Permit Details

Status:
C of o
Type:
COMMERCIAL NEW
Apply Date:
06/16/2020
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
NEW GREENHOUSE BLDG

Permit Reviews

Permit Number - T20CM03686
Permit Status: C of o
Permit Description: NEW GREENHOUSE BLDG
Start Date Submittal Complete Date Status  
06/16/2020 PLANS OK TO SUBMIT - COMM 08/03/2020 COMPLETED Review Details
08/03/2020 COMMERCIAL - NEW 08/06/2020 COMPLETED Review Details
08/06/2020 3RD PARTY REVIEW - COMMERCIAL 09/17/2020 COMPLETED Review Details
09/17/2020 RESUBMITTAL 10/19/2020 COMPLETED Review Details
10/19/2020 RESUBMITTAL 11/05/2020 COMPLETED Review Details
11/05/2020 RESUBMITTAL 11/18/2020 COMPLETED Review Details
12/01/2020 3RD PARTY REVIEW - REVISION/OTHER 02/24/2021 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T20CM03686
Permit Status: C of o
Permit Description: NEW GREENHOUSE BLDG
Total Outstanding Activity Conditions - 1
Date Name
06/16/2020 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T20CM03686
Permit Description: NEW GREENHOUSE BLDG
Total Completed Inspections - 38
Date Description Inspector Results Comments
12/15/2020 BUILDING - PROGRESS DQUINN Approved PARTIAL - 10 NORTH SIDE COLUMN FOOTINGS OK TO POUR
12/17/2020 PLUMBING - ROUGH, SOIL DQUINN Approved 4 bathrooms and a couple of separate sinks ok to backfill.
12/17/2020 ELECTRIC - UNDERGROUND DQUINN Approved Underground high and low voltage conduits, color coded, ok to backfill between south columns and over to the gutter area on the head house.
04/27/2021 EXT METAL CLIPS/EXT SHEATHING DQUINN Approved
04/27/2021 MECHANICAL - INTERMEDIATE DQUINN Approved
04/27/2021 ELECTRIC - INTERMEDIATE DQUINN Approved
04/27/2021 FRAMING DQUINN Approved
08/13/2021 TEP CLEARANCE - PM DQUINN Approved CODE GAS
08/13/2021 PLUMBING - GAS PRESS TEST FNL DQUINN Approved Ap
3 1/2 “ main, running on the north side of the green houses, feeding all green house heaters, ok .
11/30/2021 EXCAVATION/LAYOUT REBAR & ZON DQUINN Approved Ap
11/30/2021 BUILDING PRE-SLAB DQUINN Approved Ap
11/30/2021 ELECTRIC - UFER DQUINN Approved Ap
11/30/2021 ELECTRIC - ABOVE CEILING DQUINN Approved Ap
11/30/2021 ELECTRIC - PROGRESS DQUINN Approved Ap
11/30/2021 ELECTRIC - SERVICE UPGRADE DQUINN Approved Ap
11/30/2021 ELECTRIC - FINAL DQUINN Approved Ap
11/30/2021 PLUMBING - FINAL DQUINN Approved Ap
11/30/2021 MECHANICAL - FINAL DQUINN Approved Ap
12/02/2021 NPPO - FINAL BBENEDON Approved Approved. John with Barker contracting at 909-6352 will complete the required work shown on the development package and will schedule inspections from the development package permit for the remainder of site work.
12/02/2021 SIGN - FINAL BBENEDON Approved Approved. John with Barker contracting at 909-6352 will complete the required work shown on the development package and will schedule inspections from the development package permit for the remainder of site work.
12/02/2021 LANDSCAPE - FINAL BBENEDON Approved Approved. John with Barker contracting at 909-6352 will complete the required work shown on the development package and will schedule inspections from the development package permit for the remainder of site work.
12/02/2021 ENGINEERING - FINAL BBENEDON Approved Approved. John with Barker contracting at 909-6352 will complete the required work shown on the development package and will schedule inspections from the development package permit for the remainder of site work.
12/02/2021 RIGHT OF WAY - FINAL Bravin Approved no ROW issues. PSE archery
12/07/2021 FIRE - ALARM FINAL MRoss Approved
12/14/2021 BUILDING - FINAL DQUINN Approved
12/14/2021 BUILDING - FINAL DQUINN Approved APPROVED BY INSPECTOR
AWAITING CONDITIONS
12/14/2021 PLUMBING - GAS PRESSURE TEST DQUINN Approved Ap
12/14/2021 GAS CLEARANCE DQUINN Approved CODE
12/14/2021 PLUMBING - INTERMEDIATE DQUINN Approved Ap
12/14/2021 PLUMBING - ABOVE CEILING DQUINN Approved Ap
12/14/2021 PLUMBING - PRE SLAB DQUINN Approved Ap
12/14/2021 OUTDOOR LIGHTING FINAL DQUINN Approved Ap
12/14/2021 SITE - SEWER DQUINN Approved Ap
12/14/2021 PLUMBING - PROGRESS DQUINN Approved Ap
12/14/2021 MECHANICAL - ABOVE CEILING DQUINN Approved Ap
12/14/2021 MECHANICAL - PROGRESS DQUINN Approved Ap
12/14/2021 FIRE - FINAL MRoss Approved
12/14/2021 FIRE SPKLR - FINAL MRoss Approved