Permit Details

Status:
Issued
Type:
Commercial Building
Address:
1855 W DREXEL RD
Address NEW:
1855 W DREXEL RD
Apply Date:
04/22/2021
Applicant:
Description:
Addition & TI: FIre Station (TFD #18)

Permit Reviews

Permit Number - T21CM03395
Permit Status: Issued
Permit Description: Addition & TI: FIre Station (TFD #18)
Start Date Submittal Complete Date Status  
03/11/2022 REVISION - - 1ST 03/31/2022 COMPLETED Review Details
04/07/2022 REVISION - - 2ND 04/08/2022 COMPLETED Review Details
04/13/2022 REVISION - - 3RD 04/15/2022 COMPLETED Review Details
04/19/2022 REVISION - - 3RD 04/26/2022 COMPLETED Review Details
04/22/2021 COMMERCIAL - TI 06/10/2021 COMPLETED Review Details
06/29/2021 RESUBMITTAL 07/22/2021 COMPLETED Review Details
08/02/2021 RESUBMITTAL 11/29/2021 COMPLETED Review Details
05/30/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.2 06/02/2023 APPROVED Review Details
03/07/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 03/28/2023 REQUIRES RESUBMIT Review Details
06/12/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 06/15/2023 APPROVED Review Details

Conditions

Permit Number - T21CM03395
Permit Status: Issued
Permit Description: Addition & TI: FIre Station (TFD #18)
Date Description Comments
08/10/2021 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.
08/10/2021 SPECIAL INSPECTION FORMS AND REPORTS REQUIRED PRIOR TO ISSUANCE OF A CERTIFICATE OF OCCUPANCY.
08/10/2021 SPECIAL INSPECTION FOR CONCRETE IS REQUIRED..
08/10/2021 SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED.
08/10/2021 SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED.
08/10/2021 SPECIAL INSPECTION FOR SHOTCRETE IS REQUIRED.
08/10/2021 SHOP DRAWINGS REQUIRED FOR WOOD I-JOISTS
08/10/2021 SHOP DRAWINGS REQUIRED FOR NON-STRUCTURAL COMPONENT SUPPORT AND ANCHORAGE

Outstanding Inspections

Permit Status: Issued
Permit Number: T21CM03395
Permite Description: Addition & TI: FIre Station (TFD #18)
Total Outstanding Inspections - 24
Last Inspection Date Description Inspector Results Comments
10/27/2022 COT - LCBU - Building Final N/A Not Ready
10/26/2022 COT - LCME - Mechanical Final N/A Not Ready
10/26/2022 COT - LCME - Mechanical Progress N/A Not Ready
10/26/2022 COT - FCON - Underground Flush N/A Not Ready
10/27/2022 COT - LCEL - Electrical Final N/A Not Ready
10/26/2022 COT - LCBU - Sustainability N/A Not Ready
10/26/2022 COT - LCME - Mechanical Intermediate N/A Not Ready
10/26/2022 COT - LCEL - Service Upgrade N/A Not Ready
10/26/2022 FCON – OH Piping & Hydro N/A Not Ready
10/26/2022 COT - LCBU - Building Progress N/A Not Ready
10/26/2022 COT - FCON - Underground Pressure N/A Not Ready
10/26/2022 COT - LCPL - Plumbing Final N/A Not Ready
10/26/2022 COT - LCEL - Electrical Progress N/A Not Ready
10/26/2022 COT - LCPL - Plumbing Roof Drains N/A Not Ready
10/27/2022 COT - LCBU - Framing N/A Not Ready
10/26/2022 COT - LCEL - Electrical Intermediate N/A Not Ready
10/26/2022 COT - LCEL - Electrical Above Ceiling N/A Not Ready
10/26/2022 COT - LCPL - Plumbing Above Ceiling N/A Not Ready
10/26/2022 COT - LCME - Mechanical Above Ceiling N/A Not Ready
10/27/2022 COT - LCPL - Plumbing Intermediate N/A Not Ready
06/28/2023 COT - FCON - Sprinkler - Final N/A Partial Pass Need to verify hood is tied into fire alarm.
06/28/2023 COT - FCON - Hood System - Final N/A Partial Pass Need to verify hood is tied into fire alarm.
06/28/2023 COT - FCON - Alarm - Final N/A Partial Pass Need to verify hood is tied into fire alarm.
06/28/2023 COT - FCON - Fire - Final N/A Partial Pass Need to verify hood is tied into fire alarm.

Completed Inspections

Permit Status: Issued
Permit Number: T21CM03395
Permit Description: Addition & TI: FIre Station (TFD #18)
Total Completed Inspections - 20
Date Description Inspector Results Comments
01/19/2022 COT - LCPL - Plumbing Progress Passed {Activity date: 01/19/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved for under slab rough plumbing, okay to proceed with building pre-slab} ; {Activity date: 01/18/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by VVERA1 - Partial soil for the Dorm addition, okay to continue with pre slab} ; {Activity date: 12/28/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial, relocation of grease interceptor complete, install tracer line and clean outs at Inlet and Outlet locations and test system once all branch lines are installed.}
01/19/2022 COT - LCBU - Preslab Passed {Activity date: 01/19/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved for under slab rough plumbing, okay to proceed with building pre-slab}
01/31/2022 COT - LCPL - Rough Soil Passed {Activity date: 01/31/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - Approved, okay to backfill sewer line connected to existing}
06/22/2022 COT - LCBU - Exterior Clips/Sheathing Passed {Activity date: 06/22/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} ; {Activity date: 04/01/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by VVERA1 - Partial for Dorm Rooms, okay to lath progress areas}
06/22/2022 COT - LCBU - Roof Nailing Passed {Activity date: 06/22/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} ; {Activity date: 05/24/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Partial for the roof areas over rooms 121,122,123} ; {Activity date: 04/01/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by VVERA1 - Partial for Dorm Rooms, okay to dry-in progress areas}
07/11/2022 COT - LCPL - Gas Pressure Test Passed {Activity date: 07/11/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved to new apparatus bay} ; {Activity date: 12/28/2021; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Not Ready}
07/21/2022 COT - HCBU - Interior Shear Bracing Passed {Activity date: 07/21/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - approved} ; {Activity date: 05/24/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Partial for the Dorm room area walls}
01/18/2023 COT - LCEL - Electrical Above Ceiling Passed electrical above ceiling passed inspection
01/18/2023 COT - LCPL - Plumbing Above Ceiling Passed plumbing above ceiling is complete.
01/18/2023 COT - LCME - Mechanical Above Ceiling Passed mechanical above ceiling passed
01/18/2023 COT - LCBU - Building Above Ceiling Passed mechanical, electrical, & plumbing passed. okay to finish ceiling tiles.
03/23/2023 BULD - Electrical Clearance Passed Approved, INCR Clearance to TEP is required for the electrical cutover
03/29/2023 COT - LCBU - Firewall/Fire Barrier/Firestop Passed
03/29/2023 COT - LCEL - Outdoor Lighting Passed Pass
03/29/2023 COT - LCPL - Plumbing Intermediate Passed
07/12/2023 COT - FCON - Sprinkler - Final Passed
07/12/2023 COT - FCON - Hood System - Final Passed
07/12/2023 COT - FCON - Alarm - Final Passed
07/12/2023 COT - FCON - Fire - Final Passed
07/26/2023 COT - HCBU - Building Final Passed

Documents

File Name Document Type  
APPLICAITON 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
CALCULATION SHEET 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
CALCULATION SHEET_STRUCTURAL_STEEL 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
JOB CARD (2) 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
JOB CARD 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
PERMIT (2) 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
PERMIT 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
REV 2 CALCULATION SHEET 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
REV 2 PLAN SET 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
REV 2 SHOP DRAWING I-JOISTS 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
REV1_CALCULATION SHEET 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
REV1_JOB CARD 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
REV1_PERMIT 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
REV1_PLAN SET 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
REV1_STRUCTURAL ENGINEER'S LETTER 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
REV3_PLAN SET 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
REVISION APPLICATION 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
REVISION LETTER 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
REVISION NARRATIVE 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
FIRE STATION 18 TEST - BALANCE_V1.PDF DOCUMENTS VIEW
23E0737_2 TURNER 05 26 2023 1410-2023-05-26_V2.PDF DOCUMENTS VIEW
APPLICAITON.PDF DOCUMENTS VIEW
CALCULATION SHEET.PDF DOCUMENTS VIEW
CALCULATION SHEET_STRUCTURAL_STEEL.PDF DOCUMENTS VIEW
JOB CARD (2).PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW
PERMIT (2).PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
REV 2 CALCULATION SHEET.PDF DOCUMENTS VIEW
REV 2 PLAN SET.PDF DOCUMENTS VIEW
REV 2 SHOP DRAWING I-JOISTS.PDF DOCUMENTS VIEW
REV1_CALCULATION SHEET.PDF DOCUMENTS VIEW
REV1_JOB CARD.PDF DOCUMENTS VIEW
REV1_PERMIT.PDF DOCUMENTS VIEW
REV1_PLAN SET.PDF DOCUMENTS VIEW
REV1_STRUCTURAL ENGINEER'S LETTER.PDF DOCUMENTS VIEW
REV3_PLAN SET.PDF DOCUMENTS VIEW
REVISION APPLICATION.PDF DOCUMENTS VIEW
REVISION LETTER.PDF DOCUMENTS VIEW
REVISION NARRATIVE.PDF DOCUMENTS VIEW