Inspection Status: Passed
Inspection History: COT - LCBU - Masonry Pregrout
| Date |
Description |
Inspector |
Results |
Comments |
| 01/11/2022 |
COT - LCBU - Masonry Pregrout |
DQUINN |
Approved |
Entered by VVERA1 - Ap
Ok to grout to top out |
| 12/22/2021 |
COT - LCBU - Masonry Pregrout |
DQUINN |
Not ready for Inspection |
Entered by VVERA1 - nr for 2nd lift. 1st lift ok’d yesterday. |
| 12/21/2021 |
COT - LCBU - Masonry Pregrout |
DQUINN |
Partial Approval |
Entered by RSALDAT1 - pa
Ok to grout 1st lift of building’s 4 walls |