Permit: T20CM05670
Permit Details
Apply Date:
08/30/2020
Applicant:
N/A
Description:
NEW LIGHTING VAULT FOR TUCSON AIRPORT
Architects:
- FOREMAN, LISA KAY
Contractors:
- MARGARET MIEZIO
Permit Reviews
Permit Number - T20CM05670
Permit Status: L of c
Permit Description: NEW LIGHTING VAULT FOR TUCSON AIRPORT
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
08/04/2020 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 10/06/2020 | COMPLETED |
11/24/2020 | RESUBMITTAL | 12/30/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T20CM05670
Permit Status: L of c
Permit Description: NEW LIGHTING VAULT FOR TUCSON AIRPORT
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
08/30/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T20CM05670
Permit Description: NEW LIGHTING VAULT FOR TUCSON AIRPORT
Total Completed Inspections - 16
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/05/2021 | EXCAVATION/LAYOUT REBAR & ZON | ESTEVENS | Approved | APPROVED |
02/10/2021 | STEM WALL/RETAINING WALL | WGALLAGHER | Approved | APPROVED, OK FOR CONCRETE PLACEMENT |
03/17/2021 | REINFORCED MASONRY PRE-GROUT | DMUNIZ | Approved | Approved |
07/09/2021 | FRAMING | DMUNIZ | Approved | Approved, framing for control room complete. |
08/13/2021 | ELECTRIC - SERVICE UPGRADE | DMUNIZ | Approved | Approved clear TEP ECO Note: Clearance is for following Address (1871 E Aero Park Blvd.) Permit address needs to be updated to reflect correct address. Disclosed to contractor that this need to be completed, TEP and Pima County recognize New address COT can update once documentation has been provided. |
08/20/2021 | TEP CLEARANCE - PM | DMUNIZ | Approved | CODE ECO |
08/20/2021 | ELECTRIC - CONSTRUCTION POWER | DMUNIZ | Approved | Approved clear TEP ECO. Note: please expedite clearance to TEP, clearance was sent in prior under different address. Address has been corrected on the permit. |
09/14/2021 | MECHANICAL - FINAL | TGAUSP | Approved | Approved |
09/21/2021 | MECHANICAL - INTERMEDIATE | DMUNIZ | Approved | Approved |
09/21/2021 | ELECTRIC - INTERMEDIATE | DMUNIZ | Approved | Approved |
09/21/2021 | BUILDING - PROGRESS | DMUNIZ | Approved | Approved |
09/21/2021 | ELECTRIC - UNDERGROUND | DMUNIZ | Approved | Approved |
09/21/2021 | ELECTRIC - UFER | DMUNIZ | Approved | Approved |
09/21/2021 | BUILDING PRE-SLAB | DMUNIZ | Approved | Approved |
09/21/2021 | ELECTRIC - FINAL | DMUNIZ | Approved | Approved |
10/21/2021 | BUILDING - FINAL | DMUNIZ1 | Approved |