Permit: T19CM05054
Permit Details
Apply Date:
07/16/2019
Applicant:
FRANK ANZALDUA
Description:
PARKING SHADE CANOPY MOUNTED PV SYSTEM
Contractors:
- SOLON CORPORATION ***APA***
Permit Reviews
Permit Number - T19CM05054
Permit Status: L of c
Permit Description: PARKING SHADE CANOPY MOUNTED PV SYSTEM
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/16/2019 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 07/16/2019 | COMPLETED |
| 07/16/2019 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 07/26/2019 | COMPLETED |
| 07/26/2019 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 09/10/2019 | COMPLETED |
| 09/10/2019 | RESUBMITTAL | 09/10/2019 | COMPLETED |
Completed Inspections
Permit Status: L of c
Permit Number: T19CM05054
Permit Description: PARKING SHADE CANOPY MOUNTED PV SYSTEM
Total Completed Inspections - 11
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/03/2019 | EXCAVATION/LAYOUT REBAR & ZON | TVALENCIA | Approved | |
| 10/05/2019 | ELECTRIC - RECONNECT | DMUNIZ | Approved | Verbal Clearance sent to TEP @ 10:15AM (RECN). Check for $165 received upon arrival for after hours inspection. |
| 10/15/2019 | FRAMING | TVALENCIA | Approved | |
| 10/16/2019 | ELECTRIC - UNDERGROUND | TVALENCIA | Approved | |
| 10/18/2019 | ELECTRIC - UFER | TVALENCIA | Approved | |
| 10/18/2019 | ELECTRIC - INTERMEDIATE | TVALENCIA | Approved | |
| 10/29/2019 | BUILDING - FINAL | DQUINN | Approved | |
| 10/29/2019 | TEP CLEARANCE - PM | DQUINN | Approved | #8 CODE DGC |
| 10/29/2019 | ELECTRIC - FINAL | DQUINN | Approved | Building 8 canopies ok Clear dgc |
| 10/29/2019 | OUTDOOR LIGHTING FINAL | DQUINN | Approved | |
| 10/29/2019 | ELECTRIC - OUTDOOR LIGHTING | DQUINN | Approved |