Permit: T21CM04892
Permit Details
Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
2720 E RIVER RD 06
Address NEW:
2720 E RIVER RD 06
Apply Date:
06/11/2021
Applicant:
Indevco
Description:
Independent Living/Hospice/Theraphy Facility
Architects:
- Indevco Architecture, LLC
Contractors:
- Indevco
Permit Reviews
Permit Number - T21CM04892
Permit Status: C of o
Permit Description: Independent Living/Hospice/Theraphy Facility
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/19/2022 | REVISION - - 2ND | 05/20/2022 | COMPLETED |
| 06/07/2022 | REVISION - - 2ND | 06/09/2022 | COMPLETED |
| 06/11/2021 | 3RD PARTY REVIEW - COMMERCIAL TI | 07/27/2021 | COMPLETED |
| 07/19/2022 | REVISION - - 2ND | 08/01/2022 | COMPLETED |
| 08/05/2022 | REVISION - - 2ND | 08/10/2022 | COMPLETED |
| 08/26/2022 | REVISION - - 2ND | 08/31/2022 | COMPLETED |
| 09/02/2021 | REVISION - - 1ST | 09/27/2021 | COMPLETED |
| 11/02/2021 | REVISION - - 2ND | 01/05/2022 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T21CM04892
Permit Description: Independent Living/Hospice/Theraphy Facility
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/10/2021 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | Ap |
| 08/10/2021 | BUILDING PRE-SLAB | DQUINN | Approved | Ap |
| 08/10/2021 | PLUMBING - PRE SLAB | DQUINN | Approved | Ap 2 footings in SE future room 102 ok to pour. All slab cuts ok to pour. |
| 10/15/2021 | PLUMBING - FINAL | DQUINN | Approved | nr |
| 11/15/2021 | PLUMBING - GAS PRESSURE TEST | DQUINN | Approved | nr |
| 11/24/2021 | PLUMBING - ROUGH, SOIL | DQUINN | Approved | Ap Repair ok on kitchen sink drain line for units 213 and 214 |
| 11/24/2021 | FIREWALL/FIREBARRIER/FIRESTOP | DQUINN | Approved | pa Hallway firewall ok outside units 101 - 104 |
| 12/03/2021 | MECHANICAL - ABOVE CEILING | ESTEVENS | Approved | Partial. Unit number 201 and 202. |
| 12/21/2021 | FRAMING | DQUINN | Approved | pa Metal sheathed shear walls, in units 202, 203, 204, 205 ok to cover. |
| 12/27/2021 | MECHANICAL - INTERMEDIATE | RCHANDLER | Approved | -PA. Units 203, 204, and 205. |
| 12/27/2021 | PLUMBING - INTERMEDIATE | RCHANDLER | Approved | PA Units 203, 204, and 205. DWV for Units 208 and 216. |
| 12/27/2021 | ELECTRIC - INTERMEDIATE | RCHANDLER | Approved | PA. Units 203, 204, and 205. |
| 12/27/2021 | SHEET ROCK NAILING | RCHANDLER | Approved | -PA. Units 201 and 202. |
| 12/27/2021 | PLUMBING - ABOVE CEILING | RCHANDLER | Approved | NR. |
| 12/27/2021 | ELECTRIC - ABOVE CEILING | RCHANDLER | Approved | NR. |
| 08/12/2022 | ELECTRIC - FINAL | DQUINN | Approved | Ap |
| 08/12/2022 | BUILDING ABOVE CEILING | DQUINN | Approved | Ap |
| 08/17/2022 | FIRE - FINAL | wmotto | Approved | |
| 08/17/2022 | FIRE - ALARM FINAL | wmotto | Approved | |
| 08/17/2022 | FIRE SPKLR - FINAL | wmotto | Approved | |
| 08/19/2022 | MECHANICAL - FINAL | DQUINN | Approved | Ap Close permit Ok for C of O |
| 08/19/2022 | PLUMBING - GAS PRESS TEST FNL | DQUINN | Approved | Ap |
| 08/19/2022 | BUILDING - FINAL | DQUINN | Approved | Ap |