Permit: T22CM01450
Permit Details
Apply Date:
03/01/2022
Applicant:
Brent Stevens
Description:
210 unit apartment complex with clubhouse, landscaped courtyard and pool, and other amenities. Bldg 2
Permit Reviews
Permit Number - T22CM01450
Permit Status: Complete
Permit Description: 210 unit apartment complex with clubhouse, landscaped courtyard and pool, and other amenities. Bldg 2
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/01/2022 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 05/02/2022 | COMPLETED |
06/30/2022 | RESUBMITTAL | 07/19/2022 | COMPLETED |
08/12/2022 | RESUBMITTAL | 08/29/2022 | COMPLETED |
09/13/2022 | RESUBMITTAL | 09/26/2022 | COMPLETED |
10/03/2022 | RESUBMITTAL | 10/06/2022 | COMPLETED |
01/18/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 01/18/2024 | APPROVED |
Conditions
Permit Number - T22CM01450
Permit Status: Complete
Permit Description: 210 unit apartment complex with clubhouse, landscaped courtyard and pool, and other amenities. Bldg 2
Date | Description | Comments |
---|---|---|
10/06/2022 | SPECIAL INSPECTION FOR CONCRETE IS REQUIRED.. | |
10/06/2022 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. | |
10/06/2022 | SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED. | |
10/06/2022 | SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED. | |
10/06/2022 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
10/06/2022 | SPECIAL INSPECTION FOR WOOD FRAMED DIAPHRAGMS AND SHEAR WALLS IS REQUIRED. | |
10/06/2022 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
10/06/2022 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. | |
10/06/2022 | SPECIAL INSPECTION IS REQUIRED FOR WATER CHLORINATION REPORT REQUIRED PRIOR TO FINAL INSPECTION. | |
10/06/2022 | SPECIAL INSPECTION IS REQUIRED FOR AIR BALANCE REPORT REQUIRED PRIOR TO FINAL INSPECTION. | |
10/06/2022 | SHOP DRAWINGS REQUIRED FOR WOOD FLOOR JOISTS. | |
10/06/2022 | SHOP DRAWINGS REQUIRED FOR TRUSSES, WOOD ROOF TRUSSES. | |
10/06/2022 | PIMA COUNTY WASTEWATER SIGN OFF REQUIRED PRIOR TO ISSUANCE | |
10/20/2022 | PCRWRD requests that the City of Tucson, add the PCRWRD Condition to the COT building permit #T22CM01449:ISSUED WITH PCRWRD CONDITIONS: NO FINAL AND NO CERTIFICATE OF OCCUPANCY UNTIL THE DISCHARGE AUTHORIZATION IS ISSUED BY PDEQ FOR THE PRIVATE SEWER #P22SD00039 Gerry KoziolPima County DSD-Building Codes/Wastewater Utility Fee201 N Stone Ave Tucson, AZ 85701(520)724-6503 |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM01450
Permite Description: 210 unit apartment complex with clubhouse, landscaped courtyard and pool, and other amenities. Bldg 2
Total Outstanding Inspections - 13
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2022 | FCON – OH Piping & Hydro | N/A | Not Ready | |
04/25/2023 | COT - LCEL - Electrical Intermediate | N/A | Partial Pass | third floor tower 1 |
05/04/2023 | COT - LCPL - Backwater Valve | N/A | Not Applicable | |
10/26/2022 | COT - FCON - Sprinkler - Final | N/A | Not Ready | |
10/26/2022 | COT - FCON - Alarm - Final | N/A | Not Ready | |
10/25/2023 | COT - LCEL - Electrical Above Ceiling | N/A | Not Ready | |
10/26/2022 | COT - FCON - Fire - Final | N/A | Not Ready | |
12/07/2023 | COT - LCBU - Building Progress | N/A | Not Ready | Extension on permit. 12/7/2023 |
10/26/2022 | COT - LCPL - Plumbing Final | N/A | Not Ready | |
10/26/2022 | COT - LCME - Mechanical Final | N/A | Not Ready | |
05/22/2023 | COT - LCBU - Building Above Ceiling | N/A | Partial Pass | Plumbing & electrical rough-in for walls and ceiling is complete in the south side of the northeast quadrant of building. |
02/14/2024 | COT - LCBU - Sustainability | N/A | Not Applicable | |
05/22/2023 | COT - LCEL - Electrical Progress | N/A | Partial Pass | Electrical rough-in for walls and ceiling is complete in the south side of the northeast quadrant of building. |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM01450
Permit Description: 210 unit apartment complex with clubhouse, landscaped courtyard and pool, and other amenities. Bldg 2
Total Completed Inspections - 32
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/07/2022 | COT - LCPL - Rough Soil | Passed | ||
03/15/2023 | COT - LCBU - Roof Nailing | Passed | ||
04/21/2023 | COT - LCME - Mechanical Above Ceiling | Passed | first and 2nd floor tower 1 ok to insulate, third floor requires reinspect | |
04/21/2023 | COT - LCPL - Plumbing Roof Drains | Passed | ||
04/28/2023 | COT - LCBU - Excavation/Rebar/Zoning | Passed | 4/28/23: concrete slab has been poured. | |
04/28/2023 | COT - LCBU - Firewall/Fire Barrier/Firestop | Passed | Contractor has installed drywall tape around trusses and fire foamed openings of truss braces. | |
04/28/2023 | COT - LCBU - Preslab | Passed | ||
04/28/2023 | COT - HCPL - Rough Soil | Passed | 4/28/23: Rough soil is complete and concrete slab has been poured. | |
04/28/2023 | COT - LCEL - Electrical Underground | Passed | Underground electrical is complete from transformer to service panel. | |
05/04/2023 | COT - LCBU - Exterior Clips/Sheathing | Passed | ||
05/26/2023 | COT - LCPL - Plumbing Above Ceiling | Passed | ||
05/26/2023 | COT - LCPL - Plumbing Intermediate | Passed | ||
11/15/2023 | COT - HCBU - Interior Shear Bracing | Passed | ||
11/15/2023 | COT - LCPL - Sewer | Passed | ||
11/15/2023 | COT - LCME - Mechanical Intermediate | Passed | ||
11/15/2023 | COT - LCBU - Framing | Passed | ||
12/04/2023 | COT - LCEL - Service Upgrade | Passed | 11/30/23: ECO panel HPB1 south end and units 2101,2102,2103,2104,2105,2106,2201,2202,2203,2204,2205,2206,2301,2302,2303,2304,2305,2306. 12/4/23:ECO Panel HPB2 North end of building, units: 2107,2108,2109,2110,2112,2113,2114,2207,2208,2209,2210,2211,2212,2213,2214,2307, 2308,2309,2310,2311,2312,2313,2314. |
|
01/17/2024 | COT - FCON - Sprinkler - Final | Passed | ||
01/18/2024 | COT - FCON - Alarm - Final | Passed | ||
01/19/2024 | COT - LCEL - Electrical Above Ceiling | Passed | ||
01/19/2024 | COT - LCEL - Outdoor Lighting | Passed | ||
01/25/2024 | BULD - Electrical Clearance | Passed | 1/25/2024- clerance emailed ECO GARG 3 1/29/24 clearance resent |
|
01/25/2024 | COT - FCON - Fire - Final | Passed | Ok for level 4 TCO. | |
02/14/2024 | COT - LCBU - Building Progress | Passed | ||
02/14/2024 | COT - LCPL - Plumbing Final | Passed | ||
02/14/2024 | COT - LCME - Mechanical Final | Passed | ||
02/14/2024 | COT - LCPL - Plumbing Progress | Passed | ||
02/14/2024 | COT - LCBU - Building Above Ceiling | Passed | ||
02/14/2024 | COT - LCEL - Electrical Final | Passed | ||
02/14/2024 | COT - LCEL - Electrical Progress | Passed | ||
02/14/2024 | COT - LCME - Mechanical Progress | Passed | ||
05/17/2024 | COT - LCBU - Building Final | Passed | 1/25/24: units 2309-2312 need re-inspection, units 2113-2314 need re-inspection. All other units passed TCO will be given when units listed are complete. 1/26/24: Level 4 TCO all units in BLDG 2 5/17/24: building 2 ok for CofO |