Inspection Status: Passed
Inspection History: COT - LCPL - Plumbing Progress
| Date |
Description |
Inspector |
Results |
Comments |
| 01/19/2022 |
COT - LCPL - Plumbing Progress |
TGAUSP |
Approved |
Entered by NGARCIA3 - Approved for under slab rough plumbing, okay to proceed with building pre-slab |
| 01/18/2022 |
COT - LCPL - Plumbing Progress |
TGAUSP |
Partial Approval |
Entered by VVERA1 - Partial soil for the Dorm addition, okay to continue with pre slab |
| 12/28/2021 |
COT - LCPL - Plumbing Progress |
DMUNIZ |
Partial Approval |
Entered by NGARCIA3 - Partial, relocation of grease interceptor complete, install tracer line and clean outs at Inlet and Outlet locations and test system once all branch lines are installed. |