Permit Details

Status:
Complete
Type:
Commercial Building
Apply Date:
05/20/2021
Applicant:
Description:
New 288 unit multi family apartment project of type v-b construction with tenant amenities and outdo

Permit Reviews

Permit Number - T21CM04334
Permit Status: Complete
Permit Description: New 288 unit multi family apartment project of type v-b construction with tenant amenities and outdo
Start Date Submittal Complete Date Status  
05/25/2021 COMMERCIAL - BLDG/FIRE/ZONING/ENG 07/07/2021 COMPLETED Review Details
07/23/2021 RESUBMITTAL 09/08/2021 COMPLETED Review Details
08/26/2022 REVISION - - 1ST 09/12/2022 COMPLETED Review Details
09/10/2021 RESUBMITTAL 10/04/2021 COMPLETED Review Details
09/28/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 10/04/2023 APPROVED Review Details
04/03/2023 COMMERCIAL REVIEW - FULL v.2 04/18/2023 APPROVED Review Details
04/18/2023 RESTAMP - COMMERCIAL v.1 04/19/2023 APPROVED Review Details
02/16/2023 COMMERCIAL REVIEW - FULL v.1 03/14/2023 REQUIRES RESUBMIT Review Details

Conditions

Permit Number - T21CM04334
Permit Status: Complete
Permit Description: New 288 unit multi family apartment project of type v-b construction with tenant amenities and outdo
Date Description Comments
10/04/2023 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
10/04/2023 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
10/04/2023 SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED.
10/04/2023 SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED.
10/04/2023 SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED.
10/04/2023 SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED.
09/29/2023 WATER STERILIZATION REPORT IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: T21CM04334
Permite Description: New 288 unit multi family apartment project of type v-b construction with tenant amenities and outdo
Total Outstanding Inspections - 22
Last Inspection Date Description Inspector Results Comments
10/26/2022 COT - LCBU - Firewall/Fire Barrier/Firestop N/A Not Ready
10/26/2022 COT - LCPL - Plumbing Roof Drains N/A Not Ready
10/27/2022 COT - LCPL - Plumbing Intermediate N/A Not Ready
10/26/2022 COT - HCBU - Exterior Clips/Sheathing N/A Not Ready
10/26/2022 COT - LCBU - Exterior Clips/Sheathing N/A Not Ready
10/26/2022 COT - LCEL - Electrical Above Ceiling N/A Not Ready
10/26/2022 COT - LCEL - Electrical Intermediate N/A Not Ready
10/26/2022 COT - LCME - Mechanical Intermediate N/A Not Ready
10/26/2022 COT - LCME - Mechanical Above Ceiling N/A Not Ready
11/28/2022 COT - HCBU - Interior Shear Bracing N/A Not Ready
02/17/2023 COT - LCEL - Electrical Progress N/A Partial Pass f
partial approval for 2nd and 3rd floor guest room sub panels ok to cover and energize
04/19/2023 COT - LCBU - Sustainability N/A Not Applicable
06/23/2023 COT - FCON - Alarm - Final N/A Partial Pass Building 1 approved only.
09/26/2023 COT - LCME - Mechanical Final N/A Partial Pass 9/5/23 please install strain relief on electrical whips and level units

9/20/23: pod 1 west building, all unit ok for TCO level 3

9/26/23: pod 1 east building all unit ok for TCO level 3
09/26/2023 COT - LCPL - Plumbing Final N/A Partial Pass 9/5/23 partial for west 1/2 of south building all three floors awaiting chlorination report
9/20/23: pod 1 west building, all unit ok for TCO level 3
9/26/23: pod 1 east building, all units ok for TCO level 3 awaiting chlorination report
10/26/2022 COT - LCBU - Building Above Ceiling N/A Not Ready
04/19/2023 COT - LCEL - Grounding/Bonding N/A Not Ready
09/27/2023 COT - LCME - Kitchen Hood N/A Not Applicable
11/22/2023 COT - LCEL - Construction Power N/A Not Applicable
11/27/2023 COT - BULD - SWG Clearance N/A Not Applicable
09/01/2023 COT - LCBU - Building Final N/A Partial Pass pod 1 north building, all unit ok for TCO level 3
11/27/2023 ENGR Engineering Final N/A Partial Pass contractor needs to stake the trees on building, four and two patch some of the curb and remove the fence and the Porta John. Good for level 3TCO.

Completed Inspections

Permit Status: Complete
Permit Number: T21CM04334
Permit Description: New 288 unit multi family apartment project of type v-b construction with tenant amenities and outdo
Total Completed Inspections - 35
Date Description Inspector Results Comments
02/09/2022 COT - LCPL - Rough Soil Passed {Activity date: 02/09/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved}
06/01/2022 COT - LCBU - Excavation/Rebar/Zoning Passed {Activity date: 06/01/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - APPROVED} ; {Activity date: 05/17/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved, Amenity building footings ok for concrete placement.

} ; {Activity date: 03/31/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Partial, Pod 1 Southeast, East and Northwest buildings okay for concrete placement.} ; {Activity date: 03/23/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial, Pod 1 West & Southwest buildings ok for concrete placement.}
06/01/2022 COT - LCBU - Preslab Passed {Activity date: 06/01/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - APPROVED} ; {Activity date: 03/31/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Partial, Pod 1 Southeast, East and Northwest buildings okay for concrete placement.} ; {Activity date: 03/23/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial, Pod 1 West & Southwest buildings ok for concrete placement}
06/09/2022 COT - FCON - Underground Pressure Passed {Activity date: 06/09/2022; Status: Approved; Inspector: CBASALDUA; Comment: Entered by CBASALD1 - }
06/28/2022 COT - LCPL - Gas Pressure Test Passed {Activity date: 06/28/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP}
06/28/2022 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed {Activity date: 06/28/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP}
09/01/2022 COT - LCBU - Roof Nailing Passed {Activity date: 09/01/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 08/16/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Partial approval pod one, all buildings excluding amenities building} ; {Activity date: 08/01/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Partial, POD 1 EAST BUILDING COMPLETE.} ; {Activity date: 07/29/2022; Status: Not ready for Inspection; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - not ready.} ; {Activity date: 07/25/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Partial, POD 1 (S,W) Buildings topped out and deck nail inspection complete.} ; {Activity date: 06/17/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial, WEST BUILDING DECK NAIL INSPECTION OK TO PROCEED.}
10/20/2022 COT - FCON - Underground Flush Passed {Activity date: 10/20/2022; Status: Approved; Inspector: CGates; Comment: Entered by CGATES1 - UG Piping and flush approved on permit T21fc00898 on 8/30/22}
10/20/2022 FCON – OH Piping & Hydro Passed {Activity date: 10/20/2022; Status: Approved; Inspector: CGates; Comment: Entered by CGATES1 - } ; {Activity date: 09/29/2022; Status: Partial Approval; Inspector: CGates; Comment: Entered by CGATES1 - Building 1 is ok to start drywalling except Amenities building because the overhead has not been completed or inspected.}
12/09/2022 COT - LCBU - Exterior Clips/Sheathing Passed
01/19/2023 COT - LCEL - Electrical Above Ceiling Passed
01/20/2023 COT - LCEL - Electrical Intermediate Passed
01/20/2023 COT - LCME - Mechanical Intermediate Passed
01/20/2023 COT - LCME - Mechanical Above Ceiling Passed
01/20/2023 COT - HCBU - Interior Shear Bracing Passed
03/14/2023 COT - LCEL - Electrical Underground Passed
04/19/2023 COT - LCBU - Masonry Pregrout Passed
04/19/2023 COT - LCEL - Electrical Progress Passed
04/19/2023 COT - LCPL - Plumbing Progress Passed
04/19/2023 COT - LCBU - Framing Passed
04/19/2023 COT - LCME - Mechanical Progress Passed
04/19/2023 COT - LCBU - Building Progress Passed
04/19/2023 COT - LCPL - Plumbing Above Ceiling Passed
04/19/2023 COT - LCPL - Backwater Valve Passed
04/19/2023 COT - LCPL - Sewer Passed
09/22/2023 COT - FCON - Sprinkler - Final Passed
09/22/2023 COT - FCON - Alarm - Final Passed
09/27/2023 COT - LCPL - Plumbing Final Passed
09/27/2023 COT - LCEL - Electrical Final Passed
09/27/2023 COT - LCBU - Building Above Ceiling Passed
09/27/2023 COT - LCEL - Grounding/Bonding Passed
09/28/2023 COT - FCON - Fire - Final Passed Ok to obtain TCO level 4 building 1.
11/22/2023 COT - LCEL - Outdoor Lighting Passed
11/30/2023 COT - LCBU - Building Final Passed Ok for C OF O
12/01/2023 ENGR Engineering Final Passed

Documents

File Name Document Type  
COFO_FINALCOFO_COMMERCIAL.PDF DOCUMENTS VIEW
FINAL SIC-2023-09-28_V1.PDF DOCUMENTS VIEW
WATER STERILIZATION REPORT-2023-09-28_V1.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-REV1_2 PLAN SET_V2.PDF DOCUMENTS VIEW
REV1_1 NARRATIVE_V1.PDF DOCUMENTS VIEW
REV1_2 MAIL BOX CALCULATIONS_SEALED_V1.PDF DOCUMENTS VIEW
CONTRACTOR LETTER.PDF DOCUMENTS VIEW
CHECKLIST.PDF DOCUMENTS VIEW
DRAINAGE STATEMENT.PDF DOCUMENTS VIEW
GEOTECH.PDF DOCUMENTS VIEW
INSPECTION CARD.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
ONE TIME BOND EXEMPT.PDF DOCUMENTS VIEW
SPECIAL INSPECTION CERT -WRONG MISSING INFO.PDF DOCUMENTS VIEW
SPECS VOL 1.PDF DOCUMENTS VIEW
SPECS VOL 2.PDF DOCUMENTS VIEW
STRUCTURAL CALCS VOL 1.PDF DOCUMENTS VIEW
STRUCTURAL CALCS VOL 2.PDF DOCUMENTS VIEW
STRUCTURAL CALCS VOL A.PDF DOCUMENTS VIEW
TRAFFIC IMPACT ANALYSIS.PDF DOCUMENTS VIEW
PLAN SET.PDF CONSTRPLANS VIEW