Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/18/2023 | ENGR Engineering Final | Partial Pass | Contractors are asking for a TCO for the amenity building only. Contractor may receive the TCO for the amenity building and for training and stocking. | |
07/19/2023 | ENGR Engineering Final | Partial Pass | Contractors requesting TCO for the amenity building only and for training and stocking | |
09/25/2023 | ENGR Engineering Final | Partial Pass | Contractor needs to remove the bamboo steaks and we steak the trees that haven’t been staked. The scupper’s from the drainage on the west end of the building a pod one needs to be cleaned out fixed to damage curb on the entrance of pod one.ok for T.C.O LEVEL FOUR. | |
10/02/2023 | ENGR Engineering Final | Partial Pass | TC of O level 4 Handicap parking area in front of main entry to lobby has been re-painted. | |
11/22/2023 | ENGR Engineering Final | Partial Pass | Building # 4 - Repair concrete sidewalk ramp at SW corner of parking lot. Repaired asphalt at SW corner of parking lot where dumpster was removed and remove fence from North side of building #4. Repair or replace continuous crack at NE corner of sidewalk at building # 4. Remove construction debris and materials from parking lot areas. Patch multiple curb and scupper locations thru out parking lot areas for building # 4 |
|
11/27/2023 | ENGR Engineering Final | Partial Pass | contractor needs to stake the trees on building, four and two patch some of the curb and remove the fence and the Porta John. Good for level 3TCO. | |
12/01/2023 | ENGR Engineering Final | Passed |