Inspection History Details
Inspection Status: Not Ready
Inspection History: COT - LCBU - Excavation/Rebar/Zoning
Permit Number - T22CM01450
Inspection Description - COT - LCBU - Excavation/Rebar/Zoning
Inspection Status - Not Ready
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2022 | COT - LCBU - Excavation/Rebar/Zoning | Not Ready | ||
04/28/2023 | COT - LCBU - Excavation/Rebar/Zoning | Passed | 4/28/23: concrete slab has been poured. | |
11/10/2022 | COT - LCBU - Excavation/Rebar/Zoning | Not Ready | ||
11/14/2022 | COT - LCBU - Excavation/Rebar/Zoning | Partial Pass | North half of Bldg 2, okay for concrete placement | |
11/17/2022 | COT - LCBU - Excavation/Rebar/Zoning | Partial Pass | Partial - perimeter foundations, okay for concrete placement in progress areas |