Inspection Status: Passed
Inspection History: COT - LCEL - Electrical Underground
| Date |
Description |
Inspector |
Results |
Comments |
| 01/11/2022 |
COT - LCEL - Electrical Underground |
DMUNIZ |
Approved |
Entered by RSALDAT1 - Approved. |
| 10/12/2021 |
COT - LCEL - Electrical Underground |
DMUNIZ |
Partial Approval |
Entered by VVERA1 - Partial, underground conduits for site light poles ok to backfill progress areas. |
| 09/23/2021 |
COT - LCEL - Electrical Underground |
DMUNIZ |
Partial Approval |
Entered by NGARCIA3 - Partial, no inspection required for today |
| 09/22/2021 |
COT - LCEL - Electrical Underground |
TGAUSP |
Partial Approval |
Entered by RSALDAT1 - Partial, secondary conduits from transformer to building |
| 09/21/2021 |
COT - LCEL - Electrical Underground |
TGAUSP |
Not ready for Inspection |
Entered by RSALDAT1 - NR, cancelled by Contractor |
| 04/01/2021 |
COT - LCEL - Electrical Underground |
DMUNIZ |
Partial Approval |
Entered by VLEON1 - Partial, Sweep for temp power ok to proceed. |
| 03/30/2021 |
COT - LCEL - Electrical Underground |
TGAUSP |
Partial Approval |
Entered by VLEON1 - PA, 200’ interior conduits from the switch gear to panel locations, okay backfill |
| 03/19/2021 |
COT - LCEL - Electrical Underground |
DMUNIZ |
Partial Approval |
Entered by VLEON1 - Partial, Secondary Conduits from Transformer to Service entrance. |