Permit: T21CM00368
Permit Details
Apply Date:
01/13/2021
Applicant:
Steven Shell
Description:
Construct a new exterior wall to replace the entire North end of the building scheduled to be remove
Permit Reviews
Permit Number - T21CM00368
Permit Status: Expired
Permit Description: Construct a new exterior wall to replace the entire North end of the building scheduled to be remove
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/13/2021 | COMMERCIAL - TI | 02/10/2021 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T21CM00368
Permit Status: Expired
Permit Description: Construct a new exterior wall to replace the entire North end of the building scheduled to be remove
Total Outstanding Activity Conditions - 4
| Date | Name |
|---|---|
| 02/10/2021 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
| 02/10/2021 | SPECIAL INSPECTION FORMS AND REPORTS REQUIRED PRIOR TO ISSUANCE OF A CERTIFICATE OF OCCUPANCY. |
| 02/10/2021 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. |
| 02/10/2021 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. |
Outstanding Inspections
Permit Status: Expired
Permit Number: T21CM00368
Permite Description: Construct a new exterior wall to replace the entire North end of the building scheduled to be remove
Total Outstanding Inspections - 6
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/17/2021 | COT - LCEL - Electrical Intermediate | N/A | Canceled | {Activity date: 05/17/2021; Status: Not Applicable; Inspector: ESTEVENS; Comment: Entered by VLEON1 - } |
| 05/17/2021 | COT - LCME - Mechanical Final | N/A | Canceled | {Activity date: 05/17/2021; Status: Not Applicable; Inspector: ESTEVENS; Comment: Entered by VLEON1 - } |
| 05/17/2021 | COT - LCEL - Construction Power | N/A | Canceled | {Activity date: 05/17/2021; Status: Not Applicable; Inspector: ESTEVENS; Comment: Entered by VLEON1 - } ; {Activity date: 03/15/2021; Status: Not ready for Inspection; Inspector: ESTEVENS; Comment: Entered by VLEON1 - } |
| 05/17/2021 | COT - LCPL - Rough Soil | N/A | Canceled | {Activity date: 05/17/2021; Status: Not Applicable; Inspector: ESTEVENS; Comment: Entered by VLEON1 - } |
| 05/17/2021 | COT - LCPL - Plumbing Final | N/A | Canceled | {Activity date: 05/17/2021; Status: Not Applicable; Inspector: ESTEVENS; Comment: Entered by VLEON1 - } |
| 11/07/2022 | COT - LCEL - Temporary Service | N/A | Canceled | Inspection Canceled |
Completed Inspections
Permit Status: Expired
Permit Number: T21CM00368
Permit Description: Construct a new exterior wall to replace the entire North end of the building scheduled to be remove
Total Completed Inspections - 12
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/18/2021 | COT - LCBU - Excavation/Rebar/Zoning | Passed | {Activity date: 02/18/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by RSALDAT1 - Ap North wall ok to pour} |
|
| 02/18/2021 | COT - LCEL - Grounding/Bonding | Passed | {Activity date: 02/18/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by RSALDAT1 - Ap} | |
| 03/15/2021 | COT - LCBU - Framing | Passed | {Activity date: 03/15/2021; Status: Approved; Inspector: ESTEVENS; Comment: Entered by VLEON1 - } ; {Activity date: 03/04/2021; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by BSTEVENS - APPROVED TO NEW CMU WALL OK TO ROOF} ; {Activity date: 02/26/2021; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by BSTEVENS - PARTIAL LEDGER BOLTS IN PLACE} | |
| 03/15/2021 | COT - LCBU - Roof Nailing | Passed | {Activity date: 03/15/2021; Status: Approved; Inspector: ESTEVENS; Comment: Entered by VLEON1 - } | |
| 03/26/2021 | COT - LCBU - Masonry Pregrout | Passed | {Activity date: 03/26/2021; Status: Approved; Inspector: BSTEVENS; Comment: Entered by BSTEVENS - OK TO TOP OF WALL} ; {Activity date: 03/01/2021; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by BSTEVENS - PARTIAL - North wall ok to grout to top. Verts and horizontals for bond and ledger bolts ok} ; {Activity date: 02/26/2021; Status: Approved; Inspector: ESTEVENS; Comment: Entered by BSTEVENS - PARTIAL GROUT 4TH LIFT 12 TO 16 FEET} ; {Activity date: 02/25/2021; Status: Partial Approval; Inspector: KCOCO; Comment: Entered by BSTEVENS - PARTIAL APPROVAL FOR NORTH WALL 3RD LIFT} ; {Activity date: 02/24/2021; Status: Cancelled; Inspector: ESTEVENS; Comment: Entered by VLEON1 - CANCELLED BY CONTRACTOR} ; {Activity date: 02/23/2021; Status: Partial Approval; Inspector: KCOCO; Comment: Entered by BSTEVENS - FIRST LIFT TO BOND BEAM AT TOP OF STEM AND AT WINDOW SILLS. 2ND LIFT FOR NORTH WALL ONLY} |
|
| 03/30/2021 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 03/30/2021; Status: Approved; Inspector: RELEFANTE; Comment: Entered by VLEON1 - CODE RECN} | |
| 03/30/2021 | COT - LCEL - Electrical Reconnect | Passed | {Activity date: 03/30/2021; Status: Approved; Inspector: RELEFANTE; Comment: Entered by VLEON1 - } ; {Activity date: 03/26/2021; Status: Cancelled; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - AP canceled} ; {Activity date: 03/15/2021; Status: Not Applicable; Inspector: ESTEVENS; Comment: Entered by VLEON1 - } | |
| 05/17/2021 | COT - LCBU - Building Final | Passed | {Activity date: 05/17/2021; Status: Approved; Inspector: ESTEVENS; Comment: Entered by VLEON1 - } | |
| 05/17/2021 | COT - LCBU - Preslab | Passed | {Activity date: 05/17/2021; Status: Approved; Inspector: ESTEVENS; Comment: Entered by VLEON1 - APPROVED BY DAN QUINN ON FEBRUARY 18, 2021} | |
| 05/17/2021 | COT - LCEL - Electrical Final | Passed | {Activity date: 05/17/2021; Status: Approved; Inspector: ESTEVENS; Comment: Entered by VLEON1 - } | |
| 05/17/2021 | COT - LCBU - Building Progress | Passed | {Activity date: 05/17/2021; Status: Approved; Inspector: ESTEVENS; Comment: Entered by VLEON1 - } ; {Activity date: 05/14/2021; Status: Cancelled; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - AP canceled} ; {Activity date: 03/15/2021; Status: Not Applicable; Inspector: ESTEVENS; Comment: Entered by VLEON1 - } | |
| 05/18/2021 | COT - FCON - Fire - Final | Passed | {Activity date: 05/18/2021; Status: Approved; Inspector: MRoss; Comment: Entered by MROSS2 - } ; {Activity date: 05/17/2021; Status: Partial Approval; Inspector: MRoss; Comment: Entered by MROSS2 - -Provide and mount fire extinguisher, minimum size 2A 10BC -Repair or remove non working exit signs.} |