| 08/03/2021 |
COT - LCBU - Excavation/Rebar/Zoning |
TGAUSP |
Approved |
Entered by RSALDAT1 - Approved, north and south end ramps |
| 07/07/2021 |
COT - LCBU - Excavation/Rebar/Zoning |
DMUNIZ |
Partial Approval |
Entered by RSALDAT1 - Partial, inspection for following tilt panels complete and ok for concrete placement. (1, 5) |
| 07/06/2021 |
COT - LCBU - Excavation/Rebar/Zoning |
DMUNIZ |
Partial Approval |
Entered by RSALDAT1 - Partial, Inspection for following tilt panels complete and ok for concrete placement. (2, 21, 53, 54).
|
| 06/30/2021 |
COT - LCBU - Excavation/Rebar/Zoning |
TGAUSP |
Partial Approval |
Entered by VLEON1 - Partial for panels #6, #12,and #18 panel reinforcement, okay to pour |
| 06/24/2021 |
COT - LCBU - Excavation/Rebar/Zoning |
DMUNIZ |
Partial Approval |
Entered by VLEON1 - Partial, Inspection of following Tilt panels ok for concrete placement. (3, 4, 5, & 7). |
| 06/23/2021 |
COT - LCBU - Excavation/Rebar/Zoning |
DMUNIZ |
Partial Approval |
Entered by VLEON1 - Partial, Exterior footings on East side complete and continued south, corrections made per previous notes. |
| 06/16/2021 |
COT - LCBU - Excavation/Rebar/Zoning |
DMUNIZ |
Partial Approval |
Entered by VLEON1 - Partial, inspection of following tilt panels ok for concrete placement. (8,9,10,11,17,19,20). Inspection of Southwest exterior footings also ok for concrete placement. Note: Overlap rebar minimum of 36” where required. |
| 06/10/2021 |
COT - LCBU - Excavation/Rebar/Zoning |
DMUNIZ |
Partial Approval |
Entered by VLEON1 - Partial, Inspection of following tilt panels ok for concrete placement. (13, 14, 15, 16). |
| 06/08/2021 |
COT - LCBU - Excavation/Rebar/Zoning |
DMUNIZ |
Partial Approval |
Entered by VLEON1 - Partial, Perimeter footing installed from Column line J-3 to F-1 ok for concrete placement. |
| 06/04/2021 |
COT - LCBU - Excavation/Rebar/Zoning |
DMUNIZ |
Partial Approval |
Entered by VLEON1 - Partial, no inspection today see previous notes.
|
| 06/03/2021 |
COT - LCBU - Excavation/Rebar/Zoning |
DMUNIZ |
Partial Approval |
Entered by VLEON1 - Partial, Inspection of Re-bar for following tilt panels ok for concrete placement. (22, 23, 24, 25, 27). |
| 05/26/2021 |
COT - LCBU - Excavation/Rebar/Zoning |
WGALLAGHER |
Partial Approval |
Entered by VLEON1 - Partial approval for tilt walls 44,47,24,28, and 29 ok for concrete placement
|
| 05/19/2021 |
COT - LCBU - Excavation/Rebar/Zoning |
WGALLAGHER |
Partial Approval |
Entered by VLEON1 - Partial approval for tilt walls 35-40 inclusive
|
| 05/18/2021 |
COT - LCBU - Excavation/Rebar/Zoning |
WGALLAGHER |
Cancelled |
Entered by VLEON1 - CANCELLED INSPECTION BY CONTRACTOR |
| 05/12/2021 |
COT - LCBU - Excavation/Rebar/Zoning |
WGALLAGHER |
Cancelled |
Entered by VLEON1 - CANCELLED BY CONTRACTOR |
| 05/11/2021 |
COT - LCBU - Excavation/Rebar/Zoning |
ESTEVENS |
Partial Approval |
Entered by VLEON1 - Partial. Tilt up rebar panels. Numbers 38, 39, 40, 42, 45, 43, 46, 48, 49, 50, 51.
|
| 05/10/2021 |
COT - LCBU - Excavation/Rebar/Zoning |
DMUNIZ |
Not ready for Inspection |
Entered by VLEON1 - |
| 05/07/2021 |
COT - LCBU - Excavation/Rebar/Zoning |
ESTEVENS |
Cancelled |
Entered by VLEON1 - CANCELLED BY CONTRACTOR |
| 05/11/2021 |
COT - LCBU - Excavation/Rebar/Zoning |
IVR USER |
Cancelled |
Entered by IVR USER - IVRS - RI canceled |
| 04/01/2021 |
COT - LCBU - Excavation/Rebar/Zoning |
DMUNIZ |
Partial Approval |
Entered by VLEON1 - Partial, Column footings and grade beam ok for concrete placement. |