Permit: T21CM04334
Permit Details
Apply Date:
05/20/2021
Applicant:
Description:
New 288 unit multi family apartment project of type v-b construction with tenant amenities and outdo
Permit Reviews
Permit Number - T21CM04334
Permit Status: Complete
Permit Description: New 288 unit multi family apartment project of type v-b construction with tenant amenities and outdo
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
05/25/2021 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 07/07/2021 | COMPLETED |
07/23/2021 | RESUBMITTAL | 09/08/2021 | COMPLETED |
08/26/2022 | REVISION - - 1ST | 09/12/2022 | COMPLETED |
09/10/2021 | RESUBMITTAL | 10/04/2021 | COMPLETED |
09/28/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 10/04/2023 | APPROVED |
04/03/2023 | COMMERCIAL REVIEW - FULL v.2 | 04/18/2023 | APPROVED |
04/18/2023 | RESTAMP - COMMERCIAL v.1 | 04/19/2023 | APPROVED |
02/16/2023 | COMMERCIAL REVIEW - FULL v.1 | 03/14/2023 | REQUIRES RESUBMIT |
Conditions
Permit Number - T21CM04334
Permit Status: Complete
Permit Description: New 288 unit multi family apartment project of type v-b construction with tenant amenities and outdo
Date | Description | Comments |
---|---|---|
10/04/2023 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
10/04/2023 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
10/04/2023 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. | |
10/04/2023 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
10/04/2023 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. | |
10/04/2023 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. | |
09/29/2023 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T21CM04334
Permite Description: New 288 unit multi family apartment project of type v-b construction with tenant amenities and outdo
Total Outstanding Inspections - 22
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2022 | COT - LCBU - Firewall/Fire Barrier/Firestop | N/A | Not Ready | |
10/26/2022 | COT - LCPL - Plumbing Roof Drains | N/A | Not Ready | |
10/27/2022 | COT - LCPL - Plumbing Intermediate | N/A | Not Ready | |
10/26/2022 | COT - HCBU - Exterior Clips/Sheathing | N/A | Not Ready | |
10/26/2022 | COT - LCBU - Exterior Clips/Sheathing | N/A | Not Ready | |
10/26/2022 | COT - LCEL - Electrical Above Ceiling | N/A | Not Ready | |
10/26/2022 | COT - LCEL - Electrical Intermediate | N/A | Not Ready | |
10/26/2022 | COT - LCME - Mechanical Intermediate | N/A | Not Ready | |
10/26/2022 | COT - LCME - Mechanical Above Ceiling | N/A | Not Ready | |
11/28/2022 | COT - HCBU - Interior Shear Bracing | N/A | Not Ready | |
02/17/2023 | COT - LCEL - Electrical Progress | N/A | Partial Pass | f partial approval for 2nd and 3rd floor guest room sub panels ok to cover and energize |
04/19/2023 | COT - LCBU - Sustainability | N/A | Not Applicable | |
06/23/2023 | COT - FCON - Alarm - Final | N/A | Partial Pass | Building 1 approved only. |
09/26/2023 | COT - LCME - Mechanical Final | N/A | Partial Pass | 9/5/23 please install strain relief on electrical whips and level units 9/20/23: pod 1 west building, all unit ok for TCO level 3 9/26/23: pod 1 east building all unit ok for TCO level 3 |
09/26/2023 | COT - LCPL - Plumbing Final | N/A | Partial Pass | 9/5/23 partial for west 1/2 of south building all three floors awaiting chlorination report 9/20/23: pod 1 west building, all unit ok for TCO level 3 9/26/23: pod 1 east building, all units ok for TCO level 3 awaiting chlorination report |
10/26/2022 | COT - LCBU - Building Above Ceiling | N/A | Not Ready | |
04/19/2023 | COT - LCEL - Grounding/Bonding | N/A | Not Ready | |
09/27/2023 | COT - LCME - Kitchen Hood | N/A | Not Applicable | |
11/22/2023 | COT - LCEL - Construction Power | N/A | Not Applicable | |
11/27/2023 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
09/01/2023 | COT - LCBU - Building Final | N/A | Partial Pass | pod 1 north building, all unit ok for TCO level 3 |
11/27/2023 | ENGR Engineering Final | N/A | Partial Pass | contractor needs to stake the trees on building, four and two patch some of the curb and remove the fence and the Porta John. Good for level 3TCO. |
Completed Inspections
Permit Status: Complete
Permit Number: T21CM04334
Permit Description: New 288 unit multi family apartment project of type v-b construction with tenant amenities and outdo
Total Completed Inspections - 35
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/09/2022 | COT - LCPL - Rough Soil | Passed | {Activity date: 02/09/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} | |
06/01/2022 | COT - LCBU - Excavation/Rebar/Zoning | Passed | {Activity date: 06/01/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - APPROVED} ; {Activity date: 05/17/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved, Amenity building footings ok for concrete placement. } ; {Activity date: 03/31/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Partial, Pod 1 Southeast, East and Northwest buildings okay for concrete placement.} ; {Activity date: 03/23/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial, Pod 1 West & Southwest buildings ok for concrete placement.} |
|
06/01/2022 | COT - LCBU - Preslab | Passed | {Activity date: 06/01/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - APPROVED} ; {Activity date: 03/31/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Partial, Pod 1 Southeast, East and Northwest buildings okay for concrete placement.} ; {Activity date: 03/23/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial, Pod 1 West & Southwest buildings ok for concrete placement} | |
06/09/2022 | COT - FCON - Underground Pressure | Passed | {Activity date: 06/09/2022; Status: Approved; Inspector: CBASALDUA; Comment: Entered by CBASALD1 - } | |
06/28/2022 | COT - LCPL - Gas Pressure Test | Passed | {Activity date: 06/28/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
06/28/2022 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 06/28/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
09/01/2022 | COT - LCBU - Roof Nailing | Passed | {Activity date: 09/01/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 08/16/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Partial approval pod one, all buildings excluding amenities building} ; {Activity date: 08/01/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Partial, POD 1 EAST BUILDING COMPLETE.} ; {Activity date: 07/29/2022; Status: Not ready for Inspection; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - not ready.} ; {Activity date: 07/25/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Partial, POD 1 (S,W) Buildings topped out and deck nail inspection complete.} ; {Activity date: 06/17/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial, WEST BUILDING DECK NAIL INSPECTION OK TO PROCEED.} | |
10/20/2022 | COT - FCON - Underground Flush | Passed | {Activity date: 10/20/2022; Status: Approved; Inspector: CGates; Comment: Entered by CGATES1 - UG Piping and flush approved on permit T21fc00898 on 8/30/22} | |
10/20/2022 | FCON – OH Piping & Hydro | Passed | {Activity date: 10/20/2022; Status: Approved; Inspector: CGates; Comment: Entered by CGATES1 - } ; {Activity date: 09/29/2022; Status: Partial Approval; Inspector: CGates; Comment: Entered by CGATES1 - Building 1 is ok to start drywalling except Amenities building because the overhead has not been completed or inspected.} | |
12/09/2022 | COT - LCBU - Exterior Clips/Sheathing | Passed | ||
01/19/2023 | COT - LCEL - Electrical Above Ceiling | Passed | ||
01/20/2023 | COT - LCEL - Electrical Intermediate | Passed | ||
01/20/2023 | COT - LCME - Mechanical Intermediate | Passed | ||
01/20/2023 | COT - LCME - Mechanical Above Ceiling | Passed | ||
01/20/2023 | COT - HCBU - Interior Shear Bracing | Passed | ||
03/14/2023 | COT - LCEL - Electrical Underground | Passed | ||
04/19/2023 | COT - LCBU - Masonry Pregrout | Passed | ||
04/19/2023 | COT - LCEL - Electrical Progress | Passed | ||
04/19/2023 | COT - LCPL - Plumbing Progress | Passed | ||
04/19/2023 | COT - LCBU - Framing | Passed | ||
04/19/2023 | COT - LCME - Mechanical Progress | Passed | ||
04/19/2023 | COT - LCBU - Building Progress | Passed | ||
04/19/2023 | COT - LCPL - Plumbing Above Ceiling | Passed | ||
04/19/2023 | COT - LCPL - Backwater Valve | Passed | ||
04/19/2023 | COT - LCPL - Sewer | Passed | ||
09/22/2023 | COT - FCON - Sprinkler - Final | Passed | ||
09/22/2023 | COT - FCON - Alarm - Final | Passed | ||
09/27/2023 | COT - LCPL - Plumbing Final | Passed | ||
09/27/2023 | COT - LCEL - Electrical Final | Passed | ||
09/27/2023 | COT - LCBU - Building Above Ceiling | Passed | ||
09/27/2023 | COT - LCEL - Grounding/Bonding | Passed | ||
09/28/2023 | COT - FCON - Fire - Final | Passed | Ok to obtain TCO level 4 building 1. | |
11/22/2023 | COT - LCEL - Outdoor Lighting | Passed | ||
11/30/2023 | COT - LCBU - Building Final | Passed | Ok for C OF O | |
12/01/2023 | ENGR Engineering Final | Passed |