Inspection History Details
Inspection Status: Not Ready
Inspection History: COT - LCBU - Building Progress
Permit Number - T21CM05716
Inspection Description - COT - LCBU - Building Progress
Inspection Status - Not Ready
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2022 | COT - LCBU - Building Progress | Not Ready | ||
01/17/2024 | COT - LCBU - Building Progress | Partial Pass | Units 101, 102, 104, 105, 107, 108, 201, and 202. Drywall inspection. Okay to proceed progress areas. 1/17/24 | |
02/07/2024 | COT - LCBU - Building Progress | Partial Pass | 2/7/2024. Rough in intermediate (MEP'S) approved for unit #301. Drywall nailing for #302 and #303 approved. Okay to proceed progress areas. Units 101, 102, 104, 105, 107, 108, 201, and 202. Drywall inspection. Okay to proceed progress areas. 1/17/24 |
|
02/15/2024 | COT - LCBU - Building Progress | Partial Pass | Partial pass. Pending point of connection to main line. Okay to backfill progress areas. Shading is required. 2/15/2024(sewer) | |
02/21/2024 | COT - LCBU - Building Progress | Re-inspection required | Not ready. Provide a minimum 12" separation for main water line from sewer. 2/21/2024 | |
02/26/2024 | COT - LCBU - Building Progress | Partial Pass | Partial pass. Main Water line connections to all units approved. Okay to backfill shading is required. Pending connection to meter. 2/26/2024 | |
03/18/2024 | COT - LCBU - Building Progress | Passed | ||
04/14/2023 | COT - LCBU - Building Progress | Partial Pass | meeting called status update for contractor found bond beams previously installed and advised contractor third-party inspection by Terracon will be satisfactory | |
06/23/2023 | COT - LCBU - Building Progress | Partial Pass | 6-23-23: Rough framing is complete on all 3 buildings, electrical rough-in is complete in building 1, plumbing rough-in complete in all 3 buildings. Roofing materials are being installed on building 1. |