Permit Details

Status:
Complete
Type:
Commercial Building
Apply Date:
03/01/2022
Applicant:
Brent Stevens
Description:
210 unit apartment complex with clubhouse, landscaped courtyard and pool, and other amenities. Bldg 2

Permit Reviews

Permit Number - T22CM01450
Permit Status: Complete
Permit Description: 210 unit apartment complex with clubhouse, landscaped courtyard and pool, and other amenities. Bldg 2
Start Date Submittal Complete Date Status  
03/01/2022 COMMERCIAL - BLDG/FIRE/ZONING/ENG 05/02/2022 COMPLETED Review Details
06/30/2022 RESUBMITTAL 07/19/2022 COMPLETED Review Details
08/12/2022 RESUBMITTAL 08/29/2022 COMPLETED Review Details
09/13/2022 RESUBMITTAL 09/26/2022 COMPLETED Review Details
10/03/2022 RESUBMITTAL 10/06/2022 COMPLETED Review Details
01/18/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 01/18/2024 APPROVED Review Details

Conditions

Permit Number - T22CM01450
Permit Status: Complete
Permit Description: 210 unit apartment complex with clubhouse, landscaped courtyard and pool, and other amenities. Bldg 2
Date Description Comments
10/06/2022 SPECIAL INSPECTION FOR CONCRETE IS REQUIRED..
10/06/2022 SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED.
10/06/2022 SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED.
10/06/2022 SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED.
10/06/2022 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.
10/06/2022 SPECIAL INSPECTION FOR WOOD FRAMED DIAPHRAGMS AND SHEAR WALLS IS REQUIRED.
10/06/2022 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
10/06/2022 SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED.
10/06/2022 SPECIAL INSPECTION IS REQUIRED FOR WATER CHLORINATION REPORT REQUIRED PRIOR TO FINAL INSPECTION.
10/06/2022 SPECIAL INSPECTION IS REQUIRED FOR AIR BALANCE REPORT REQUIRED PRIOR TO FINAL INSPECTION.
10/06/2022 SHOP DRAWINGS REQUIRED FOR WOOD FLOOR JOISTS.
10/06/2022 SHOP DRAWINGS REQUIRED FOR TRUSSES, WOOD ROOF TRUSSES.
10/06/2022 PIMA COUNTY WASTEWATER SIGN OFF REQUIRED PRIOR TO ISSUANCE
10/20/2022 PCRWRD requests that the City of Tucson, add the PCRWRD Condition to the COT building permit #T22CM01449:ISSUED WITH PCRWRD CONDITIONS: NO FINAL AND NO CERTIFICATE OF OCCUPANCY UNTIL THE DISCHARGE AUTHORIZATION IS ISSUED BY PDEQ FOR THE PRIVATE SEWER #P22SD00039 Gerry KoziolPima County DSD-Building Codes/Wastewater Utility Fee201 N Stone Ave Tucson, AZ 85701(520)724-6503

Outstanding Inspections

Permit Status: Complete
Permit Number: T22CM01450
Permite Description: 210 unit apartment complex with clubhouse, landscaped courtyard and pool, and other amenities. Bldg 2
Total Outstanding Inspections - 13
Last Inspection Date Description Inspector Results Comments
10/26/2022 FCON – OH Piping & Hydro N/A Not Ready
04/25/2023 COT - LCEL - Electrical Intermediate N/A Partial Pass third floor tower 1
05/04/2023 COT - LCPL - Backwater Valve N/A Not Applicable
10/26/2022 COT - FCON - Sprinkler - Final N/A Not Ready
10/26/2022 COT - FCON - Alarm - Final N/A Not Ready
10/25/2023 COT - LCEL - Electrical Above Ceiling N/A Not Ready
10/26/2022 COT - FCON - Fire - Final N/A Not Ready
12/07/2023 COT - LCBU - Building Progress N/A Not Ready Extension on permit. 12/7/2023
10/26/2022 COT - LCPL - Plumbing Final N/A Not Ready
10/26/2022 COT - LCME - Mechanical Final N/A Not Ready
05/22/2023 COT - LCBU - Building Above Ceiling N/A Partial Pass Plumbing & electrical rough-in for walls and ceiling is complete in the south side of the northeast quadrant of building.
02/14/2024 COT - LCBU - Sustainability N/A Not Applicable
05/22/2023 COT - LCEL - Electrical Progress N/A Partial Pass Electrical rough-in for walls and ceiling is complete in the south side of the northeast quadrant of building.

Completed Inspections

Permit Status: Complete
Permit Number: T22CM01450
Permit Description: 210 unit apartment complex with clubhouse, landscaped courtyard and pool, and other amenities. Bldg 2
Total Completed Inspections - 32
Date Description Inspector Results Comments
12/07/2022 COT - LCPL - Rough Soil Passed
03/15/2023 COT - LCBU - Roof Nailing Passed
04/21/2023 COT - LCME - Mechanical Above Ceiling Passed first and 2nd floor tower 1 ok to insulate, third floor requires reinspect
04/21/2023 COT - LCPL - Plumbing Roof Drains Passed
04/28/2023 COT - LCBU - Excavation/Rebar/Zoning Passed 4/28/23: concrete slab has been poured.
04/28/2023 COT - LCBU - Firewall/Fire Barrier/Firestop Passed Contractor has installed drywall tape around trusses and fire foamed openings of truss braces.
04/28/2023 COT - LCBU - Preslab Passed
04/28/2023 COT - HCPL - Rough Soil Passed 4/28/23: Rough soil is complete and concrete slab has been poured.
04/28/2023 COT - LCEL - Electrical Underground Passed Underground electrical is complete from transformer to service panel.
05/04/2023 COT - LCBU - Exterior Clips/Sheathing Passed
05/26/2023 COT - LCPL - Plumbing Above Ceiling Passed
05/26/2023 COT - LCPL - Plumbing Intermediate Passed
11/15/2023 COT - HCBU - Interior Shear Bracing Passed
11/15/2023 COT - LCPL - Sewer Passed
11/15/2023 COT - LCME - Mechanical Intermediate Passed
11/15/2023 COT - LCBU - Framing Passed
12/04/2023 COT - LCEL - Service Upgrade Passed 11/30/23: ECO panel HPB1 south end and units 2101,2102,2103,2104,2105,2106,2201,2202,2203,2204,2205,2206,2301,2302,2303,2304,2305,2306.

12/4/23:ECO Panel HPB2 North end of building, units: 2107,2108,2109,2110,2112,2113,2114,2207,2208,2209,2210,2211,2212,2213,2214,2307, 2308,2309,2310,2311,2312,2313,2314.
01/17/2024 COT - FCON - Sprinkler - Final Passed
01/18/2024 COT - FCON - Alarm - Final Passed
01/19/2024 COT - LCEL - Electrical Above Ceiling Passed
01/19/2024 COT - LCEL - Outdoor Lighting Passed
01/25/2024 BULD - Electrical Clearance Passed 1/25/2024- clerance emailed ECO GARG 3
1/29/24 clearance resent
01/25/2024 COT - FCON - Fire - Final Passed Ok for level 4 TCO.
02/14/2024 COT - LCBU - Building Progress Passed
02/14/2024 COT - LCPL - Plumbing Final Passed
02/14/2024 COT - LCME - Mechanical Final Passed
02/14/2024 COT - LCPL - Plumbing Progress Passed
02/14/2024 COT - LCBU - Building Above Ceiling Passed
02/14/2024 COT - LCEL - Electrical Final Passed
02/14/2024 COT - LCEL - Electrical Progress Passed
02/14/2024 COT - LCME - Mechanical Progress Passed
05/17/2024 COT - LCBU - Building Final Passed 1/25/24: units 2309-2312 need re-inspection, units 2113-2314 need re-inspection. All other units passed TCO will be given when units listed are complete.
1/26/24: Level 4 TCO all units in BLDG 2
5/17/24: building 2 ok for CofO

Documents

File Name Document Type  
COFO_FINALCOFO_COMMERCIAL.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
TUCSON LANDING LAB REPORT 1-17-24-2024-01-18_V1.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
COMCHECK BLDG TYPE A.PDF DOCUMENTS VIEW
CHECKLIST.PDF DOCUMENTS VIEW
COMCHECK BLDG TYPE B.PDF DOCUMENTS VIEW
COMCHECK BLDG TYPE D.PDF DOCUMENTS VIEW
COMCHECK BLDG TYPE C.PDF DOCUMENTS VIEW
COMCHECK CLUBHOUSE.PDF DOCUMENTS VIEW
GEOTECHNICAL REPORT.PDF DOCUMENTS VIEW
GEOTECH REPORT.PDF DOCUMENTS VIEW
HVAC CALCULATIONS.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
STRUCTURAL CALCULATIONS.PDF DOCUMENTS VIEW
SPECIFICATION MANUAL.PDF DOCUMENTS VIEW
PLAN SET 1 OF 2.PDF CONSTRPLANS VIEW
PLAN SET 2 OF 2.PDF CONSTRPLANS VIEW