Permit: T19CM04509
Permit Details
Apply Date:
06/25/2019
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
NEW SURF THRU CAR WASH
Contractors:
- KDC CONSTRUCTION
Permit Reviews
Permit Number - T19CM04509
Permit Status: C of o
Permit Description: NEW SURF THRU CAR WASH
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/31/2020 | COMMERCIAL - NEW | 02/27/2020 | COMPLETED |
02/27/2020 | RESUBMITTAL | 03/11/2020 | COMPLETED |
03/11/2020 | RESUBMITTAL | 04/11/2020 | COMPLETED |
05/13/2020 | REVISION - - 1ST | 06/23/2020 | COMPLETED |
06/25/2019 | PLANS OK TO SUBMIT - COMM | 06/25/2019 | COMPLETED |
06/25/2019 | COMMERCIAL - NEW | 11/07/2019 | COMPLETED |
11/07/2019 | COMMERCIAL - NEW | 01/31/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM04509
Permit Status: C of o
Permit Description: NEW SURF THRU CAR WASH
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
06/25/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T19CM04509
Permit Description: NEW SURF THRU CAR WASH
Total Completed Inspections - 44
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/15/2020 | PLUMBING - SEWER HCS CONNECT | WGALLAGHER | Approved | |
04/20/2020 | ELECTRIC - UFER | TTREMBULAK | Approved | RVI |
05/19/2020 | ROOF NAILING | DMUNIZ | Approved | |
05/19/2020 | EXT METAL CLIPS/EXT SHEATHING | DMUNIZ | Approved | |
06/03/2020 | STEM WALL/RETAINING WALL | DMUNIZ | Approved | |
06/11/2020 | FRAMING | WGALLAGHER | Approved | |
06/18/2020 | BUILDING PRE-SLAB | WGALLAGHER | Approved | Approved |
06/18/2020 | EXCAVATION/LAYOUT REBAR & ZON | WGALLAGHER | Approved | Approved |
07/14/2020 | REINFORCED MASONRY PRE-GROUT | WGALLAGHER | Approved | Approved |
07/27/2020 | SITE - SEWER | DMUNIZ | Approved | Approved |
08/17/2020 | ELECTRIC - OUTDOOR LIGHTING | DMUNIZ | Approved | Approved, 7 Caissons and Uffer for Exterior lights poles ok for concrete encasement. |
08/19/2020 | PLUMBING - ROOF DRAINS | TTREMBULAK | Approved | Approved |
08/19/2020 | PLUMBING - YARD WTR LINE/TEST | TTREMBULAK | Approved | Approved |
08/19/2020 | PLUMBING - INTERMEDIATE | TTREMBULAK | Approved | Approved |
08/25/2020 | U VALUE FOR WINDOW | WGALLAGHER | Approved | Approved |
08/25/2020 | MECHANICAL - INTERMEDIATE | WGALLAGHER | Approved | Approved pay station |
09/08/2020 | STUCCO MESH | TTREMBULAK | Approved | Approved |
11/17/2020 | TEP CLEARANCE - AM | WGALLAGHER | Approved | CODE ECO |
12/01/2020 | ELECTRIC - FINAL | WGALLGHER | Approved | Partial approval see 2035 |
12/01/2020 | FIRE SPKLR - FINAL | jfordney | Approved | |
12/02/2020 | ELECTRIC - UNDERGROUND | WGALLAGHER | Approved | |
12/02/2020 | PLUMBING - ROUGH, SOIL | WGALLAGHER | Approved | |
12/02/2020 | ELECTRIC - TEMPORARY SERVICE | WGALLAGHER | Approved | Not a required inspection |
12/02/2020 | ELECTRIC - CONSTRUCTION POWER | WGALLAGHER | Approved | Not a required inspection |
12/03/2020 | ENGINEERING - FINAL | DROBERTS | Approved | |
12/03/2020 | PLUMBING - FINAL | WGALLAGHER | Approved | |
12/03/2020 | ELECTRIC - INTERMEDIATE | WGALLAGHER | Approved | |
12/03/2020 | SHEET ROCK NAILING | WGALLAGHER | Approved | |
12/03/2020 | FIREWALL/FIREBARRIER/FIRESTOP | WGALLAGHER | Approved | Not a required inspection |
12/03/2020 | BUILDING ABOVE CEILING | WGALLAGHER | Approved | |
12/03/2020 | PLUMBING - FINAL | WGALLAGHER | Approved | |
12/03/2020 | ELECTRIC - ABOVE CEILING | WGALLAGHER | Approved | |
12/03/2020 | SHEET ROCK NAILING | WGALLAGHER | Approved | |
12/03/2020 | FIREWALL/FIREBARRIER/FIRESTOP | WGALLAGHER | Approved | Not a required inspection |
12/03/2020 | BUILDING ABOVE CEILING | WGALLAGHER | Approved | |
12/03/2020 | FIRE - FINAL | jvincent | Approved | |
12/03/2020 | FIRE - ALARM FINAL | jvincent | Approved | |
12/03/2020 | ENGINEERING - FINAL | DROBERTS | Approved | PARTIAL, OK FOR A TCO BUT NOT FOR THE FINAL |
12/03/2020 | PLUMBING - FINAL | RSHERRY | Approved | REVIEW OF WATER DISINFECTION REPORT COMPLETE |
12/08/2020 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETED |
12/11/2020 | CERTIFICATE OF OCCUPANCY | JG3 | Approved | |
12/11/2020 | BUILDING - FINAL | JG3 | Approved | |
12/11/2020 | OUTDOOR LIGHTING FINAL | WGALLAGHER | Approved | |
12/11/2020 | BUILDING - FINAL | WGALLAGHER | Approved | Partial approval recommend for C/O |