Permit: T20CM03686

Parcel: 10707003H

Inspection Status: Approved

Inspection History: BUILDING - PROGRESS

Date Description Inspector Results Comments
11/30/2021 BUILDING - PROGRESS Approved Ap
01/07/2021 BUILDING - PROGRESS Cancelled Cancel.
12/15/2020 BUILDING - PROGRESS Partial Approval PARTIAL - 10 NORTH SIDE COLUMN FOOTINGS OK TO POUR
12/11/2020 BUILDING - PROGRESS Partial Approval pa. Column footings around the head house, intermittent columns at the south elevation, and along the mid-south line, ok to pour.
12/08/2020 BUILDING - PROGRESS Partial Approval pa. Ok to pour 44 column footings from north center to east
12/04/2020 BUILDING - PROGRESS Partial Approval PA 46 post footings, completing 2 south rows and starting the next 2 rows to the north. Ok to pour.
12/01/2020 BUILDING - PROGRESS Partial Approval From s.w. Corner east - ok to pour 4 rows of 11 columns per row
11/30/2020 BUILDING - PROGRESS Denied Denied. No messages, no contractor listed. Please contact your inspector for further information to set up a video inspection.