Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T21CM07886
Permit Details
Apply Date:
10/04/2021
Applicant:
Ivonne Rosas
Description:
Laundry & Bedroom Addition
Permit Reviews
Permit Number - T21CM07886
Permit Status: Complete
Permit Description: Laundry & Bedroom Addition
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/23/2022 | REVISION - - 1ST | 03/09/2022 | COMPLETED |
10/04/2021 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 10/28/2021 | COMPLETED |
11/15/2021 | RESUBMITTAL | 11/23/2021 | COMPLETED |
Outstanding Inspections
Permit Status: Complete
Permit Number: T21CM07886
Permite Description: Laundry & Bedroom Addition
Total Outstanding Inspections - 2
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2022 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | N/A | Not Ready | |
10/27/2022 | COT - LCBU - Framing | N/A | Not Ready |
Completed Inspections
Permit Status: Complete
Permit Number: T21CM07886
Permit Description: Laundry & Bedroom Addition
Total Completed Inspections - 10
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/14/2022 | COT - RSPL - Rough Soil | Passed | {Activity date: 04/14/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} | |
04/22/2022 | COT - RSBU - Preslab | Passed | {Activity date: 04/22/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved, okay for concrete placement} | |
04/22/2022 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 04/22/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 04/14/2022; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - not ready} | |
07/27/2022 | COT - RSBU - Roof Nailing | Passed | {Activity date: 07/27/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - approved} ; {Activity date: 07/25/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} | |
07/27/2022 | COT - RSBU - Exterior Clips/Sheathing | Passed | {Activity date: 07/27/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - approved} ; {Activity date: 07/25/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} | |
09/29/2023 | COT - RSME - Mechanical Final | Passed | ||
09/29/2023 | RSBU - Building Final | Passed | ||
09/29/2023 | RSME - Mechanical Progress | Passed | ||
03/27/2024 | COT - RSPL - Plumbing Final | Passed | 3/27/24: Building final passed by Javier Areolla 9/29/23 | |
03/27/2024 | COT - RSEL - Electrical Final | Passed | 3/27/24: Building final passed by Javier Areolla 9/29/23 |