Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Commercial Building
Apply Date:
12/27/2021
Applicant:
Lisa Bowers
Description:
New Family Entertainment Center with full dining, bowling, laser tag, arcade games, party areas

Permit Reviews

Permit Number - T21CM09873
Permit Status: Complete
Permit Description: New Family Entertainment Center with full dining, bowling, laser tag, arcade games, party areas
Start Date Submittal Complete Date Status  
03/01/2022 RESUBMITTAL 04/07/2022 COMPLETED Review Details
04/07/2022 RESUBMITTAL 04/21/2022 COMPLETED Review Details
05/25/2022 REVISION - - 1ST 07/21/2022 COMPLETED Review Details
08/04/2022 REVISION - - 2ND 09/22/2022 COMPLETED Review Details
12/27/2021 3RD PARTY REVIEW - COMMERCIAL 02/28/2022 COMPLETED Review Details
02/08/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.2 02/08/2023 APPROVED Review Details
02/01/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 02/07/2023 REQUIRES RESUBMIT Review Details

Conditions

Permit Number - T21CM09873
Permit Status: Complete
Permit Description: New Family Entertainment Center with full dining, bowling, laser tag, arcade games, party areas
Date Description Comments
02/25/2022 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.
02/25/2022 SPECIAL INSPECTION FOR CONCRETE IS REQUIRED..
02/25/2022 SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED.
02/25/2022 SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED.
02/25/2022 SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED.
02/25/2022 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
02/25/2022 SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED.
02/25/2022 SPECIAL INSPECTION IS REQUIRED FOR STRUCTURAL STEEL.
02/25/2022 SHOP DRAWINGS REQUIRED FOR AUTOMATIC FIRE SPRINKLERS.
02/25/2022 SHOP DRAWINGS REQUIRED FOR FIRE ALARM.
02/25/2022 SHOP DRAWINGS REQUIRED FOR KITCHEN HOOD SUPPRESSION SYSTEM.
02/25/2022 SHOP DRAWINGS REQUIRED FOR SIGNAGE.
02/25/2022 SHOP DRAWINGS REQUIRED FOR OPEN-WEB STEEL ROOF JOISTS AND ROOF GIRDERS.
02/25/2022 SHOP DRAWINGS REQUIRED FOR COLD-FORMED-METAL STUD FRAMING.

Outstanding Inspections

Permit Status: Complete
Permit Number: T21CM09873
Permite Description: New Family Entertainment Center with full dining, bowling, laser tag, arcade games, party areas
Total Outstanding Inspections - 12
Last Inspection Date Description Inspector Results Comments
10/26/2022 COT - LCME - Mechanical Above Ceiling N/A Not Ready
10/26/2022 COT - LCPL - Plumbing Roof Drains N/A Not Ready
10/26/2022 COT - LCEL - Electrical Intermediate N/A Not Ready
10/27/2022 COT - LCBU - Framing N/A Not Ready
10/26/2022 COT - LCEL - Electrical Above Ceiling N/A Not Ready
10/26/2022 COT - LCBU - Masonry Pregrout N/A Not Ready
10/26/2022 COT - HCBU - Interior Shear Bracing N/A Not Ready
11/04/2022 COT - LCPL - Rough Soil N/A Partial Pass Partial approval 1500 gal grease interceptor and lines from building to 6”main, okay to backfill progress areas
10/26/2022 COT - LCPL - Plumbing Above Ceiling N/A Not Ready
10/26/2022 COT - LCEL - Grounding/Bonding N/A Not Ready
10/26/2022 COT - LCEL - Outdoor Lighting N/A Not Ready
01/26/2023 COT - HCME - Mechanical Final N/A Not Ready

Completed Inspections

Permit Status: Complete
Permit Number: T21CM09873
Permit Description: New Family Entertainment Center with full dining, bowling, laser tag, arcade games, party areas
Total Completed Inspections - 33
Date Description Inspector Results Comments
07/06/2022 COT - LCBU - Preslab Passed {Activity date: 07/06/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved}
10/10/2022 COT - LCBU - Exterior Clips/Sheathing Passed {Activity date: 10/10/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 10/07/2022; Status: Partial Approval; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - Partial. North side and south side bump out sheathings of building are done. Still waiting on East and West side bump out sheathing center of building to be installed.

} ; {Activity date: 09/28/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by VVERA1 - Partial for clips and framing, okay to sheath}
11/07/2022 COT - LCPL - Rough Soil Passed
11/07/2022 COT - HCPL - Yard Water Line Passed
11/16/2022 COT - LCPL - Gas Pressure Test Passed
11/16/2022 COT - LCPL - Plumbing Above Ceiling Passed
12/05/2022 BULD - Electrical Clearance Passed ECO
12/05/2022 COT - LCEL - Construction Power Passed
01/04/2023 COT - BULD - SWG Clearance Passed
01/04/2023 COT - HCPL - Gas Final Passed For SW Gas meter
01/09/2023 COT - LCBU - Building Above Ceiling Passed
01/10/2023 COT - LCEL - Electrical Underground Passed
01/10/2023 COT - LCPL - Plumbing Intermediate Passed
01/10/2023 COT - LCPL - Sewer Passed
01/10/2023 COT - LCME - Mechanical Intermediate Passed
01/10/2023 COT - LCBU - Excavation/Rebar/Zoning Passed
01/13/2023 COT - HCBU - Masonry Pregrout Passed
01/13/2023 COT - LCBU - Roof Nailing Passed
01/17/2023 COT - LCEL - Grounding/Bonding Passed
01/17/2023 COT - LCBU - Sustainability Passed
01/17/2023 COT - LCEL - Outdoor Lighting Passed
01/19/2023 COT - LCEL - Electrical Final Passed
01/20/2023 COT - LCME - Mechanical Final Passed
01/24/2023 COT - FCON - Underground Flush Passed
01/24/2023 COT - FCON - Sprinkler - Final Passed
01/24/2023 COT - FCON - Underground Pressure Passed
01/24/2023 COT - LCPL - Plumbing Final Passed
01/24/2023 COT - FCON - Alarm - Final Passed
01/24/2023 COT - FCON - Hood System - Final Passed
01/24/2023 COT - LCME - Kitchen Hood Passed
01/24/2023 FCON – OH Piping & Hydro Passed
01/24/2023 COT - FCON - Fire - Final Passed
01/26/2023 COT - LCBU - Building Final Passed recommend for C/O

Documents

File Name Document Type  
REV1_JOB CARD 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
REV1_PLAN SET 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
REV1_REVISION NARRATIVE 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
REV2_BAR JOIST CALCS 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
REV2_DRAWING JOIST 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
REV2_DRAWING STUDS 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
REV2_STURUCTURAL CALCS 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
REVISION APPLICATION 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
REVISION1 APPLICATION 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
REV1_JOB CARD.PDF DOCUMENTS VIEW
REV1_PLAN SET.PDF DOCUMENTS VIEW
REV1_REVISION NARRATIVE.PDF DOCUMENTS VIEW
REV2_BAR JOIST CALCS.PDF DOCUMENTS VIEW
REV2_DRAWING JOIST.PDF DOCUMENTS VIEW
REV2_DRAWING STUDS.PDF DOCUMENTS VIEW
REV2_STURUCTURAL CALCS.PDF DOCUMENTS VIEW
REVISION APPLICATION.PDF DOCUMENTS VIEW
REVISION1 APPLICATION.PDF DOCUMENTS VIEW
COFO_FINALCOFO_COMMERCIAL.PDF DOCUMENTS VIEW
MAIN EVENT TUCSON HOOD SMOKE_V2.PDF DOCUMENTS VIEW
T21CM09873 SPECIAL INSPECTION FORM-2023-02-08_V2.PDF DOCUMENTS VIEW
CONTRACTOR LETTER.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
ENERGY COMCHECK.PDF DOCUMENTS VIEW
GEOTECH.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW
MECH CALCS.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
SPECIAL INSPECTION CERT.PDF DOCUMENTS VIEW
PSA_STANTEC.PDF DOCUMENTS VIEW
STRUCTURAL CALCS.PDF DOCUMENTS VIEW
TRELLIS PLANS.PDF CONSTRPLANS VIEW
PLAN SET.PDF CONSTRPLANS VIEW