Permit: T19CM08781
Permit Details
Apply Date:
11/27/2019
Applicant:
LANNING, ROBERT SCOTT
Description:
APARTMENTS
Contractors:
- DURAZO CONSTRUCTION
Permit Reviews
Permit Number - T19CM08781
Permit Status: C of o
Permit Description: APARTMENTS
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/22/2020 | RESUBMITTAL | 03/23/2020 | COMPLETED |
11/27/2019 | PLANS OK TO SUBMIT - COMM | 12/03/2019 | COMPLETED |
12/03/2019 | COMMERCIAL - TI | 01/22/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM08781
Permit Status: C of o
Permit Description: APARTMENTS
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
11/27/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T19CM08781
Permit Description: APARTMENTS
Total Completed Inspections - 35
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/16/2020 | PLUMBING - ROUGH, SOIL | TVALENCIA | Approved | approved 1- DWV water test provided, this inspection is for the bldg drain for all units up to P.O.C to bldg. sewer except Units A & C. |
06/24/2020 | EXT METAL CLIPS/EXT SHEATHING | TVALENCIA | Approved | partial 1- Shear walls and exterior clips on parapets and roof okay. |
07/02/2020 | PLUMBING - ROOF DRAINS | TVALENCIA | Approved | partial. 1- Rain water conductors water test provided. 2- Shall provide Roof Drain deck collars. |
07/09/2020 | BUILDING PRE-SLAB | TTREMBULAK | Approved | partial 1- Steel reinforcement is okay for concrete for the East and West Stairwell footings and the exterior West wall footing. |
09/25/2020 | MECHANICAL - INTERMEDIATE | ESTEVENS | Approved | Approved. |
09/25/2020 | PLUMBING - INTERMEDIATE | ESTEVENS | Approved | Approved. |
09/25/2020 | ELECTRIC - ABOVE CEILING | ESTEVENS | Approved | Approved. |
09/25/2020 | ELECTRIC - INTERMEDIATE | ESTEVENS | Approved | Approved. |
09/25/2020 | BUILDING ABOVE CEILING | ESTEVENS | Approved | Approved. |
09/25/2020 | FRAMING | ESTEVENS | Approved | Approved. |
09/29/2020 | EXCAVATION/LAYOUT REBAR & ZON | WGALLAGHER | Approved | Partial approval for one light pole base |
10/06/2020 | ELECTRIC - UNDERGROUND | ESTEVENS | Approved | Approved. |
10/09/2020 | REINFORCED MASONRY PRE-GROUT | ESTEVENS | Approved | Partial . West side site wall. |
10/19/2020 | STUCCO MESH | ESTEVENS | Approved | APPROVED. |
10/28/2020 | BUILDING - PROGRESS | JBURGE | Approved | Partial. Soffits in apartment units and commercial units: electric and plumbing in soffits. Ok to cover progress areas. |
10/28/2020 | FIREWALL/FIREBARRIER/FIRESTOP | JBURGE | Approved | Partial. Bathroom ceilings in apartments and commercial areas. |
11/23/2020 | PLUMBING - YARD WTR LINE/TEST | ESTEVENS | Approved | |
12/16/2020 | ELECTRIC - PROGRESS | RBOOHER | Approved | Partial. Approved grounding only, INCR - Ok to set meter at service panel. |
12/18/2020 | TEP CLEARANCE - PM | RBOOHER | Approved | CODE INCR/UNITS 101, 102, 103, 104, 105, 106, 107, 108, 109, 110, 111, 112, 113, 114, 150, 160, 201, 202, 203, 215, 216, |
03/26/2021 | FIRE SPKLR - FINAL | wmotto1 | Approved | |
03/26/2021 | FIRE - ALARM FINAL | wmotto1 | Approved | |
04/02/2021 | U VALUE FOR WINDOW | JBURGE | Approved | . Approved |
04/02/2021 | ELECTRIC - UFER | JBURGE | Approved | 2090 |
04/02/2021 | ELECTRIC - TEMPORARY SERVICE | JBURGE | Approved | 2090 |
04/02/2021 | ELECTRIC - CONSTRUCTION POWER | JBURGE | Approved | 2090 |
04/02/2021 | ELECTRIC - SERVICE UPGRADE | JBURGE | Approved | 2090 |
04/02/2021 | ELECTRIC - OUTDOOR LIGHTING | JBURGE | Approved | 2090 |
04/02/2021 | ELECTRIC - FINAL | JBURGE | Approved | . Approved |
04/02/2021 | OUTDOOR LIGHTING FINAL | JBURGE | Approved | . Approved |
04/02/2021 | PLUMBING - FINAL | JBURGE | Approved | . Approved |
04/02/2021 | MECHANICAL - FINAL | JBURGE | Approved | . Approved |
04/13/2021 | CERTIFICATE OF OCCUPANCY | JBURGE | Approved | |
04/13/2021 | BUILDING - FINAL | JBURGE | Approved | APPROVED PENDING ENGINEERING FINAL |
04/14/2021 | FIRE - FINAL | CBASALDUA | Approved | |
05/21/2021 | ENGINEERING - FINAL | DROBERTS | Approved |