Inspection Status: Approved
Inspection History: ELECTRIC - UNDERGROUND
| Date |
Description |
Inspector |
Results |
Comments |
| 11/30/2021 |
ELECTRIC - UNDERGROUND |
|
Approved |
Ap |
| 02/23/2021 |
ELECTRIC - UNDERGROUND |
|
Partial Approval |
PARTIAL - 12 conduits from greenhouses 1 2, to future n. side switch gear, ok to backfill. |
| 01/19/2021 |
ELECTRIC - UNDERGROUND |
|
Partial Approval |
PARTIAL UNDERGOUND ON NORTH SIDE OF TO BACKFILL |
| 01/07/2021 |
ELECTRIC - UNDERGROUND |
|
Partial Approval |
Partial. From breezeway transformer to SES. From SES to high-voltage panel. From SES high voltage lighting north and south sides |
| 12/17/2020 |
ELECTRIC - UNDERGROUND |
|
Partial Approval |
Underground high and low voltage conduits, color coded, ok to backfill between south columns and over to the gutter area on the head house. |
| 11/20/2020 |
ELECTRIC - UNDERGROUND |
|
Partial Approval |
Underground conduit from main building to greenhouse ok to backfill. |