Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T20CM06301
Permit Details
Status:
Inspections
Type:
Commercial Building
Address:
9013 E OLD VAIL RD BLDG 8
Address NEW:
9013 E OLD VAIL RD BLDG 8
Apply Date:
09/14/2020
Applicant:
les Martin
Description:
TI: WHITE BOX
Permit Reviews
Permit Number - T20CM06301
Permit Status: Inspections
Permit Description: TI: WHITE BOX
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/07/2022 | RESUBMITTAL | 03/02/2022 | COMPLETED |
| 03/14/2022 | RESUBMITTAL | 03/22/2022 | COMPLETED |
| 03/29/2022 | RESUBMITTAL | 04/15/2022 | COMPLETED |
| 10/14/2020 | COMMERCIAL - TI | 11/25/2020 | COMPLETED |
| 12/06/2021 | RESUBMITTAL - TI ALL | 01/04/2022 | COMPLETED |
| 11/01/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 11/05/2023 | APPROVED |
Outstanding Activity Conditions
Permit Number - T20CM06301
Permit Status: Inspections
Permit Description: TI: WHITE BOX
Total Outstanding Activity Conditions - 5
| Date | Name |
|---|---|
| 09/14/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
| 10/14/2020 | SPECIAL INSPECTION FORMS AND REPORTS REQUIRED PRIOR TO ISSUANCE OF A CERTIFICATE OF OCCUPANCY. |
| 10/14/2020 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. |
| 10/14/2020 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. |
| 10/14/2020 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. |
Conditions
Permit Number - T20CM06301
Permit Status: Inspections
Permit Description: TI: WHITE BOX
| Date | Description | Comments |
|---|---|---|
| 10/14/2020 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. | |
| 12/15/2021 | SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED. | |
| 11/03/2023 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
| 11/03/2023 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 11/03/2023 | SPECIAL INSPECTION FOR SPECIAL MOMENT RESISTING STEEL FRAMES IS REQUIRED. |
Outstanding Inspections
Permit Status: Inspections
Permit Number: T20CM06301
Permite Description: TI: WHITE BOX
Total Outstanding Inspections - 8
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/26/2022 | COT - LCEL - Electrical Intermediate | N/A | Not Ready | |
| 10/26/2022 | COT - LCME - Mechanical Intermediate | N/A | Not Ready | |
| 10/27/2022 | COT - LCPL - Plumbing Intermediate | N/A | Not Ready | |
| 10/09/2023 | COT - LCBU - Building Above Ceiling | N/A | Not Applicable | |
| 10/09/2023 | COT - LCBU - Sustainability | N/A | Not Applicable | |
| 10/09/2023 | COT - LCEL - Temporary Service | N/A | Not Applicable | |
| 10/09/2023 | COT - LCEL - Electrical Underground | N/A | Not Applicable | |
| 10/09/2023 | COT - LCEL - Electrical Above Ceiling | N/A | Not Applicable |
Completed Inspections
Permit Status: Inspections
Permit Number: T20CM06301
Permit Description: TI: WHITE BOX
Total Completed Inspections - 18
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/14/2022 | COT - LCPL - Rough Soil | Passed | {Activity date: 07/14/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
| 07/27/2022 | COT - LCBU - Preslab | Passed | {Activity date: 07/27/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} ; {Activity date: 07/26/2022; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Not Ready} | |
| 07/27/2022 | COT - LCBU - Exterior Clips/Sheathing | Passed | {Activity date: 07/27/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
| 01/04/2023 | COT - LCEL - Electrical Intermediate | Passed | ||
| 01/04/2023 | COT - LCME - Mechanical Intermediate | Passed | ||
| 01/04/2023 | COT - LCPL - Plumbing Intermediate | Passed | ||
| 06/09/2023 | COT - LCEL - Construction Power | Passed | TEP ECO | |
| 07/10/2023 | BULD - Electrical Clearance | Passed | Building 8 - ECO Clearances to TEP are required for 3 meters (units 8119, 8139, 8169) | |
| 10/09/2023 | COT - LCPL - Plumbing Final | Passed | ||
| 10/09/2023 | COT - LCBU - Excavation/Rebar/Zoning | Passed | ||
| 10/09/2023 | COT - LCEL - Electrical Final | Passed | ||
| 10/09/2023 | COT - LCBU - Building Progress | Passed | ||
| 10/09/2023 | COT - LCME - Mechanical Final | Passed | ||
| 10/09/2023 | COT - LCBU - Framing | Passed | ||
| 10/09/2023 | COT - LCEL - Outdoor Lighting | Passed | ||
| 10/16/2023 | COT - FCON - Fire - Final | Passed | ||
| 10/16/2023 | COT - LCBU - Firewall/Fire Barrier/Firestop | Passed | ||
| 02/26/2025 | COT - LCBU - Building Final | Passed | 10/2/23: building is not ADA compliant. 11/2/23: OK to issue TCO level 4 2/26/25: OK For CofO. Pending conditions. |