Permit: T21CM05716
Permit Details
Apply Date:
07/13/2021
Applicant:
Nicholas Tomko
Description:
(T20DV02355) Rehab of existing structures based on damage from previous owners. No new expansion. E
Permit Reviews
Permit Number - T21CM05716
Permit Status: Issued
Permit Description: (T20DV02355) Rehab of existing structures based on damage from previous owners. No new expansion. E
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/11/2022 | REVISION - - 1ST | 05/06/2022 | COMPLETED |
06/04/2022 | REVISION - - 1ST | 07/05/2022 | COMPLETED |
07/13/2021 | COMMERCIAL - TI | 08/19/2021 | COMPLETED |
08/31/2021 | RESUBMITTAL | 09/14/2021 | COMPLETED |
02/10/2023 | COMMERCIAL REVIEW - FULL v.1 | 02/13/2023 | REQUIRES RESUBMIT |
03/13/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/06/2023 | APPROVED |
02/16/2023 | COMMERCIAL REVIEW - FULL v.2 | 02/28/2023 | APPROVED |
04/18/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 05/01/2023 | APPROVED |
01/11/2023 | COMMERCIAL REVIEW - FULL v.1 | 01/30/2023 | APPROVED |
Outstanding Activity Conditions
Permit Number - T21CM05716
Permit Status: Issued
Permit Description: (T20DV02355) Rehab of existing structures based on damage from previous owners. No new expansion. E
Total Outstanding Activity Conditions - 6
Date | Name |
---|---|
02/27/2023 | AIR BALANCING REPORT IS REQUIRED. |
04/13/2022 | ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I) |
04/13/2022 | SPECIAL INSPECTION FORMS AND REPORTS REQUIRED PRIOR TO ISSUANCE OF A CERTIFICATE OF OCCUPANCY. |
04/13/2022 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
05/01/2023 | Structural analysis of the existing building masonry walls at new roof joist locations as identified by Terracon per report dated 3/22/2023. Report number 63231035.0001. Notified Nick / DZ Builders that existing walls appeared not to be grouted and no reinforcing steel was present at time of inspection. Notified Nick that they should call structural engineer for site visit and recommendations for grout and wall reinforcement placement. |
05/01/2023 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. |
Conditions
Permit Number - T21CM05716
Permit Status: Issued
Permit Description: (T20DV02355) Rehab of existing structures based on damage from previous owners. No new expansion. E
Date | Description | Comments |
---|---|---|
05/01/2023 | Masonry Inspection Report submittal review is required. |
Outstanding Inspections
Permit Status: Issued
Permit Number: T21CM05716
Permite Description: (T20DV02355) Rehab of existing structures based on damage from previous owners. No new expansion. E
Total Outstanding Inspections - 15
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2022 | COT - FCON - Alarm - Final | N/A | Not Ready | |
10/26/2022 | COT - FCON - Sprinkler - Final | N/A | Not Ready | |
10/26/2022 | COT - LCBU - Sustainability | N/A | Not Ready | |
10/26/2022 | COT - LCEL - Temporary Service | N/A | Not Ready | |
10/26/2022 | COT - FCON - Fire - Final | N/A | Not Ready | |
10/26/2022 | COT - LCBU - CofO | N/A | Not Ready | |
06/05/2023 | COT - LCPL - Rough Soil | N/A | Partial Pass | Partial pass. Unit #304 okay to back fill. Shading is required. 5/25/2023 Partial pass. #103 and #110 okay to backfill. Shading required. 5/30/2023 (Superintendent stated that Unit #110 is actually #106. Map was provided for verification) Partial pass. Unit #101 and #102 okay to backfill. Shading is required. 6/5/23 Partial pass. Unit #104 and #105 okay to backfill. Shading is required. 6/5/23 |
12/05/2023 | COT - LCEL - Electrical Intermediate | N/A | Partial Pass | Partial pass. MEP'S units 104, 105, 107, and 108. Okay to proceed progress areas. 12/5/2023 |
02/07/2024 | COT - LCBU - Building Progress | N/A | Partial Pass | 2/7/2024. Rough in intermediate (MEP'S) approved for unit #301. Drywall nailing for #302 and #303 approved. Okay to proceed progress areas. Units 101, 102, 104, 105, 107, 108, 201, and 202. Drywall inspection. Okay to proceed progress areas. 1/17/24 |
12/08/2023 | COT - LCME - Mechanical Intermediate | N/A | Partial Pass | 12/08/23: 101,102, 104,105,107,108 all partial for intermediates |
12/08/2023 | COT - LCPL - Plumbing Intermediate | N/A | Partial Pass | 12/08/23: 101,102, 104,105,107,108 all partial for intermediates |
10/26/2022 | COT - LCEL - Grounding/Bonding | N/A | Not Ready | |
10/26/2022 | COT - LCME - Mechanical Final | N/A | Not Ready | |
10/26/2022 | COT - LCPL - Plumbing Final | N/A | Not Ready | |
08/06/2024 | BULD - Electrical Clearance | N/A | Partial Pass | Ok for clearance for units 101,102,103,104,105,106,107,108,109,110, 201 and 202 and house panel |
Completed Inspections
Permit Status: Issued
Permit Number: T21CM05716
Permit Description: (T20DV02355) Rehab of existing structures based on damage from previous owners. No new expansion. E
Total Completed Inspections - 24
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/01/2023 | COT - LCEL - Electrical Underground | Passed | ||
06/13/2023 | COT - LCBU - Excavation/Rebar/Zoning | Passed | ||
06/13/2023 | COT - LCBU - Preslab | Passed | ||
06/20/2023 | COT - HCPL - Rough Soil | Passed | Duplicate of Light commercial permit | |
06/23/2023 | COT - LCPL - Rough Soil | Passed | 6-23-23. Rough soil complete in building 3. Okay to backfill and pour concrete back. | |
06/23/2023 | COT - LCBU - Framing | Passed | Rough framing for buildings 1, 2, & 3 is complete. Okay to insulate, sheet rock, tape, & texture walls. | |
06/23/2023 | COT - LCBU - Exterior Clips/Sheathing | Passed | Buildings 201, 202, 301, 302, 303, & 304 have H2.5 clips on each rafter. | |
06/23/2023 | COT - LCBU - Roof Nailing | Passed | Buildings 301, 302, 303, & 304 have roof sheathing properly nailed off. | |
07/07/2023 | COT - LCBU - Firewall/Fire Barrier/Firestop | Passed | All deficiencies have been corrected. Ok to cover areas in question. | |
03/18/2024 | COT - LCEL - Electrical Intermediate | Passed | ||
03/18/2024 | COT - LCBU - Building Progress | Passed | ||
03/18/2024 | COT - LCME - Mechanical Intermediate | Passed | ||
03/19/2024 | COT - HCPL - Sewer | Passed | ||
03/19/2024 | COT - LCBU - Building Above Ceiling | Passed | ||
03/19/2024 | COT - LCPL - Plumbing Intermediate | Passed | ||
03/19/2024 | COT - HCBU - Exterior Clips/Sheathing | Passed | ||
06/11/2024 | COT - HCBU - Interior Shear Bracing | Passed | ||
06/11/2024 | COT - HCEL - Electrical Intermediate | Passed | Approved intermediates for unit #106,#301, and #304, okay to cover progress areas | |
07/08/2024 | COT - LCEL - Construction Power | Passed | ||
07/08/2024 | COT - LCEL - Grounding/Bonding | Passed | ||
07/24/2024 | COT - LCBU - Building Final | Passed | Approved all finals - units #101-#108 , units #201, #202 , and units #302, #303 | |
07/24/2024 | COT - LCEL - Electrical Final | Passed | Approved all finals - units #101-#108 , units #201, #202 , and units #302, #303 | |
07/24/2024 | COT - LCME - Mechanical Final | Passed | Approved all finals - units #101-#108 , units #201, #202 , and units #302, #303 | |
07/24/2024 | COT - LCPL - Plumbing Final | Passed | Approved all finals - units #101-#108 , units #201, #202 , and units #302, #303 |