2023 | COT - LCBU - Building Final | Passed |