Permit: T21CM09794
Permit Details
Status:
Needs Resubmittal
Type:
Commercial Building
Address:
2445 N HUACHUCA DR
Address NEW:
2445 N HUACHUCA DR
Apply Date:
12/21/2021
Applicant:
Daniel McPeak
Description:
TI: Office
Permit Reviews
Permit Number - T21CM09794
Permit Status: Needs resubmittal
Permit Description: TI: Office
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/08/2022 | RESUBMITTAL | 03/23/2022 | COMPLETED |
| 04/08/2022 | RESUBMITTAL | 04/12/2022 | COMPLETED |
| 12/21/2021 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 02/25/2022 | COMPLETED |
| 01/13/2026 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 01/14/2026 | REQUIRES RESUBMIT |
| 04/11/2023 | RESTAMP - COMMERCIAL v.1 | 04/13/2023 | APPROVED |
| 09/12/2024 | COMMERCIAL REVIEW - FULL REVISION v.1 | 10/08/2024 | APPROVED |
| 02/07/2023 | COMMERCIAL REVIEW - FULL v.1 | 03/06/2023 | REQUIRES RESUBMIT |
| 05/19/2025 | COMMERCIAL REVIEW - FULL REVISION v.1 | 06/11/2025 | APPROVED |
| 03/14/2023 | COMMERCIAL REVIEW - FULL v.2 | 04/11/2023 | APPROVED |
Outstanding Activity Conditions
Permit Number - T21CM09794
Permit Status: Needs resubmittal
Permit Description: TI: Office
Total Outstanding Activity Conditions - 6
| Date | Name |
|---|---|
| 02/12/2025 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. |
| 02/12/2025 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
| 02/12/2025 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. |
| 02/12/2025 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. |
| 02/12/2025 | SHOP DRAWINGS REQUIRED FOR SPRINKLERS. |
| 02/12/2025 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. |
Conditions
Permit Number - T21CM09794
Permit Status: Needs resubmittal
Permit Description: TI: Office
| Date | Description | Comments |
|---|---|---|
| 04/12/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. | |
| 03/24/2023 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. |
Outstanding Inspections
Permit Status: Needs Resubmittal
Permit Number: T21CM09794
Permite Description: TI: Office
Total Outstanding Inspections - 18
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/27/2022 | COT - LCBU - Building Final | N/A | Not Ready | |
| 10/26/2022 | COT - LCPL - Plumbing Progress | N/A | Not Ready | |
| 10/26/2022 | COT - LCME - Mechanical Above Ceiling | N/A | Not Ready | |
| 10/26/2022 | COT - LCME - Mechanical Progress | N/A | Not Ready | |
| 10/26/2022 | COT - LCEL - Outdoor Lighting | N/A | Not Ready | |
| 10/27/2022 | COT - LCEL - Electrical Final | N/A | Not Ready | |
| 10/26/2022 | COT - LCPL - Plumbing Above Ceiling | N/A | Not Ready | |
| 10/26/2022 | COT - LCBU - Sustainability | N/A | Not Ready | |
| 10/26/2022 | COT - FCON - Fire - Final | N/A | Not Ready | |
| 10/26/2022 | COT - LCME - Mechanical Intermediate | N/A | Not Ready | |
| 10/26/2022 | COT - LCBU - Building Progress | N/A | Not Ready | |
| 10/26/2022 | COT - LCME - Mechanical Final | N/A | Not Ready | |
| 10/26/2022 | COT - LCPL - Plumbing Final | N/A | Not Ready | |
| 10/26/2022 | COT - LCPL - Gas Pressure Test | N/A | Not Ready | |
| 10/26/2022 | COT - LCEL - Service Upgrade | N/A | Not Ready | |
| 10/26/2022 | COT - LCBU - Preslab | N/A | Not Ready | |
| 10/26/2022 | COT - LCEL - Electrical Above Ceiling | N/A | Not Ready | |
| 01/12/2026 | COT - LCEL - Electrical Progress | N/A | Not Ready | please supply a Letter of Torque |
Completed Inspections
Permit Status: Needs Resubmittal
Permit Number: T21CM09794
Permit Description: TI: Office
Total Completed Inspections - 9
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/19/2023 | COT - LCPL - Gas Pressure Test | Passed | N/a 10/19/2023 | |
| 10/19/2023 | COT - LCEL - Service Upgrade | Passed | N/a 10/19/2023 | |
| 10/19/2023 | COT - LCBU - Preslab | Passed | ||
| 10/19/2023 | COT - LCPL - Plumbing Intermediate | Passed | All plumbing approved in walls. Okay to proceed progress areas. 10/19/2023 | |
| 10/19/2023 | COT - LCEL - Electrical Intermediate | Passed | All electrical in walls approved. okay to proceed progress areas. 10/19/2023 | |
| 10/19/2023 | COT - LCBU - Framing | Passed | ||
| 12/18/2023 | COT - HCBU - Interior Shear Bracing | Passed | ||
| 02/15/2024 | COT - LCBU - Building Above Ceiling | Passed | ||
| 11/21/2025 | COT - LCEL - Electrical Above Ceiling | Passed |