Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
C of o
Type:
COMMERCIAL NEW
Address:
3738 W RIVER RD
Address NEW:
3738 W RIVER RD
Apply Date:
07/01/2019
Applicant:
N/A
Description:
NEW BLDG RETAIL
Contractors:
  • EPSTEIN CONSTRUCTION L L C

Permit Reviews

Permit Number - T19CM04691
Permit Status: C of o
Permit Description: NEW BLDG RETAIL
Start Date Submittal Complete Date Status  
01/02/2020 REVISION - - 3RD 01/07/2020 COMPLETED Review Details
01/31/2020 REVISION - - 4TH 02/03/2020 COMPLETED Review Details
07/01/2019 COMMERCIAL - NEW 07/01/2019 COMPLETED Review Details
07/01/2019 COMMERCIAL - NEW 08/12/2019 COMPLETED Review Details
08/12/2019 RESUBMITTAL 08/13/2019 COMPLETED Review Details
08/13/2019 COMMERCIAL - NEW 08/15/2019 COMPLETED Review Details
11/15/2019 REVISION - - 1ST 11/15/2019 COMPLETED Review Details
12/12/2019 REVISION - - 2ND 12/12/2019 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T19CM04691
Permit Status: C of o
Permit Description: NEW BLDG RETAIL
Total Outstanding Activity Conditions - 1
Date Name
07/01/2019 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T19CM04691
Permit Description: NEW BLDG RETAIL
Total Completed Inspections - 37
Date Description Inspector Results Comments
08/14/2019 MECHANICAL - FINAL RSHERRY Approved AIR BALANCE REPORT REQUIRED
08/14/2019 PLUMBING - FINAL RSHERRY Approved WATER DISINFECTION REPORT REQUIRED
10/03/2019 ELECTRIC - UFER DQUINN Approved
10/08/2019 STEM WALL/RETAINING WALL RCHANDLER Approved Stemwall.
11/07/2019 EXCAVATION/LAYOUT REBAR & ZON DQUINN Approved All entry and column footings ok to pour pending staking clarification of the templates.
11/26/2019 REINFORCED MASONRY PRE-GROUT JCLAXTON Approved Top out on west wall
01/10/2020 PLUMBING - SEWER HCS CONNECT DQUINN Approved
01/10/2020 PLUMBING - YARD WTR LINE/TEST DQUINN Approved Ok from meter to 10’ inside building.
01/10/2020 PLUMBING - ROUGH, SOIL DQUINN Approved
02/14/2020 ELECTRIC - SERVICE UPGRADE DQUINN Approved RVI
02/18/2020 TEP CLEARANCE - AM DQUINN Approved CODE ECO/INCR
03/10/2020 PLUMBING - INTERMEDIATE DQUINN Approved
03/24/2020 GAS CLEARANCE DMUNIZ Approved
03/24/2020 PLUMBING - GAS PRESSURE TEST DMUNIZ Approved Clear Southwest Gas
04/07/2020 MECHANICAL - ABOVE CEILING DQUINN Approved PARTIALS ARE FOR WEST ENTRY, 2 BATHS, BREAK ROOM, FRAME ROOM, CASH ROOM AND OFFICE - OK TO DROP LID
04/07/2020 PLUMBING - ABOVE CEILING DQUINN Approved PARTIALS ARE FOR WEST ENTRY, 2 BATHS, BREAK ROOM, FRAME ROOM, CASH ROOM AND OFFICE - OK TO DROP LID
05/11/2020 MECHANICAL - INTERMEDIATE JBURGE Approved
05/11/2020 PLUMBING - ROOF DRAINS JBURGE Approved
05/11/2020 ELECTRIC - ABOVE CEILING JBURGE Approved
05/11/2020 ELECTRIC - INTERMEDIATE JBURGE Approved
05/11/2020 ELECTRIC - UNDERGROUND JBURGE Approved
05/11/2020 SHEET ROCK NAILING JBURGE Approved
05/11/2020 FIREWALL/FIREBARRIER/FIRESTOP JBURGE Approved
05/11/2020 U VALUE FOR WINDOW JBURGE Approved
05/11/2020 BUILDING ABOVE CEILING JBURGE Approved
05/11/2020 FRAMING JBURGE Approved
05/11/2020 ROOF NAILING JBURGE Approved
05/11/2020 EXT METAL CLIPS/EXT SHEATHING JBURGE Approved
05/11/2020 BUILDING PRE-SLAB JBURGE Approved
05/19/2020 FIRE - ALARM FINAL CBASALDUA Approved
05/19/2020 FIRE SPKLR - FINAL CBASALDUA Approved
05/20/2020 CERTIFICATE OF OCCUPANCY ESTEVENS Approved Partial. Pending other inspections.
05/20/2020 ELECTRIC - OUTDOOR LIGHTING ESTEVENS Approved
05/20/2020 ELECTRIC - FINAL ESTEVENS Approved
05/26/2020 BUILDING - FINAL CTREVIL Approved
05/26/2020 ENGINEERING - FINAL CTREVIL Approved
07/01/2020 FIRE - FINAL JPEELDAVIS Approved FIRE ALARM MONITORING PERMIT REQUIRED PRIOR TO A COFO BEING ISSUED.