Permit: T19CM07239
Permit Details
Status:
Expired
Type:
Residential Building - One or Two Family
Address:
2864 N FAIR OAKS AV
Address NEW:
2864 N FAIR OAKS AV
Apply Date:
10/03/2019
Applicant:
Description:
NEW SFR: CORN150019 T19-M0094
Permit Reviews
Permit Number - T19CM07239
Permit Status: Expired
Permit Description: NEW SFR: CORN150019 T19-M0094
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/03/2019 | RESIDENTIAL - BLDG/ZONING-WALKTHRU | 10/22/2019 | COMPLETED |
| 10/22/2019 | REVISION - - 1ST | 10/22/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM07239
Permit Status: Expired
Permit Description: NEW SFR: CORN150019 T19-M0094
Total Outstanding Activity Conditions - 2
| Date | Name |
|---|---|
| 10/03/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
| 10/03/2019 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
Conditions
Permit Number - T19CM07239
Permit Status: Expired
Permit Description: NEW SFR: CORN150019 T19-M0094
| Date | Description | Comments |
|---|---|---|
| 10/03/2019 | ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I) |
Outstanding Inspections
Permit Status: Expired
Permit Number: T19CM07239
Permite Description: NEW SFR: CORN150019 T19-M0094
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/19/2019 | COT - LCPL - Plumbing Roof Drains | N/A | Canceled | {Activity date: 12/19/2019; Status: Not Applicable; Inspector: RCHANDLER; Comment: Entered by DMERANZ1 - } |
| 12/19/2019 | RSPL - Plumbing Progress | N/A | Canceled | {Activity date: 12/19/2019; Status: Not Applicable; Inspector: RCHANDLER; Comment: Entered by DMERANZ1 - } |
Completed Inspections
Permit Status: Expired
Permit Number: T19CM07239
Permit Description: NEW SFR: CORN150019 T19-M0094
Total Completed Inspections - 24
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/08/2019 | COT - RSPL - Rough Soil | Passed | {Activity date: 10/08/2019; Status: Approved; Inspector: JCLAXTON; Comment: Entered by DMERANZ1 - Ok to bury.} | |
| 10/23/2019 | COT - RSBU - Preslab | Passed | {Activity date: 10/23/2019; Status: Approved; Inspector: RCHANDLER; Comment: Entered by DMERANZ1 - Fire walls added to resolve corrections.} ; {Activity date: 10/17/2019; Status: Correction Required; Inspector: RCHANDLER; Comment: Entered by DMERANZ1 - 1-The forms for this house will put the concrete six feet from the adjacent house; both walls are unrated with openings, which does not meet the requirements of IRC R Section R302.1 Exterior walls. REVISE Section by DELETING all text and tables (TABLE R302.1(1) EXTERIOR WALLS and TABLE R302.1(2) EXTERIOR WALLS-DWELLINGS WITH FIRE SPRINKLERS) and REPLACING with the following: Exterior walls with a fire separation distance less than 3 feet (914mm) shall have not less than a one- hour fire-resistive rating with exposure from both sides. Projections shall not extend to a point closer than 2 feet (610 mm) from the line used to determine the fire separation distance. Projections extending into the fire separation distance shall have not less than one-hour fire-resistive construction on the underside. The above provisions shall not apply to walls which are perpendicular to the line used to determine the fire separation distance.} |
|
| 10/23/2019 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 10/23/2019; Status: Approved; Inspector: RCHANDLER; Comment: Entered by DMERANZ1 - Note: Fire walls added to this lot due to being too close to property lines.} ; {Activity date: 10/17/2019; Status: Correction Required; Inspector: RCHANDLER; Comment: Entered by DMERANZ1 - 1-The forms for this house will put the concrete six feet from the adjacent house; both walls are unrated with openings, which does not meet the requirements of IRC R Section R302.1 Exterior walls. REVISE Section by DELETING all text and tables (TABLE R302.1(1) EXTERIOR WALLS and TABLE R302.1(2) EXTERIOR WALLS-DWELLINGS WITH FIRE SPRINKLERS) and REPLACING with the following: Exterior walls with a fire separation distance less than 3 feet (914mm) shall have not less than a one- hour fire-resistive rating with exposure from both sides. Projections shall not extend to a point closer than 2 feet (610 mm) from the line used to determine the fire separation distance. Projections extending into the fire separation distance shall have not less than one-hour fire-resistive construction on the underside. The above provisions shall not apply to walls which are perpendicular to the line used to determine the fire separation distance.} |
|
| 11/18/2019 | COT - RSBU - Roof Nailing | Passed | {Activity date: 11/18/2019; Status: Approved; Inspector: RCHANDLER; Comment: Entered by DMERANZ1 - } ; {Activity date: 11/08/2019; Status: Not ready for Inspection; Inspector: DQUINN; Comment: Entered by DMERANZ1 - Need access to roof, preferably from inside 2nd floor. } |
|
| 11/27/2019 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | {Activity date: 11/27/2019; Status: Approved; Inspector: RCHANDLER; Comment: Entered by DMERANZ1 - Inspected via Face-Time. Per Builder and Inspection Supervisor openings can be recessed, and will be complete for inspection at intermediate.} ; {Activity date: 11/22/2019; Status: Correction Required; Inspector: RCHANDLER; Comment: Entered by DMERANZ1 - 1-Strap is not installed per approved plans. 2-Per Inspection manger, if window are not less than three feet from property line they can remain; installed window next door is 6’ 1/2" from rough frame of this house window opening. Combustion air openings are 5’ 9-1/2" apart, kitchen hood duct exhaust openings are 5’ 10" apart. Builder declines to obtain survey to determine where the property line is. } ; {Activity date: 11/18/2019; Status: Correction Required; Inspector: RCHANDLER; Comment: Entered by DMERANZ1 - 1-Still need strap at top played. 2-Need revision for firewalls required on both sides.} ; {Activity date: 11/08/2019; Status: Denied; Inspector: DQUINN; Comment: Entered by DMERANZ1 - Missing rsp-4s on south wall studs, top and bottom. Need continuity strap to tie angled roof top plates to blocking below the flat roof top plates. (SD2 #8) detail. Check shear transfer nailing of between truss boxes, from roof and 2nd floor.} |
|
| 12/19/2019 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 12/19/2019; Status: Approved; Inspector: RCHANDLER; Comment: Entered by DMERANZ1 - } | |
| 12/19/2019 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 12/19/2019; Status: Approved; Inspector: RCHANDLER; Comment: Entered by DMERANZ1 - } | |
| 12/19/2019 | COT - LCBU - Framing | Passed | {Activity date: 12/19/2019; Status: Approved; Inspector: RCHANDLER; Comment: Entered by DMERANZ1 - } ; {Activity date: 11/22/2019; Status: Not ready for Inspection; Inspector: RCHANDLER; Comment: Entered by DMERANZ1 - Work incomplete. This should be scheduled when intermediate is ready.} ; {Activity date: 11/18/2019; Status: Correction Required; Inspector: RCHANDLER; Comment: Entered by DMERANZ1 - Need revision for fire wall required on both sides.} | |
| 12/19/2019 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 12/19/2019; Status: Approved; Inspector: RCHANDLER; Comment: Entered by DMERANZ1 - } | |
| 12/19/2019 | COT - RSEL - Electrical Underground | Passed | {Activity date: 12/19/2019; Status: Approved; Inspector: RCHANDLER; Comment: Entered by DMERANZ1 - } | |
| 12/19/2019 | RSME - Mechanical Progress | Passed | {Activity date: 12/19/2019; Status: Approved; Inspector: RCHANDLER; Comment: Entered by DMERANZ1 - } | |
| 12/31/2019 | COT - RSBU - Firewall/Fire Barrier/Firestop | Passed | {Activity date: 12/31/2019; Status: Approved; Inspector: DQUINN; Comment: Entered by DMERANZ1 - } | |
| 01/17/2020 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 01/17/2020; Status: Approved; Inspector: ESTEVENS; Comment: Entered by ESTEVEN1 - IVR} | |
| 03/04/2020 | COT - RSPL - Yard Water Line | Passed | {Activity date: 03/04/2020; Status: Approved; Inspector: RCHANDLER; Comment: Entered by DMERANZ1 - } | |
| 03/09/2020 | COT - RSPL - Sewer | Passed | {Activity date: 03/09/2020; Status: Approved; Inspector: RCHANDLER; Comment: Entered by DMERANZ1 - } | |
| 03/10/2020 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 03/10/2020; Status: Approved; Inspector: RCHANDLER; Comment: Entered by DMERANZ1 - CODE ECO} | |
| 03/10/2020 | COT - RSEL - Construction Power | Passed | {Activity date: 03/10/2020; Status: Approved; Inspector: RCHANDLER; Comment: Entered by DMERANZ1 - Clearance TEP eco} | |
| 03/11/2020 | COT - BULD - SWG Clearance | Passed | {Activity date: 03/11/2020; Status: Approved; Inspector: RCHANDLER; Comment: Entered by SFLORES2 - } | |
| 04/01/2020 | COT - RSPL - Plumbing Final | Passed | {Activity date: 04/01/2020; Status: Approved; Inspector: RCHANDLER; Comment: Entered by SFLORES2 - } | |
| 04/03/2020 | COT - RSME - Mechanical Final | Passed | {Activity date: 04/03/2020; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VFLORES1 - RVI} | |
| 04/03/2020 | RSBU - Building Final | Passed | {Activity date: 04/03/2020; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VFLORES1 - RVI} ; {Activity date: 04/01/2020; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by SFLORES2 - RVI Pending other inspections.} ; {Activity date: 03/11/2020; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by SFLORES2 - Clearance for SW gas only. Ok to connect} |
|
| 04/03/2020 | COT - RSEL - Outdoor Lighting | Passed | {Activity date: 04/03/2020; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VFLORES1 - RVI} | |
| 04/03/2020 | COT - RSPL - Gas Pressure Test | Passed | {Activity date: 04/03/2020; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VFLORES1 - RVI NO CLEARANCE NEEDED} | |
| 04/03/2020 | COT - RSEL - Electrical Final | Passed | {Activity date: 04/03/2020; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VFLORES1 - RVI} ; {Activity date: 04/01/2020; Status: Correction Required; Inspector: RCHANDLER; Comment: Entered by SFLORES2 - RVI Lights at stairway are not working. } |