Inspection Status: Approved
Inspection History: REINFORCED MASONRY PRE-GROUT
| Date |
Description |
Inspector |
Results |
Comments |
| 03/17/2021 |
REINFORCED MASONRY PRE-GROUT |
|
Approved |
Approved |
| 03/16/2021 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
Partial, Top out on East Exterior walls ok for grout. |
| 03/12/2021 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
Partial, 2nd lift Interior CMU walls, 3rd lift exterior west wall all ok for grout. |
| 03/09/2021 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
PARTIAL 3RD LIFT OF SOUTH END AT TOP OUT ON NORTH SIDE OF BUILDING OK FOR GROUT |
| 03/05/2021 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
Partial, 1st lift on exterior pop outs and interior walls. 2nd lift for exterior walls ok to grout and proceed. |
| 03/03/2021 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
PARTIAL, 1ST LIFT OK TO GROUT AND PROCEED WITH 2ND LIFT |