Permit: T21CM08148
Permit Details
Status:
Inspections Complete
Type:
Residential Building - One or Two Family
Address:
6057 S AVENIDA CANECA
Address NEW:
6057 S AVENIDA CANECA
Apply Date:
10/14/2021
Applicant:
Samuel Munyankumburwa
Description:
Bedroom Suite and Porch Addition
Permit Reviews
Permit Number - T21CM08148
Permit Status: Inspections complete
Permit Description: Bedroom Suite and Porch Addition
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/14/2021 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 11/08/2021 | COMPLETED |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: T21CM08148
Permite Description: Bedroom Suite and Porch Addition
Total Outstanding Inspections - 10
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/26/2022 | COT - RSBU - Roof Nailing | N/A | Not Ready | |
| 10/26/2022 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | N/A | Not Ready | |
| 07/26/2023 | COT - LCBU - Framing | N/A | Re-inspection required | 7/26/23: Structural Electrical Plumbing HVAC error issues. Remove ALL drywall and insulation for full thorough inspection. 1/23/2024 J&A General Construction assumes all liability, see attachments |
| 07/26/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | N/A | Re-inspection required (with fee) | 7/26/23: Structural Electrical Plumbing HVAC error issues. Remove ALL drywall and insulation for full thorough inspection. 1/23/2024 J&A General Construction assumes all liability, see attachments |
| 07/26/2023 | COT - RSEL - Electrical Underground | N/A | Re-inspection required | 1/23/2024 J&A General Construction assumes all liability, see attachments |
| 07/26/2023 | RSME - Mechanical Progress | N/A | Re-inspection required | 7/26/23: Structural Electrical Plumbing HVAC error issues. Remove ALL drywall and insulation for full thorough inspection. 1/23/2024 J&A General Construction assumes all liability, see attachments |
| 07/26/2023 | RSBU - Building Final | N/A | Re-inspection required | 7/26/23: Structural Electrical Plumbing HVAC error issues. Remove ALL drywall and insulation for full thorough inspection. |
| 07/26/2023 | COT - RSME - Mechanical Final | N/A | Re-inspection required | 7/26/23: Structural Electrical Plumbing HVAC error issues. Remove ALL drywall and insulation for full thorough inspection. |
| 07/26/2023 | COT - RSEL - Electrical Final | N/A | Re-inspection required | 7/26/23: Structural Electrical Plumbing HVAC error issues. Remove ALL drywall and insulation for full thorough inspection. |
| 07/26/2023 | COT - RSPL - Plumbing Final | N/A | Re-inspection required | 7/26/23: Structural Electrical Plumbing HVAC error issues. Remove ALL drywall and insulation for full thorough inspection. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: T21CM08148
Permit Description: Bedroom Suite and Porch Addition
Total Completed Inspections - 8
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/12/2022 | COT - RSPL - Rough Soil | Passed | {Activity date: 08/12/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved} | |
| 08/16/2022 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 08/16/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - approved} | |
| 08/16/2022 | COT - RSBU - Preslab | Passed | {Activity date: 08/16/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - approved} | |
| 08/16/2022 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 08/16/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - approved} | |
| 05/17/2024 | RSBU - Building Final | Passed | 5/17/24: Letter has been submitted by contractor taking full responsibility of addition for the life of the property and will be liable for all work done. See letter in attachments. | |
| 05/17/2024 | COT - RSME - Mechanical Final | Passed | 5/17/24: Letter has been submitted by contractor taking full responsibility of addition for the life of the property and will be liable for all work done. See letter in attachments. | |
| 05/17/2024 | COT - RSEL - Electrical Final | Passed | 5/17/24: Letter has been submitted by contractor taking full responsibility of addition for the life of the property and will be liable for all work done. See letter in attachments. | |
| 05/17/2024 | COT - RSPL - Plumbing Final | Passed | 5/17/24: Letter has been submitted by contractor taking full responsibility of addition for the life of the property and will be liable for all work done. See letter in attachments. |