Inspection Status: Not Ready
Inspection History: COT - LCBU - Building Final
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/27/2022 | COT - LCBU - Building Final | Not Ready | ||
| 01/18/2024 | COT - LCBU - Building Final | Not Ready | ||
| 01/19/2024 | COT - LCBU - Building Final | Partial Pass | TCO level 3 south half | |
| 01/25/2024 | COT - LCBU - Building Final | Partial Pass | 1/25/24: units 2309-2312 need re-inspection, units 2113-2314 need re-inspection. All other units passed TCO will be given when units listed are complete. | |
| 01/26/2024 | COT - LCBU - Building Final | Partial Pass | 1/25/24: units 2309-2312 need re-inspection, units 2113-2314 need re-inspection. All other units passed TCO will be given when units listed are complete. 1/26/24: Level 4 TCO all units in BLDG 2 |
|
| 05/17/2024 | COT - LCBU - Building Final | Passed | 1/25/24: units 2309-2312 need re-inspection, units 2113-2314 need re-inspection. All other units passed TCO will be given when units listed are complete. 1/26/24: Level 4 TCO all units in BLDG 2 5/17/24: building 2 ok for CofO |