Permit Details

Status:
Complete
Type:
Commercial Building
Address:
6360 S TUCSON BL
Address NEW:
6360 S TUCSON BL
Apply Date:
12/28/2020
Applicant:
Description:
New Warehouse Shell building

Permit Reviews

Permit Number - T20CM09060
Permit Status: Complete
Permit Description: New Warehouse Shell building
Start Date Submittal Complete Date Status  
02/18/2021 RESUBMITTAL 03/08/2021 COMPLETED Review Details
04/05/2021 3RD PARTY REVIEW - REVISION/OTHER 04/27/2021 COMPLETED Review Details
12/28/2020 3RD PARTY REVIEW - COMMERCIAL 02/16/2021 COMPLETED Review Details

Conditions

Permit Number - T20CM09060
Permit Status: Complete
Permit Description: New Warehouse Shell building
Date Description Comments
01/25/2021 SPECIAL INSPECTION FOR CONCRETE IS REQUIRED..
01/25/2021 SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED.
01/25/2021 SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED.
01/25/2021 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: T20CM09060
Permite Description: New Warehouse Shell building
Total Outstanding Inspections - 5
Last Inspection Date Description Inspector Results Comments
10/27/2021 COT - LCBU - Exterior Clips/Sheathing N/A Canceled {Activity date: 10/27/2021; Status: Not Applicable; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Not Applicable, tilt panel}
11/01/2021 COT - LCPL - Sewer N/A Canceled {Activity date: 11/01/2021; Status: Not Applicable; Inspector: TGAUSP; Comment: Entered by VVERA1 - NA}
01/11/2022 COT - LCPL - Medical Gas Preconstruction Mtg N/A Canceled {Activity date: 01/11/2022; Status: Not Applicable; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Not Applicable.}
10/27/2022 COT - LCBU - Building Final N/A Not Ready
10/26/2022 COT - LCME - Mechanical Final N/A Not Ready

Completed Inspections

Permit Status: Complete
Permit Number: T20CM09060
Permit Description: New Warehouse Shell building
Total Completed Inspections - 24
Date Description Inspector Results Comments
04/14/2021 COT - LCBU - Preslab Passed {Activity date: 04/14/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - }
08/03/2021 COT - LCBU - Excavation/Rebar/Zoning Passed {Activity date: 08/03/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - Approved, north and south end ramps} ; {Activity date: 07/07/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Partial, inspection for following tilt panels complete and ok for concrete placement. (1, 5)} ; {Activity date: 07/06/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Partial, Inspection for following tilt panels complete and ok for concrete placement. (2, 21, 53, 54).
} ; {Activity date: 06/30/2021; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by VLEON1 - Partial for panels #6, #12,and #18 panel reinforcement, okay to pour} ; {Activity date: 06/24/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VLEON1 - Partial, Inspection of following Tilt panels ok for concrete placement. (3, 4, 5, & 7).} ; {Activity date: 06/23/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VLEON1 - Partial, Exterior footings on East side complete and continued south, corrections made per previous notes.} ; {Activity date: 06/16/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VLEON1 - Partial, inspection of following tilt panels ok for concrete placement. (8,9,10,11,17,19,20). Inspection of Southwest exterior footings also ok for concrete placement. Note: Overlap rebar minimum of 36” where required.} ; {Activity date: 06/10/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VLEON1 - Partial, Inspection of following tilt panels ok for concrete placement. (13, 14, 15, 16).} ; {Activity date: 06/08/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VLEON1 - Partial, Perimeter footing installed from Column line J-3 to F-1 ok for concrete placement.} ; {Activity date: 06/04/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VLEON1 - Partial, no inspection today see previous notes.

} ; {Activity date: 06/03/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VLEON1 - Partial, Inspection of Re-bar for following tilt panels ok for concrete placement. (22, 23, 24, 25, 27).} ; {Activity date: 05/26/2021; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - Partial approval for tilt walls 44,47,24,28, and 29 ok for concrete placement

} ; {Activity date: 05/19/2021; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - Partial approval for tilt walls 35-40 inclusive

} ; {Activity date: 05/18/2021; Status: Cancelled; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - CANCELLED INSPECTION BY CONTRACTOR} ; {Activity date: 05/12/2021; Status: Cancelled; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - CANCELLED BY CONTRACTOR} ; {Activity date: 05/11/2021; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by VLEON1 - Partial. Tilt up rebar panels. Numbers 38, 39, 40, 42, 45, 43, 46, 48, 49, 50, 51.
} ; {Activity date: 05/10/2021; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by VLEON1 - } ; {Activity date: 05/07/2021; Status: Cancelled; Inspector: ESTEVENS; Comment: Entered by VLEON1 - CANCELLED BY CONTRACTOR} ; {Activity date: 05/11/2021; Status: Cancelled; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - RI canceled} ; {Activity date: 04/01/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VLEON1 - Partial, Column footings and grade beam ok for concrete placement.}
08/17/2021 COT - LCPL - Yard Water Line Passed {Activity date: 08/17/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved}
09/02/2021 COT - FCON - Underground Pressure Passed {Activity date: 09/02/2021; Status: Approved; Inspector: wmotto1; Comment: Entered by WMOTTO1 - 11. 200 lb pressure test and visual inspection of pipe ok to burry.}
09/16/2021 COT - LCBU - Roof Nailing Passed {Activity date: 09/16/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved, okay to roof

}
10/08/2021 COT - LCBU - Framing Passed {Activity date: 10/08/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved, okay to cover} ; {Activity date: 09/01/2021; Status: Not ready for Inspection; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Not ready}
11/01/2021 COT - LCPL - Plumbing Roof Drains Passed {Activity date: 11/01/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved}
11/01/2021 COT - LCPL - Plumbing Intermediate Passed {Activity date: 11/01/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved} ; {Activity date: 08/17/2021; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Not Ready.}
11/05/2021 COT - FCON - Underground Flush Passed {Activity date: 11/05/2021; Status: Approved; Inspector: wmotto1; Comment: Entered by WMOTTO1 - }
11/22/2021 COT - LCEL - Electrical Intermediate Passed {Activity date: 11/22/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved, 2500AMP SES & SUB Panels installed and feeders terminated @ SES.}
12/09/2021 PDSD Building Division - TEP PM Clearance Passed {Activity date: 12/09/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - CODE ECO (FIRE PUMP METER)} ; {Activity date: 11/22/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - CODE ECO for Meter 1 (House Panel)} ; {Activity date: 04/01/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VLEON1 - CODE TMPP}
01/11/2022 COT - LCEL - Electrical Underground Passed {Activity date: 01/11/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved.} ; {Activity date: 10/12/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Partial, underground conduits for site light poles ok to backfill progress areas.} ; {Activity date: 09/23/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial, no inspection required for today} ; {Activity date: 09/22/2021; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - Partial, secondary conduits from transformer to building} ; {Activity date: 09/21/2021; Status: Not ready for Inspection; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - NR, cancelled by Contractor} ; {Activity date: 04/01/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VLEON1 - Partial, Sweep for temp power ok to proceed.} ; {Activity date: 03/30/2021; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by VLEON1 - PA, 200’ interior conduits from the switch gear to panel locations, okay backfill} ; {Activity date: 03/19/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VLEON1 - Partial, Secondary Conduits from Transformer to Service entrance.}
01/11/2022 COT - LCEL - Construction Power Passed {Activity date: 01/11/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved.} ; {Activity date: 12/09/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Partial, Clear TEP ECO (FIRE PUMP METER)}
01/11/2022 COT - LCME - Mechanical Intermediate Passed {Activity date: 01/11/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved.}
01/11/2022 COT - LCEL - Grounding/Bonding Passed {Activity date: 01/11/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved.} ; {Activity date: 04/01/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VLEON1 - Partial, 2 ground rods and EGC installed at Temporary service.}
02/18/2022 COT - FCON - Alarm - Final Passed {Activity date: 02/18/2022; Status: Approved; Inspector: wmotto1; Comment: Entered by WMOTTO1 - }
02/18/2022 COT - FCON - Sprinkler - Final Passed {Activity date: 02/18/2022; Status: Approved; Inspector: wmotto1; Comment: Entered by WMOTTO1 - }
02/18/2022 FCON – OH Piping & Hydro Passed {Activity date: 02/18/2022; Status: Approved; Inspector: wmotto1; Comment: Entered by WMOTTO1 - }
02/22/2022 COT - LCEL - Electrical Final Passed {Activity date: 02/22/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} ; {Activity date: 01/11/2022; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Not Ready}
02/22/2022 COT - FCON - Fire - Final Passed {Activity date: 02/22/2022; Status: Approved; Inspector: wmotto; Comment: Entered by WMOTTO1 - } ; {Activity date: 02/03/2022; Status: Prior to Final Inspectn; Inspector: wmotto1; Comment: Entered by WMOTTO1 - 1. need temp control unit installed in the fire pump room.
2. Need Knox FDC caps on on the FDC.
3. need to test the bell}
02/22/2022 COT - LCPL - Plumbing Final Passed {Activity date: 02/22/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} ; {Activity date: 01/11/2022; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Not Ready} ; {Activity date: 11/01/2021; Status: Not ready for Inspection; Inspector: TGAUSP; Comment: Entered by VVERA1 - NR}
02/24/2022 COT - LCEL - Outdoor Lighting Passed {Activity date: 02/24/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved}
04/06/2022 COT - LCPL - Rough Soil Passed {Activity date: 04/06/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMUNIZ1 - } ; {Activity date: 04/01/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VLEON1 - Partial, Rough soil plumbing for two future TI’s installed and tested.} ; {Activity date: 03/24/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by RSALDAT1 - -AP

}
04/07/2022 ENGR Engineering Final Passed {Activity date: 04/07/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 02/25/2022; Status: Partial Approval; Inspector: DROBERTS; Comment: Entered by DROBERT5 - OK FOR TCO} ; {Activity date: 02/25/2022; Status: Prior to 1010/1015; Inspector: DROBERTS; Comment: Entered by DROBERT5 - OK FOR TCO STOCKING PURPOSES ONLY}

Documents

File Name Document Type  
FINAL SIC 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
REV1_1 REVISION LETTER 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
REVISION PLAN 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
LOFC_LETTEROFCOMPLETION.PDF DOCUMENTS VIEW
FINAL SIC.PDF DOCUMENTS VIEW
REV1_1 REVISION LETTER.PDF DOCUMENTS VIEW
REVISION PLAN.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW
CHECKLIST.PDF DOCUMENTS VIEW
THIRD PARTY PSA.PDF DOCUMENTS VIEW
SPECIAL INSPECTION CERT.PDF DOCUMENTS VIEW
LETTER.PDF DOCUMENTS VIEW
GEOTECH.PDF DOCUMENTS VIEW
STRUCTURAL CALCS.PDF DOCUMENTS VIEW
PLAN SITE.PDF CONSTRPLANS VIEW
PLAN SET.PDF CONSTRPLANS VIEW