Inspection Status: Not Ready
Inspection History: COT - LCBU - Masonry Pregrout
| Date |
Description |
Inspector |
Results |
Comments |
| 10/26/2022 |
COT - LCBU - Masonry Pregrout |
|
Not Ready |
|
| 07/21/2022 |
COT - LCBU - Masonry Pregrout |
SCARRAZCO |
Partial Approval |
Entered by NGARCIA3 - Partial. Panels 0p1, 0p2, 0p4. P3, P38, P37. |
| 07/18/2022 |
COT - LCBU - Masonry Pregrout |
ESTEVENS |
Partial Approval |
Entered by VVERA1 - Partial. Panels 31 thru 36. |
| 07/14/2022 |
COT - LCBU - Masonry Pregrout |
DMUNIZ |
Partial Approval |
Entered by NGARCIA3 - PARTIAL,Following tilt panels are ok for concrete placement (5,6,7,8,910,12) |
| 07/12/2022 |
COT - LCBU - Masonry Pregrout |
TGAUSP |
Partial Approval |
Entered by NGARCIA3 - - Partial - Tilt-Wall reinforcement for panels 15, 16, 17, 18, 19, 20, 21, 22 okay for concrete placement. Special Inspection performed
|
| 07/11/2022 |
COT - LCBU - Masonry Pregrout |
TGAUSP |
Not ready for Inspection |
Entered by VVERA1 - NR, cancelled by Contractor |
| 07/07/2022 |
COT - LCBU - Masonry Pregrout |
TGAUSP |
Partial Approval |
Entered by NGARCIA3 - Partial - Tilt-Wall reinforcement for panels 23, 24, 25, 26, 27, 28, 29, 30, okay for concrete placement. Special Inspection performed |
| 07/07/2022 |
COT - LCBU - Masonry Pregrout |
TGAUSP |
Partial Approval |
Entered by NGARCIA3 - Partial - poured in place Tilt-Wall reinforcement, panels 23, 24, 25, 26, 27, 28, 29, 30, okay for concrete placement |
| 10/25/2022 |
COT - LCBU - Masonry Pregrout |
|
Passed |
|