Permit: T21CM00635
Permit Details
Apply Date:
01/21/2021
Applicant:
Garry Brav
Description:
Private Lift Station (Per Bob Sherry this needs building, plumbing & electrical reviews)
Permit Reviews
Permit Number - T21CM00635
Permit Status: Issued
Permit Description: Private Lift Station (Per Bob Sherry this needs building, plumbing & electrical reviews)
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/25/2021 | OTHER | 03/18/2021 | COMPLETED |
03/26/2021 | RESUBMITTAL | 04/15/2021 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T21CM00635
Permit Status: Issued
Permit Description: Private Lift Station (Per Bob Sherry this needs building, plumbing & electrical reviews)
Total Outstanding Activity Conditions - 5
Date | Name |
---|---|
03/15/2021 | SPECIAL INSPECTION FORMS AND REPORTS REQUIRED PRIOR TO ISSUANCE OF A CERTIFICATE OF OCCUPANCY. |
03/15/2021 | SPECIAL INSPECTION FOR CONCRETE IS REQUIRED.. |
03/15/2021 | SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED. |
03/15/2021 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. |
03/15/2021 | SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED. |
Outstanding Inspections
Permit Status: Issued
Permit Number: T21CM00635
Permite Description: Private Lift Station (Per Bob Sherry this needs building, plumbing & electrical reviews)
Total Outstanding Inspections - 6
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2022 | COT - LCEL - Temporary Service | N/A | Not Ready | |
10/26/2022 | COT - LCEL - Service Upgrade | N/A | Not Ready | |
10/26/2022 | COT - LCPL - Sewer | N/A | Not Ready | |
10/26/2022 | COT - LCPL - Plumbing Final | N/A | Not Ready | |
10/26/2022 | PDSD Building Division Pre-Construction Meeting | N/A | Not Ready | |
06/28/2024 | COT - LCEL - Electrical Final | N/A | Not Ready |
Completed Inspections
Permit Status: Issued
Permit Number: T21CM00635
Permit Description: Private Lift Station (Per Bob Sherry this needs building, plumbing & electrical reviews)
Total Completed Inspections - 11
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/18/2021 | COT - LCEL - Electrical Underground | Passed | {Activity date: 11/18/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap} ; {Activity date: 09/29/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap All conduits from stub out to TEP equipment, to service panel and then to equipment, ok to backfill.} |
|
11/18/2021 | COT - LCBU - Excavation/Rebar/Zoning | Passed | {Activity date: 11/18/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap} ; {Activity date: 11/15/2021; Status: Denied; Inspector: DQUINN; Comment: Entered by RSALDAT1 - Original contact handed off inspection to Woody. Haven’t heard from Woody at 3pm. Please recall for inspection and leave a message with Woody’s phone #. Thank you. If you go to the site today, gets pictures of the footings. Then you won’t have to drive back there. } |
|
11/18/2021 | COT - LCBU - Preslab | Passed | {Activity date: 11/18/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap} | |
11/18/2021 | COT - LCEL - Grounding/Bonding | Passed | {Activity date: 11/18/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap} | |
01/11/2022 | COT - LCBU - Masonry Pregrout | Passed | {Activity date: 01/11/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by VVERA1 - Ap Ok to grout to top out} ; {Activity date: 12/22/2021; Status: Not ready for Inspection; Inspector: DQUINN; Comment: Entered by VVERA1 - nr for 2nd lift. 1st lift ok’d yesterday.} ; {Activity date: 12/21/2021; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by RSALDAT1 - pa Ok to grout 1st lift of building’s 4 walls} |
|
01/25/2022 | COT - LCEL - Electrical Intermediate | Passed | {Activity date: 01/25/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap All panels in place. Will inspect them when ready for power.} ; {Activity date: 09/29/2021; Status: Not ready for Inspection; Inspector: DQUINN; Comment: Entered by NGARCIA3 - nr} |
|
08/15/2024 | COT - LCEL - Construction Power | Passed | Approved 3-phase 200A service panel - ECO Clearance to TEP is required (Temp const power NA) | |
08/16/2024 | COT - LCBU - Building Final | Passed | ||
08/16/2024 | COT - LCBU - Building Progress | Passed | ||
08/16/2024 | COT - LCEL - Electrical Final | Passed | ||
08/16/2024 | BULD - Electrical Clearance | Passed |