Permit: T20CM06162
Permit Details
Apply Date:
09/09/2020
Applicant:
Andrew Cook
Description:
EXTERIOR AND INTERIOR RENOVATION
Permit Reviews
Permit Number - T20CM06162
Permit Status: Complete
Permit Description: EXTERIOR AND INTERIOR RENOVATION
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/14/2022 | REVISION - - 2ND | 05/03/2022 | COMPLETED |
| 04/28/2021 | RESUBMITTAL | 07/09/2021 | COMPLETED |
| 05/03/2022 | REVISION - - 2ND | 05/09/2022 | COMPLETED |
| 07/14/2021 | RESUBMITTAL | 07/28/2021 | COMPLETED |
| 07/28/2021 | RESUBMITTAL | 08/02/2021 | COMPLETED |
| 09/04/2020 | COMMERCIAL - TI | 11/04/2020 | COMPLETED |
| 11/04/2020 | RESUBMITTAL | 12/08/2020 | COMPLETED |
| 11/10/2021 | REVISION - - 1ST | 11/12/2021 | COMPLETED |
| 11/23/2021 | REVISION - - 1ST | 12/07/2021 | COMPLETED |
| 12/08/2021 | REVISION - - 1ST | 12/14/2021 | COMPLETED |
| 12/15/2021 | REVISION - - 1ST | 12/15/2021 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T20CM06162
Permit Status: Complete
Permit Description: EXTERIOR AND INTERIOR RENOVATION
Total Outstanding Activity Conditions - 2
| Date | Name |
|---|---|
| 02/05/2021 | FUP T20OT00715 MUST BE PAID AND ISSUED BEFORE FINAL INSPECTIONS. |
| 09/09/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T20CM06162
Permite Description: EXTERIOR AND INTERIOR RENOVATION
Total Outstanding Inspections - 5
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/26/2022 | COT - LCME - Mechanical Final | N/A | Not Ready | |
| 10/26/2022 | COT - LCBU - Exterior Clips/Sheathing | N/A | Not Ready | |
| 10/26/2022 | COT - LCPL - Plumbing Final | N/A | Not Ready | |
| 10/26/2022 | COT - LCBU - Roof Nailing | N/A | Not Ready | |
| 10/26/2022 | COT - LCBU - Building Progress | N/A | Not Ready |
Completed Inspections
Permit Status: Complete
Permit Number: T20CM06162
Permit Description: EXTERIOR AND INTERIOR RENOVATION
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/22/2021 | COT - LCPL - Rough Soil | Passed | {Activity date: 12/22/2021; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved} | |
| 12/22/2021 | COT - LCPL - Sewer | Passed | {Activity date: 12/22/2021; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved. Ok to cover progress areas.} | |
| 01/14/2022 | COT - LCEL - Electrical Underground | Passed | {Activity date: 01/14/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved 147 W SIMPSON ST} ; {Activity date: 01/14/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved 143 W SIMPSON ST} ; {Activity date: 01/14/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved 141 W SIMPSON ST} |
|
| 08/09/2022 | COT - LCEL - Electrical Intermediate | Passed | {Activity date: 08/09/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. 143 W SIMPSON ST} ; {Activity date: 08/09/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved 147 W SIMPSON ST} ; {Activity date: 08/09/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved 141 W SIMPSON ST} |
|
| 08/09/2022 | COT - LCBU - Framing | Passed | {Activity date: 08/09/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. Ok to insulate and cover walls. 143 W SIMPSON ST} ; {Activity date: 08/09/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. Ok to insulate and cover walls. 147 W SIMPSON ST} ; {Activity date: 08/09/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. Ok to insulate and cover walls. 141 W SIMPSON ST} |
|
| 08/09/2022 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 08/09/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. 143 W SIMPSON ST} ; {Activity date: 08/09/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved 147 W SIMPSON ST} ; {Activity date: 08/09/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved 141 W SIMPSON ST} |
|
| 08/09/2022 | COT - LCME - Mechanical Intermediate | Passed | {Activity date: 08/09/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. 143 W SIMPSON ST} ; {Activity date: 08/09/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved 147 W SIMPSON ST} ; {Activity date: 08/09/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved 141 W SIMPSON ST} |
|
| 08/30/2022 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 08/30/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - CODE INCR/CUTOVER 147 W SIMPSON ST} ; {Activity date: 08/30/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - CODE INCR/CUTOVER 141 W SIMPSON ST} ; {Activity date: 08/30/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - CODE INCR/CUTOVER 143 W SIMPSON ST} | |
| 08/30/2022 | COT - LCEL - Service Upgrade | Passed | {Activity date: 08/30/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap Clear incr for cutover 147 W SIMPSON ST} ; {Activity date: 08/30/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap Clear incr for cutover 141 W SIMPSON ST} ; {Activity date: 08/30/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap Clear incr for cutover 143 W SIMPSON ST} |
|
| 09/30/2022 | COT - HCBU - Exterior Clips/Sheathing | Passed | {Activity date: 09/30/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved. Ok to apply scratch coat.} ; {Activity date: 09/30/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved. Ok to apply scratch coat.} ; {Activity date: 09/30/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved. Ok to apply scratch coat.} | |
| 02/09/2023 | COT - LCME - Mechanical Final | Passed | ||
| 02/09/2023 | COT - LCBU - Exterior Clips/Sheathing | Passed | ||
| 02/09/2023 | COT - LCPL - Plumbing Final | Passed | ||
| 02/09/2023 | COT - LCBU - Roof Nailing | Passed | ||
| 02/09/2023 | COT - LCBU - Building Progress | Passed | ||
| 02/09/2023 | COT - LCEL - Electrical Above Ceiling | Passed | ||
| 02/09/2023 | COT - LCEL - Construction Power | Passed | Permanent power has been issued. | |
| 02/09/2023 | COT - LCPL - Yard Water Line | Passed | ||
| 02/09/2023 | COT - LCEL - Temporary Service | Passed | ||
| 02/09/2023 | COT - LCBU - Building Final | Passed | ||
| 02/09/2023 | COT - LCEL - Grounding/Bonding | Passed | ||
| 02/09/2023 | COT - LCEL - Outdoor Lighting | Passed | ||
| 02/09/2023 | COT - LCEL - Electrical Final | Passed |