Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2022 | COT - LCEL - Electrical Underground | Not Ready | ||
10/05/2022 | COT - LCEL - Electrical Underground | JBURGE | Partial Approval | Entered by NGARCIA3 - Partial. Conduit lines for pool panel and electric gates (3/4", 1"’ 1 1/4"). Conduit trench is approximately 50’. Ok to cover progress areas. |
09/19/2022 | COT - LCEL - Electrical Underground | WGALLAGHER | Cancelled | Entered by VVERA1 - Inspection canceled by contractor |
09/16/2022 | COT - LCEL - Electrical Underground | ESTEVENS | Partial Approval | Entered by VVERA1 - Partial. From building 1 Eastside main panel to across the motorized gate and island, to the light pole, |
09/15/2022 | COT - LCEL - Electrical Underground | WGALLAGHER | Partial Approval | Entered by NGARCIA3 - Partial approval for east north east side of bldg E pod 1 light pole base and car charger conduits ok to cover |
09/13/2022 | COT - LCEL - Electrical Underground | WGALLAGHER | Partial Approval | Entered by VVERA1 - Partial approval for light pole base conduits on SE corner of bldg 1 |
06/22/2022 | COT - LCEL - Electrical Underground | TGAUSP | Partial Approval | Entered by VVERA1 - Partial at Pod 1, for the 2-4” secondary lines at the west transformer location to West building, and from the south transformer location Southwest building, okay to backfill progress areas |
06/16/2022 | COT - LCEL - Electrical Underground | DMUNIZ | Partial Approval | Entered by NGARCIA3 - PARTIAL , SECONDARY CONDUITS INSTALLED FROM TRANSFORMER LOCATION TO BUILDING EDGE, OK TO BACKFILL PROGRESS AREAS. |
06/13/2022 | COT - LCEL - Electrical Underground | DMUNIZ | Partial Approval | Entered by VVERA1 - Partial, no inspection today see previous notes |
03/09/2022 | COT - LCEL - Electrical Underground | DMUNIZ | Partial Approval | Entered by NGARCIA3 - Partial, underground conduits North building Pod 1 installed for sub panel feeders and fire alarm. Ok to backfill progress area. |
03/04/2022 | COT - LCEL - Electrical Underground | TGAUSP | Partial Approval | Entered by VVERA1 - Partial for all under slab conduits within the east building apartments, pod 1, okay to cover |
03/02/2022 | COT - LCEL - Electrical Underground | TGAUSP | Partial Approval | Entered by VVERA1 - Partial for electrical conduit from leasing office area to fitness room area on north-east end of building, okay to backfill progress areas |
02/25/2022 | COT - LCEL - Electrical Underground | DMUNIZ | Partial Approval | Entered by NGARCIA3 - Partial under foundation raceways installed for Pod 1 West building. |
03/14/2023 | COT - LCEL - Electrical Underground | Passed |