Inspection History Details
Inspection Status: Approved
Inspection History: MECHANICAL - ABOVE CEILING
Permit Number - T21CM04892
Inspection Description - MECHANICAL - ABOVE CEILING
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/12/2022 | MECHANICAL - ABOVE CEILING | Approved | Ap | |
| 03/30/2022 | MECHANICAL - ABOVE CEILING | Partial Approval | pa All ok in unit # 217 |
|
| 03/21/2022 | MECHANICAL - ABOVE CEILING | Partial Approval | pa Unit # 212 Hvac complete. |
|
| 03/16/2022 | MECHANICAL - ABOVE CEILING | Partial Approval | Partial approval for room 212 walls and hard lids only | |
| 03/09/2022 | MECHANICAL - ABOVE CEILING | Partial Approval | Partial. Unit #213. | |
| 02/25/2022 | MECHANICAL - ABOVE CEILING | Partial Approval | pa All the above mep’s ok in 214, 215, 216 |
|
| 02/08/2022 | MECHANICAL - ABOVE CEILING | Partial Approval | pa Firewalls ok to tape at: Hallway outside 201 - 205, Rooms 206 - 212 Intermediates complete in unit 209 Metal Shear walls ok to rock in units 209 and 212, and in the hallway W. of the N. elevator. |
|
| 02/03/2022 | MECHANICAL - ABOVE CEILING | Partial Approval | Partial approval for 208 210 and 211 ok for drywall on walls only |
|
| 12/03/2021 | MECHANICAL - ABOVE CEILING | Partial Approval | Partial. Unit number 201 and 202. | |
| 11/01/2021 | MECHANICAL - ABOVE CEILING | Partial Approval | pa All mech in 102, 103, and 104 ok to cover |
|
| 10/18/2021 | MECHANICAL - ABOVE CEILING | Partial Approval | pa Above ceiling in 101 and 105 ok to rock |